Iterative or Linear?

Mark Woodland 10 preguntas

Hacer el test

Preguntas del test (10)

  1. 1Each subtask is taken through the development life cycle in a cyclic way until it is complete
    1. AIterative?
    2. BLinear?
  2. 2At the start of the project the client’s requirements are fixed and then cannot be changed
    1. AIterative?
    2. BLinear?
  3. 3The project manager can plan each phase of the project with certainty because the requirements and deliverables are fixed and cannot change.
    1. AIterative?
    2. BLinear?
  4. 4Each subtask can be developed in detail before the whole requirement is agreed
    1. AIterative?
    2. BLinear?
  5. 5The project is broken down into subtasks
    1. AIterative?
    2. BLinear?
  6. 6The deliverables, which are documents or systems that will be given to the client at each phase of the project, will be agreed by the client and the project team at the start of the project
    1. AIterative?
    2. BLinear?
  7. 7Once a phase has been signed off it will not be repeated
    1. AIterative?
    2. BLinear?
  8. 8At the end of each phase the client will have a review to check the quality of the deliverables and if they are OK will sign them off and will also give approval to proceed to the next phase of the project
    1. AIterative?
    2. BLinear?
  9. 9This method allows loop back during the life cycle when requirements are changed or added
    1. AIterative?
    2. BLinear?
  10. 10The project is broken down into a sequential set of phases (or stages) (analysis, design, construction, testing, installation & conversion and review & maintenance)
    1. AIterative?
    2. BLinear?

Información

Descripción
Test sobre Iterative or Linear?, creado por Mark Woodland el 09/02/2017.
Idioma
English
Visitas
0
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?