  1. 1According to AIA documents, which of the following are NOT considered a part of the construction contract documents?

    I. Specifications
    II. Addenda
    III. Shop Dwgs
    IV. Owner-Architect Agreement
    V. Supplementary Conditions
    1. AA. IV only
    2. BB. II and III
    3. CC. I and V
    4. DD. III and IV
  2. 2A [blank_start]performance bond[blank_end] assures an owner that the contractor will execute the work in accordance with the contract.
    1. Aperformance bond
  3. 3During the course of construction, liability insurance should be maintained by which of the following?

    I. The mortgagee
    II. Trade unions
    III. The surety company
    IV. The owner
    V. The contractor
    1. AA. IV only
    2. BB. I and V
    3. CC. IV and V
    4. DD. II and III
  4. 4Where would provisions for liquidated damages be found?
    1. AA. Owner-Contractor Agreement
    2. BB. General Conditions of the Contract for Construction
    3. CC. Additive Alternates to the Contract
    4. DD. Proposal For and Instructions to Bidders
  5. 5A change during construction in the location of underground lines from that shown on the site utilities plan should be reflected in
    1. AA. record drawings.
    2. BB. architectural drawings.
    3. CC. field sketches.
    4. DD. shop drawings.
  6. 6Architects are responsible for preparing which parts of a Project Manual?

    I. Specifications
    II. General Conditions
    III. Supplementary Conditions
    IV. Owner-Contractor Agreement
    1. AA. I only
    2. BB. I and III
    3. CC. II and III
    4. DD. I, II, III, and IV
  7. 7Which of the following are responsibilities of the owner under the provisions of the AIA General Conditions (remember to answer per the A201 as stated in the question, not your own experience.)?

    I. Provide access to the construction site.
    II. Make payment to the contractor.
    III. Make payments to the subcontractors.
    IV. Obtain necessary easements.
    V. Provide necessary copies of the construction documents.
    1. AA. II only
    2. BB. II and III
    3. CC. I and IV
    4. DD. II, IV, and V
  8. 8Which of these statements is true? Contract time
    1. AA. is measured in working days.
    2. BB. ends at substantial completion.
    3. CC. The general warranty period is one year.
    4. DD. Warranties are worthless without bonds to back them up.
  9. 9Under the conditions of the A201 General Conditions, which of the following statements is true?
    1. AA. Warranty periods begin at substantial completion.
    2. BB. Warranty periods begin at final completion.
    3. CC. The general warranty period is one year.
    4. DD. Warranties are worthless without bonds to back them up.
  10. 10An architect issues certificates for payment for work performed by the contractor. For what reasons might an architect legitimately nullify all or party of a previously issued certificate for payment?

    I. The architect discovers defective work.
    II. The owner's lender refuses to release funds.
    III. The contractor fails to pay subcontractors.
    IV. A pedestrian walking past the project site is injured by a falling piece of lumber and sues the owner.
    V. The contractor persistently fails to comply with the contract documents.
    1. AA. I, II, III, IV, and V
    2. BB. I only
    3. CC. I, III, IV, and IV
    4. DD. III and V

Information

Description
Quiz on Kaplan - CDs 2009 [Conditions of the Contract for Construction] Chapter Quiz Questions , created by Tiffany Brown on 27/06/2016.
Language
English
Views
52
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?