1A problem arises in a project 18 months after substantial completion. The Owner contacts you and complains and while you are on site, you notice that the wrong length screws were used to install metal paneling that is now falling off the walls. When contacting the Contractor, the Contractor apologizes but says that the project is no longer under warranty. How does AIA A201 define the Contractor’s warranty obligation?
- AContinues though applicable statute of limitations or repose, whichever is shorter
- B1 year
- C6 months
- DContinues though applicable statute of limitation or repose, whichever is longer
2As a project is nearing completion you realize that the actual project is quite different that the construction drawings. Who is responsible for preparing a permanent record of the work as constructed?
- AArchitect
- BContractor
- CDraftsperson
- DOwner’s Agent
3After completion of a project, who files for the Notice of Completion for a project?
- Aarchitect
- Bbldg official
- CGC
- Downer
4Refer to figure. You receive an application for payment from the Contractor on a project. What is the retainage percentage for this contract?

- A12
- B5
- C8
- D10
5The Architect on a project is preparing to authorize substantial completion with a Contractor. What is the significance of ‘Substantial Completion’?
- AThe warranty period begins for work performed by the General Contractor
- BThe General Contractor has completed all of the Work
- COnce the building official has received the Certificate of Substantial Completion, he/she will make a final inspection
- DThe Owner may occupy the building
6Refer to Figure. You are reviewing a continuation sheet from an application for payment from a Contractor on a project your firm in managing in CA. According to this document, what percentage of completion is this contract?

- A66.67%
- B81%
- C72.73%
- D100%
7After you order the Contractor to perform a pressure test on a plumbing system, you discover some of the supply lines are leaking. Who is ultimately responsible for the cost of repair under AIA Contract Document A201?
- AOwner
- BArchitect
- CPlumber
- DContractor
8You are at project closeout and conducting a final review of open issues. You have identified a conflict in the code when conducting code research relevant to the project. Which requirement shall apply if there is a conflict between a general requirement and a specific requirement?
- ALeast Restrictive
- BMost Restrictive
- Cspecific
- Dgeneral
9After a project’s construction is complete you discuss with the Owner some of the benefits of designing and implementing a building commissioning plan. What are some of these advantages (Choose 3)?
- AOrganized operation and maintenance manuals
- BEnergy efficiency
- CExtends Contractors warranty period
- DImproved air Quality
- EReduce contract costs
- FIncluded in Architect's basic services
10You are attempting to encourage the principal of your firm to complete more Post Occupancy Evaluations. What are some benefits of these evaluations that you might highlight in an effort to convince your firm to invest more resources in this area (choose the best 4)?
- AObtain photos for social media
- BIdentify cost saving measures
- CExtract private information for leverage in future negotiations
- DExtend client relationships
- ESolicit feedback on design and performance
- FLearn from previous experiences to enhance future designs
- GRepair damage to faulty installations
Información
- Descripción
- CE Test sobre CE4, creado por M. A. el 05/11/2019.
- Autor
- M. A.
- Idioma
- English
- Visitas
- 1
- Etiquetas
- Valoración
- Aún sin valoraciones Valora este test