048_Validate_scope

Contenido del mapa
048_Validate_scope
- The Validate Scope process actually involves frequent, planned meetings with the customer or sponsor to gain formal acceptance of deliverables during project monitoring and controlling.
Requirements documentation
Traceability matrix
Deliverables
- These are verified deliverables, which means they’ve been through Perform Quality Control.
Work performance data
- As per the PMBOK Guide, the work performance data is “the raw observations and measurements identified during activities performed to carry out the project work; e.g. actual cost, actual duration, and percent of work physically completed.”
Group decisionmaking techniques
- Once the stakeholders have inspected the deliverables, they’ll need to decide whether or not the deliverables can be accepted
- This is where the stakeholders actually look closely at the what the team did and make sure that every single piece of work was completed.
Verified deliverables
- If the team did the work right, then the stakeholders will formally accept the deliverables (which means they do it in writing).
Change requests
Project document updates
Work performance information
- As per the PMBOK Guide, the work performance information is “the performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas; e.g. status of deliverables, and forecasted estimates to complete, etc.”
Relationship between validate scope and control quality
Imágenes y archivos del mapa
Información
- Descripción
- PMP Credential Taller PMP Mapa Mental sobre 048_Validate_scope, creado por Alejandro Becerra el 27/02/2016.
- Creado por
- Alejandro Becerra
- Visitas
- 2
- Historial
-
- Creado por edith.labastida. · 27 feb 2016
- Copiado por Alejandro Becerra · 27 feb 2016
- Valoración