SAB11#55_ESTIMATE_ACTIVITIES DURATIONS

Description

Mind Map on SAB11#55_ESTIMATE_ACTIVITIES DURATIONS, created by oscar_arguetap on 25/06/2016.
oscar_arguetap
Mind Map by oscar_arguetap, updated more than 1 year ago
oscar_arguetap
Created by oscar_arguetap almost 8 years ago
12
0

Resource summary

SAB11#55_ESTIMATE_ACTIVITIES DURATIONS
  1. ESTIMATE ACTIVITY DURATIONS IS THE PROCESS OF ESTIMATING THE NUMBER OF WORK PERIODS NEEDED TO COMPLETE INDIVIDUAL ACTIVITIES WITH ESTIMATED RESOURCES
    1. ROLE OF THE PROJECT MANAGER IN ESTIMATING IS TO:
      1. 1. PROVIDE THE TEAM WITH ENOUGH INFORMATION TO PROPERLY ESTIMATE EACH ACTIVITY
        1. 2. LET THOSE DOING THE ESTIMATING KNOW HOW REFINED THEIR ESTIMATES MUST BE
          1. 3. COMPLETE A SANITY CHECK OF THE ESTIMATES
            1. 4. PREVENT PADDING.PADDING IS EXTRA TIME OR COST ADDED TO AN ESTIMATE BECAUSE THE ESTIMATOR DOES NOT HAVE ENOUGH INFORMATION
              1. 5. FORMULATE A RESERVE
                1. 6. MAKE ASSURE ASSUMPTIONS MADE DURING ETIMATING ARE RECORDED FOR LATER REVIEW
              2. 1. SHEDULE MANAGEMENT PLAN
                1. 2. ACTIVITY LIST
                  1. 3. ACTIVITY ATRIBUTESS
                    1. 4.ACTIVITY RESOURCES REQUIREMENTS
                      1. 5. RESOURCES CALENDARS
                        1. 6. PROJECT SCOPE STAMENTS
                          1. 7. RISK REGISTER
                            1. 8.RESOURCES BREAKDOWN
                              1. 9. ENTERRPRISE ENVIRONMENTAL FACTORS
                                1. 10. ORGANIZATIONAL PROCESS ASSETS
                                  1. 1. EXPERT JUDGMENTS. GUIDED BY HISTORICAL INFORMATION FROM SIMILAR PROJECTS
                                    1. 2. ANALOGOUS ESTIMATING. TO ESTIMATE COST OF AN ACTIVITY OF A PROJECT OF HISTORICAL DATA. USED WHEN THERE IS LIMITED INFORMATION. GENERALLY NOT AS ACCURATE AS OTHER ESTIMATING TECHIQUES
                                      1. 4. THREE POINT ESTIMATING. TRIANGULAR DISTRIBUTION AVERAGE (P+O+M)/3 P=PESSIMISTIC, O=OPTIMISTIC,M=MAS PROBABLE. TRIANGULAR DISTRIBUTION BETA (P+4M+O)/6 BETA ACTIVITY STANDARD DEVIATION =P-O/6
                                        1. 3.PARAMETRIC ESTIMATING. HISTORICAL RECORDS FROM PREVIOUS PROJECTS. USES AN STATISTICAL RELATIONSHIP BETWEEN HISTORICAL DATA AND OTHER VARIABLES
                                          1. 5. GROUP DECISION-MAKING TECNIQUES. USES BRAINSTORMING, AND DELPHI.
                                            1. 6. RESERVE ANALYSIS . TIMES RESERVES IN THE GLOBAL SCHEDULE F THE PROJECT.
                                              1. 1. ACTIVITY DURATION ESTIMATES
                                                1. 2. PROJECT DOCUMENTS UPDATES
                                                  Show full summary Hide full summary

                                                  Similar

                                                  Social Influence
                                                  smita089
                                                  Atoms and Reactions
                                                  siobhan.quirk
                                                  Criminal Law
                                                  jesusreyes88
                                                  Application of technology in learning
                                                  Jeff Wall
                                                  Biology Unit 2 - DNA, meiosis, mitosis, cell cycle
                                                  DauntlessAlpha
                                                  Maths Revision
                                                  Asmaa Ali
                                                  Revision Timetable
                                                  katy.lay
                                                  Prep Like a Pro with GoConqr's Revision Timetable
                                                  Mike Nervo
                                                  New GCSE Maths required formulae
                                                  Sarah Egan
                                                  Procedimientos Operacionales
                                                  Adriana Forero
                                                  PSBD/PSCOD/ASSD-New
                                                  Yuvraj Sunar