Process review

Karolina Dubauskas Inglés 14 diapositivas

Diapositivas del conjunto (14)

  1. Diapositiva 1

    • Process: Define Activities
    • Knowledge Area: Schedule Management
    • Process Group: Planning
    • What Does It Mean? Create an activity list from each work package
  2. Diapositiva 2

    • Process: Sequence Activities
    • Knowledge Area: Schedule Management
    • Process Group: Planning
    • What Does It Mean? Create a network diagram
  3. Diapositiva 3

    • Process: Plan Procurement Management
    • Knowledge Area: Procurement Management
    • Process Group: Planning
    • What Does It Mean? Create the procurement statement of work, procurement strategy, bid documents, and the procurement management plan
  4. Diapositiva 4

    • Process: Develop Project Management Plan
    • Knowledge Area: Integration Management
    • Process Group: Planning
    • What Does It Mean? Create a project management plan that is bought into, approved, realistic, and formal
  5. Diapositiva 5

    • Process: Collect Requirements
    • Knowledge Area: Scope Management
    • Process Group: Planning
    • What Does It Mean? Finalize and document detailed requirements and determine how they will be managed
  6. Diapositiva 6

    • Process: Direct and Manage Project Work
    • Knowledge Area: Integration Management
    • Process Group: Executing
    • What Does It Mean? Produce work according to the project management plan (also called deliverables); create an issue log to track and record issues that have the potential to impact the project
  7. Diapositiva 7

    • Process: Develop Schedule
    • Knowledge Area: Schedule Management
    • Process Group: Planning
    • What Does It Mean? Create a bought into, approved, realistic, and formal project schedule and schedule baseline
  8. Diapositiva 8

    • Process: Perform Qualitative Risk Analysis
    • Knowledge Area: Risk Management
    • Process Group: Planning
    • What Does It Mean? Analyze the probability and impact of potential risks to determine which risks might warrant a response or further analysis
  9. Diapositiva 9

    • Process: Define Scope
    • Knowledge Area: Scope Management
    • Process Group: Planning
    • What Does It Mean? Create the project scope statement
  10. Diapositiva 10

    • Process: Validate Scope
    • Knowledge Area: Scope Management
    • Process Group: Monitoring and controlling
    • What Does It Mean? Meet with the customer to gain formal acceptance of interim deliverables
  11. Diapositiva 11

    • Process: Identify Stakeholders
    • Knowledge Area: Stakeholder Management
    • Process Group: Initiating
    • What Does It Mean? Identify and document information (in the stakeholder register) about the stakeholders on the project
  12. Diapositiva 12

    • Process: Conduct Procurements
    • Knowledge Area: Procurement Management
    • Process Group: Executing
    • What Does It Mean? Select a seller based on the seller responses and obtain a signed contract
  13. Diapositiva 13

    • Process: Monitor and Control Project Work
    • Knowledge Area: Integration Management
    • Process Group: Monitoring and controlling
    • What Does It Mean? Measure performance against the project management plan; change requests may be a result of this comparison
  14. Diapositiva 14

    • Process: Perform Integrated Change Control
    • Knowledge Area: Integration Management
    • Process Group: Monitoring and controlling
    • What Does It Mean? Evaluate the impact of change to the project and approve, reject, or defer change requests

Información

Descripción
Diapositivas sobre Process review, creado por Karolina Dubauskas el 06/03/2021.
Visitas
3
Valoración

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?