Tiffany Brown
Test por , creado hace más de 1 año

Test sobre Kaplan - CDs 2009 [Conditions of the Contract for Construction] Chapter Quiz Questions , creado por Tiffany Brown el 27/06/2016.

10
0
0
Tiffany Brown
Creado por Tiffany Brown hace casi 8 años
Cerrar

Kaplan - CDs 2009 [Conditions of the Contract for Construction] Chapter Quiz Questions

Pregunta 1 de 15

1

According to AIA documents, which of the following are NOT considered a part of the construction contract documents?

I. Specifications
II. Addenda
III. Shop Dwgs
IV. Owner-Architect Agreement
V. Supplementary Conditions

Selecciona una de las siguientes respuestas posibles:

  • A. IV only

  • B. II and III

  • C. I and V

  • D. III and IV

Explicación

Pregunta 2 de 15

1

Rellena el espacio en blanco para completar el texto.

A assures an owner that the contractor will execute the work in accordance with the contract.

Explicación

Pregunta 3 de 15

1

During the course of construction, liability insurance should be maintained by which of the following?

I. The mortgagee
II. Trade unions
III. The surety company
IV. The owner
V. The contractor

Selecciona una de las siguientes respuestas posibles:

  • A. IV only

  • B. I and V

  • C. IV and V

  • D. II and III

Explicación

Pregunta 4 de 15

1

Where would provisions for liquidated damages be found?

Selecciona una de las siguientes respuestas posibles:

  • A. Owner-Contractor Agreement

  • B. General Conditions of the Contract for Construction

  • C. Additive Alternates to the Contract

  • D. Proposal For and Instructions to Bidders

Explicación

Pregunta 5 de 15

1

A change during construction in the location of underground lines from that shown on the site utilities plan should be reflected in

Selecciona una de las siguientes respuestas posibles:

  • A. record drawings.

  • B. architectural drawings.

  • C. field sketches.

  • D. shop drawings.

Explicación

Pregunta 6 de 15

1

Architects are responsible for preparing which parts of a Project Manual?

I. Specifications
II. General Conditions
III. Supplementary Conditions
IV. Owner-Contractor Agreement

Selecciona una de las siguientes respuestas posibles:

  • A. I only

  • B. I and III

  • C. II and III

  • D. I, II, III, and IV

Explicación

Pregunta 7 de 15

1

Which of the following are responsibilities of the owner under the provisions of the AIA General Conditions (remember to answer per the A201 as stated in the question, not your own experience.)?

I. Provide access to the construction site.
II. Make payment to the contractor.
III. Make payments to the subcontractors.
IV. Obtain necessary easements.
V. Provide necessary copies of the construction documents.

Selecciona una de las siguientes respuestas posibles:

  • A. II only

  • B. II and III

  • C. I and IV

  • D. II, IV, and V

Explicación

Pregunta 8 de 15

1

Which of these statements is true? Contract time

Selecciona una de las siguientes respuestas posibles:

  • A. is measured in working days.

  • B. ends at substantial completion.

  • C. The general warranty period is one year.

  • D. Warranties are worthless without bonds to back them up.

Explicación

Pregunta 9 de 15

1

Under the conditions of the A201 General Conditions, which of the following statements is true?

Selecciona una de las siguientes respuestas posibles:

  • A. Warranty periods begin at substantial completion.

  • B. Warranty periods begin at final completion.

  • C. The general warranty period is one year.

  • D. Warranties are worthless without bonds to back them up.

Explicación

Pregunta 10 de 15

1

An architect issues certificates for payment for work performed by the contractor. For what reasons might an architect legitimately nullify all or party of a previously issued certificate for payment?

I. The architect discovers defective work.
II. The owner's lender refuses to release funds.
III. The contractor fails to pay subcontractors.
IV. A pedestrian walking past the project site is injured by a falling piece of lumber and sues the owner.
V. The contractor persistently fails to comply with the contract documents.

Selecciona una de las siguientes respuestas posibles:

  • A. I, II, III, IV, and V

  • B. I only

  • C. I, III, IV, and IV

  • D. III and V

Explicación

Pregunta 11 de 15

1

Which of the following statements concerning payments to a contractor is FALSE?

Selecciona una de las siguientes respuestas posibles:

  • A. Payments are based on a schedule of values.

  • B. Title to materials and equipment passes to the owner upon payment.

  • C. The owner must pay the contractor within 21 days after the architect issues the certificate for payment.

  • D. Payments do not normally cover materials in transit.

Explicación

Pregunta 12 de 15

1

Which of the following parties are responsible for workers' safety on a construction site?

I. The owner
II. The architect
III. The general contractor
IV. The contractor's surety company

Selecciona una de las siguientes respuestas posibles:

  • A. III only

  • B. I only

  • C. I, II, and III

  • D. I, II, III, and IV

Explicación

Pregunta 13 de 15

1

An architect, under the provisions of the AIA documents, inspects a project how often during the construction phase?

Selecciona una de las siguientes respuestas posibles:

  • A. Never. The architect *observes* construction.

  • B. At intervals appropriate to the progress of the construction work.

  • C. Once, at final completion.

  • D. Twice, at substantial completion and at final completion.

Explicación

Pregunta 14 de 15

1

Which of the following is NOT a prerequisite for final payment to the contractor?

Selecciona una de las siguientes respuestas posibles:

  • A. Final inspection by the architect.

  • B. Owner's receipt of the certificate of final completion from the architect.

  • C. Owner's receipt of the contractors affidavit or payment of debts.

  • D. Owner's receipt of consent of the contractor's surety company.

Explicación

Pregunta 15 de 15

1

Which of the following parties must *approve* shop drawings according to the AIA General Conditions? Check all that apply.

Selecciona una o más de las siguientes respuestas posibles:

  • A. Architect

  • B. Contractor

  • C. Owner

  • D. Engineers

  • E. Subcontractors

Explicación