1Planning meetings and analysis are used in which process?
- AManage Stakeholder Expectations.
- BPerform Quantitative Risk Analysis
- CPlan Risk Responses
- DPlan Risk Management.
2Which of the following would NOT be contained in the risk management plan?
- AA risk breakdown structure.
- BA description of the overall approach to risk on the project.
- CRisk roles and responsibilities.
- DA list of identified risk.