  1. 1There are ____ main processes involved in project time management.


    1. Aa. two
    2. Bb. four
    3. Cc. six
    4. Dd. ten
  2. 2____ involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.


    1. Aa. Defining activities
    2. Bb. Sequencing activities
    3. Cc. Estimating activity resources
    4. Dd. Estimating activity durations
  3. 3The main outputs of the ____ process are an activity list, activity attributes, and milestone list.




    1. Aa. defining activities
    2. Bb. sequencing activities
    3. Cc. resource estimating activities
    4. Dd. duration estimating activities
  4. 4____ involves identifying and documenting the relationships between project activities.




    1. Aa. Defining activities
    2. Bb. Sequencing activities
    3. Cc. Estimating activity resources
    4. Dd. Estimating activity durations
  5. 5____ involves estimating the number of work periods that are needed to complete individual activities.




    1. Aa. Defining activities
    2. Bb. Sequencing activities
    3. Cc. Estimating activity resources
    4. Dd. Estimating activity durations
  6. 6____ involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule.


    1. Aa. Estimating activity durations
    2. Bb. Developing the schedule
    3. Cc. Controlling the schedule
    4. Dd. Estimating activity resources
  7. 7____ involves controlling and managing changes to the project schedule.


    1. Aa. Estimating activity durations
    2. Bb. Developing the schedule
    3. Cc. Controlling the schedule
    4. Dd. Estimating activity resources
  8. 8Outputs from ____ include work performance measurements, organizational process assets updates, change requests, project management plan updates, and project document updates.


    1. Aa. estimating activity durations
    2. Bb. developing schedules
    3. Cc. controlling the schedule
    4. Dd. estimating activity resources
  9. 9The ____ provide(s) schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.


    1. Aa. activity list
    2. Bb. milestones
    3. Cc. activity descriptions
    4. Dd. activity attributes
  10. 10The goal of ____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.


    1. Aa. defining activities
    2. Bb. sequencing activities
    3. Cc. estimating activity resources
    4. Dd. estimating activity durations

Información

Descripción
Test sobre Q VI, creado por Nero Fortuna el 07/03/2017.
Idioma
English
Visitas
0
Historial
Creado el 7 mar 2017 · actualizado el 7 mar 2017
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?