PRACTICE STANDARD FOR EARNEDVALUE MANAGEMENT

canet milla saenz Español

Contenido del mapa

PRACTICE STANDARD FOR EARNEDVALUE MANAGEMENT

  1. CHAPTER 1. INTRODUCTION

    • Has been developed as a supplement to A Guide to the Project Management Body of Knowledge
    • Is a document that describes established norms, methods, processes, and practices
    • Is designed to provide readers who are familiar with the fundamental practices of project management
    • Purpose of this Practice Standard
      • Identifi es a subset of project management practices that are used for earned value management.
      • Promotes a common vocabulary
    • Relationship to the PMBOK ® Guide
      • The Practice Standard for Earned Value Management
        • Focuses on the effective integration of those project management practices that are used for earned value management.
      • The PMBOK® Guide
        • Identifi es a set of internal and external environmental factors.
        • Have a positive or negative infl uence on the outcomes
          • Organizational culture, structure, and processes
          • Government or industry standards
          • Infrastructure
          • Company work authorization systems
          • Project management information systems
        • There are two main categories
          • Processes and procedures
          • The corporate knowledge base
        • The following is an abbreviated lis
          • Processes and procedures
          • Standard project life cycles
          • Policies
          • Templates
          • Financial control procedures
          • Change control procedures
          • Work authorization procedures
          • Corporate knowledge base
          • Project fi les
          • Lessons learned
          • Historical information from past projects
          • Estimating information from past projects
    • Assumptions
      • Additional assumptions include
        • The organization has the corporate policies and procedures to support EVM.
        • The organization has the integrated information systems necessary to implement EVM.
        • The project management team has the knowledge and skills needed to plan, execute, and control projects using EVM.
        • Project team members and other stakeholders have suffi cient training and understanding of EVM concepts to plan their work accordingly.
    • Structure of the Practice Standard
      • Introduction.
        • Introduces the concept that will be described in the chapter. Includes a graphic with inputs and outputs.
      • Inputs.
        • Identifi es the documents necessary to conduct the process.
      • Description.
        • Describes the methods, tools, and techniques used to conduct the process.
      • Outputs.
        • . Identifi es the documents or outcomes that are a result of the process.
      • Considerations.
        • Discusses variables and perspectives that an EVM practitioner needs to keep in mind when implementing the process.
      • Summary
        • Summarizes the information in the chapter.
  2. CHAPTER 2:EARNED VALUE PROJECT MANAGEMENT OVERVIEW

    • Introduction
      • Developed as a supplement
      • Provide a standard for project management practitioners and other stakeholders
      • Provide a reference for the basic concepts and applications of earned value management
    • EVM and the Project Management Process
      • Is consistent with good project management as outlined in A Guide to the Project Management Body of Knowledge
      • Project planning is mostly a matter of determining:
        • What work must be done (scope) and in what pieces (work breakdown structure
        • Who is going to perform and manage the work (responsibility assignment matrix)
        • When the work will be done (schedule).
        • The cost and quantity of the labor, material, and related resources the work will require.
    • Basic EVM Terminology
      • Actual Cost (AC
        • The realized cost incurred for the work performed on an activity during a specifi c time period.
      • Budget at Completion (BAC).
        • The sum of all the budgets established for the work to be performed on a project.
      • Contingency Reserve.
        • Budget within the performance management baseline that is allocated for identifi ed risks
      • Control Account
        • A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value
      • Distributed Budget.
        • The budget for project scope that has been identifi ed to work breakdown structure
      • Earned Value (EV).
        • The measure of the work performed, expressed in terms of the budget authorized for that work
      • Estimate at Completion (EAC).
        • The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete
      • Estimate To Complete (ETC).
        • The estimated cost to fi nish all the remaining work
      • Management Reserve (MR).
        • An amount of the project budget base (PBB) withheld for management control purposes.
      • Performance Measurement Baseline (PMB).
        • . An approved integrated scope-schedule-cost plan
      • Planned Value (PV).
        • The authorized budget assigned to scheduled work as of a given reporting date
      • Planning Package.
        • The estimated cost to fi nish all the remaining work. Adding the ETC to the actual cost
      • Project Budget Base (PBB).
        • The starting point upon which original budgets are built.
      • Summary Level Planning Budget (SLPB).
        • A time-phased budget for future work that cannot be reasonably planned down to control accounts.
      • Undistributed Budget (UB).
        • The budget for project scope that has not yet been identifi ed to WBS
      • Work Package.
        • The work defi ned at the lowest level of the work breakdown structure
      • Work Breakdown Structure (WBS).
        • is a hierarchical decomposition of the total scope of the work to be carried out
      • Work Breakdown Structure Dictionary
        • A document that provides detailed deliverable, activity, and scheduling information
    • Basic EVM Concepts
      • Defi ne product and project scope and decompose work to a manageable level.
      • Assign clear management responsibility for discrete work elements.
      • Plan the activities of the project into a logical schedule.
      • Develop a time-phased budget for each element of the WBS.
      • Select EV measurement techniques for each work package prior to execution.
      • Establish a performance measurement baseline based on the previous fi ve steps.
      • Develop a structure for collecting costs into the same accounts and time periods where performance is being measured.
      • Determine earned value by objectively measuring the physical work progress according to the earned value technique selected for the work.
      • Analyze cost/schedule performance.
      • . Forecast cost /schedule performance.
      • Project the estimates at completion.
      • Report performance problems and take appropriate corrective action.
      • Maintain integrity of the PMB
    • Considerations
      • This practice standard may be applicable to smaller scale projects as well

Información

Descripción
Mapa Mental sobre PRACTICE STANDARD FOR EARNEDVALUE MANAGEMENT, creado por canet milla saenz el 19/09/2017.