  1. 1What term indicates the percentage of time the work center is active compared to the available time?
    1. Aefficiency
    2. Beffectiveness
    3. Cutilization
    4. Duptime
  2. 2what term is used for the ration of standard hours of work produced to actual hours worked?
    1. Aefficiency
    2. Beffectiveness
    3. Cutilization
    4. Duptime
  3. 3what term is used for calculating available time x utilization x efficiency?
    1. Aeffectiveness
    2. Buseful capacity
    3. Cdemonstrated capacity
    4. Drated capacity
  4. 4which of the following shows the capacity required at each work center based on planned and released orders for each time period of the plan?
    1. Awork center profile
    2. Bload profile
    3. Cscheduled order profile
    4. Dwork-to-be-done report
  5. 5which of the following PAC activities must be done when planning the flow of work?
    1. Abe sure the material and tooling needed are available
    2. Badvise the plant supervisor of future orders
    3. Crefer to the production plan for what orders to run
    4. Dcomplete a material requisition plan
  6. 6Which of the following is concerned with very short-term detailed planning of the flow of orders through manufacturing?
    1. Aproduction planning
    2. Bmaster production scheduling
    3. CMRP
    4. DPAC
  7. 7which of the following is an element of manufacturing lead time?
    1. Adesign time
    2. Bdelivery lead time
    3. Cwait time
    4. Dpurchase lead time
  8. 8what is the name given to a scheduling system in which the last operation on a routing is scheduled first and for completion on the due date?
    1. Aforward scheduling
    2. Bbackward scheduling
    3. Cinfinite scheduling
    4. Dfinite scheduling
  9. 9which of the following statements is most accurate?
    1. Awork centers located after a bottleneck should work at full capacity.
    2. Ba time buffer should be a established after a bottleneck.
    3. Cwork centers feeding a bottleneck should work at full capacity.
    4. Da bottleneck will control the throughput of all products processed by it.
  10. 10which of the following statements is most accurate?
    1. Awork centers located after a bottleneck should work at full capacity.
    2. Ba time buffer should be established after a bottleneck.
    3. Cwork centers feeding a bottleneck should work at full capacity.
    4. Da bottleneck will control the throughput of all products processed by it.

Información

Descripción
Test sobre BSCM , creado por haiden el 16/01/2016.
Autor
haiden
Idioma
English
Visitas
4
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?