Test
Intake9 BIM L4C BEP
Preguntas del test (5)
1Who authors the BIM Execution Plan?
- AThe BIM Manager
- BThe Employer
- CThe Principal Consultant
- DThe BIM Coordinator
2When should the BIM Execution Plan be authored and signed off?
- AWhen Documentation phase starts
- BBefore Design begins
- CBefore Construction begins
- DWhen project handed over to employer for Facilities Management
3The BIM Execution Plan should include:
- AProject Goals
- BBIM Deliverables
- CProcess for BIM
- DAll of the above
4Hardware and Software requirements should be included in the BIM Execution Plan
- AVerdadero
- BFalso
5The "BIM Use Case Template" in Appendix A is identical to the SIngapore BIM Guide Appendix B "Objectives and Responsibilities Matrix"
- AVerdadero
- BFalso
Información
- Descripción
- Test sobre Intake9 BIM L4C BEP, creado por Stanley Chia el 09/03/2016.
- Autor
- Stanley Chia
- Idioma
- English
- Visitas
- 446
- Valoración
- 4,0 de 5 · 1 valoración Valora este test