Foundations of Project Management EXAM (1-6)

Descripción

Lecture 1-6 Review
Leah D'Souza
Test por Leah D'Souza, actualizado hace más de 1 año
Leah D'Souza
Creado por Leah D'Souza hace alrededor de 4 años
5
0

Resumen del Recurso

Pregunta 1

Pregunta
Even though a company might work on similar projects over and over again, such as building houses, providing training courses or developing specific types of products, there are unique challenges because all projects involve _________
Respuesta
  • Progressive elaboration
  • People
  • Uncertainty
  • Competition

Pregunta 2

Pregunta
Which of following is a difference between projects and operations?
Respuesta
  • Operations have well defined objectives whereas projects do not need to have a unique purpose
  • Operations are undertaken to create unique products, services or results whereas projects are not
  • Projects are temporary endevours, whereas an organization's operations are ongoing in nature
  • Projects are undertaken to sustain an organization's business whereas operations are not

Pregunta 3

Pregunta
In which of the five project management process groups is the most time and money usually spent?
Respuesta
  • Initiating
  • Planning
  • Execution
  • Monitoring and controlling

Pregunta 4

Pregunta
Project Management is compromised of ________________,______________________ and _____________________
Respuesta
  • A set of skills .... an information system.... a methodology
  • Knowledge..... applications... processes
  • A set of skills.... a suite of tools... a series of processes
  • A set of tools...a methodology.... a team

Pregunta 5

Pregunta
Managers__________ while leaders _____________.
Respuesta
  • Maintain ... develop
  • administrate... focus on people
  • do paperwork .... innovate
  • do things right ..... constrain

Pregunta 6

Pregunta
Main goal for a Project Portfolio is to _______________
Respuesta
  • balance project budgets
  • do the right project at the right time
  • assign resources to projects
  • Execute projects

Pregunta 7

Pregunta
The balanced scorecard that focuses on the organization as being a great place to work is called?
Respuesta
  • Process
  • People and learning
  • Customers
  • Financial stewardship

Pregunta 8

Pregunta
One of the typical goals for a PMO is __________
Respuesta
  • Balance project budget
  • execute projects
  • optimize resources utilization
  • develop project methodologies

Pregunta 9

Pregunta
You are reviewing 4 project. Based on the NPV, which project would be the best choice?
Respuesta
  • Project C, C
Mostrar resumen completo Ocultar resumen completo

Similar

5 Steps to Learning Success
Andrea Leyden
Interactive Multimodal Learning Environments
kaylamclaughlin8
Innovative Uses of Technology
John Marttila
Sociology: Education
Siobhan Lee
Inclusive Education: Background and Theory
Maisie Rose Woodward
Bullying: Background
Maisie Rose Woodward
Bullying: Theories
Maisie Rose Woodward
4 Lesson Planning Tips for Teachers
Micheal Heffernan
Teaching Using GoConqr's Tools
Micheal Heffernan
Using GoConqr to teach French
Sarah Egan
Using GoConqr to teach Maths
Sarah Egan