Test
ASAP 8 Methodology Cut Over Management Work Stream Quiz
Preguntas del test (3)
1What are tasks of the Production Cutover deliverable?
(More than one answer is correct. Please choose the correct answers.)- AInitiate Solution Manager Update - Solution Documentation
- BExecute Go Live Simulations 1 - n
- CConduct Data Quality Readiness Check
- DFinal Check of Production Readiness and Sign-Off
- EProvide Post Go Live Support
2What is the purpose of the Cut Over work stream in the Realisation phase?
(One answer)- ATo simulate the cut over procedure in the development environment and to provide support for the solution during the period immediately following production cutover.
- BTo execute the SAP Going Live Check service
- CTo begin documenting the timing, steps, and logistics for moving from the as-is solution to the to-be solution and to complete the Technical Integration Check service.
- DTo execute the functional testing and performance testing.
- ETo plan the production cutover weekend party
3What is the purpose of the preliminary cutover plan?
(One answer)- ATo setup the schedule transfer of data from the SAP development system and legacy systems to the SAP production system.
- BTo document the strategy, scope and timelines for moving from the as-is solution to the to-be solution and the hyper care period immediately following go-live.
- CTo identify which named users from the customer organisation that will drive the cutover process according to the working schedule.
- DTo execute communication activities to project stakeholders during cut-over and go live.
- ETo document the instructions on how to slice the cake after a successful go-live.
Información
- Descripción
- Diploma ASA380 - ASAP Implementation Methodology Test sobre ASAP 8 Methodology Cut Over Management Work Stream Quiz , creado por kim.t.dowling el 16/03/2016.
- Autor
- kim.t.dowling
- Idioma
- English
- Visitas
- 33
- Etiquetas
- Valoración
- Aún sin valoraciones Valora este test