  1. 1The term ____ describes a product produced as part of a project.

    1. Aa. end-product
    2. Bb. scope
    3. Cc. deliverable
    4. Dd. outcome
  2. 2There are ____ main processes involved in project scope management.


    1. Aa. three
    2. Bb. four
    3. Cc. five
    4. Dd. six
  3. 3____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them.




    1. Aa. Collecting requirements
    2. Bb. Defining scope
    3. Cc. Controlling scope
    4. Dd. Verifying scope
  4. 4____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.



    1. Aa. Planning scope
    2. Bb. Defining scope
    3. Cc. Controlling scope
    4. Dd. Verifying scope
  5. 5____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables during this process.


    1. Aa. Planning scope
    2. Bb. Defining scope
    3. Cc. Controlling scope
    4. Dd. Verifying scope
  6. 6The main outputs of ____ are accepted deliverables and change requests.




    1. Aa. planning scope
    2. Bb. controlling scope
    3. Cc. defining scope
    4. Dd. verifying scope
  7. 7____ involves controlling changes to project scope throughout the life of the project, which is a challenge on many information technology projects.

    1. Aa. Planning scope
    2. Bb. Defining scope
    3. Cc. Controlling scope
    4. Dd. Verifying scope
  8. 8Good ____ is very important to project success because it helps improve the accuracy of time, cost, and resource estimates, it defines a baseline for performance measurement and project control, and it aids in communicating clear work responsibilities.



    1. Aa. scope planning
    2. Bb. scope management
    3. Cc. scope definition
    4. Dd. scope verification
  9. 9An up-to-date ____ is an important document for developing and confirming a common understanding of the project scope.


    1. Aa. scope management plan
    2. Bb. project scope statement
    3. Cc. WBS
    4. Dd. decomposition
  10. 10Of the following constraints, it is most difficult to describe, agree upon, and meet the ____ goal of many projects.


    1. Aa. Scope
    2. Bb. Time
    3. Cc. cost
    4. Dd. technical

Información

Descripción
Test sobre Q V, creado por Nero Fortuna el 07/03/2017.
Idioma
English
Visitas
0
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?