  1. 1Which of the following statement about composite structure diagram element are correct?
    1. APorts are modeled as small squares
    2. BPorts appears on the boundary of an object
    3. CCollaboration element is represented by a rectangle
    4. DCollaboration occurrences show instances of collaboration
  2. 2Which of the following statements are true about the Subsystem?
    1. ASubsystems are smaller systems within a large system
    2. BA subsystem realizes one or more interfaces. Which define the behaviour it can perform
    3. CIt may be represented as a UML packagcustosche or a set of operations
  3. 3Which of the following situation , aggregation may be appropriate?
    1. An object is physically composed of other objects.
    2. An object is logical collection of other object.
    3. An object can physically contain other objects.
    1. A1,2
    2. B2,3
    3. C1,3
    4. D1,2,3
  4. 4A_________ is represented as a task of zero duration showing an important achievement
    1. AMilestone
    2. BSchedule
    3. CProject Phase
    4. DTracker
  5. 5By default, MS Project 2010 accrues resource costs ______________
    1. AOn a prorated basis
    2. BAt the start of the project
    3. CAt the end of the project task
    4. DAs soon as the specific task starts in the project
  6. 6In Ms project 2010, project managers can use the _________ field in the Resource sheet to designate resources with estimated rates or costs that update with actual rates as the project progresses
    1. AMaterial
    2. BCode
    3. CWork
    4. DResource
  7. 7By default, all tasks in MS Project are ____________
    1. AFixed units tasks
    2. BFixed duration tasks
    3. CFixed work tasks
  8. 8Increasing the number of resources of a task will __________ the duration and decreasing the resources will _________ the duration of the task
    1. AIncrease, Decreases
    2. BDecreases, Decreases
    3. CDecreases, Increase
    4. DIncrease, Increase
  9. 9Which of the following task types MS Project dose not considered as effort – driven tasks by default?
    1. AFixed duration
    2. BFixed work
    3. CFixed units
    4. DFixed time
  10. 10MS Project 2010 comes with a unique feature of saving a project baseline data up to _________ times during the project life cycle
    1. A6
    2. B10
    3. C11
    4. D15

Información

Descripción
Hell Aqib Test sobre Important (ADSE I), creado por Muhammad Aqib el 20/06/2019.
Idioma
English
Visitas
632
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?