Jubilee River - Case Study

Description

Flashcards on Jubilee River - Case Study, created by Tom .. on 12/04/2018.
Tom ..
Flashcards by Tom .., updated more than 1 year ago
Tom ..
Created by Tom .. about 6 years ago
105
1

Resource summary

Question Answer
Location Relief channel for River Thames in south-east England
Cost £330 million
Opened 2002
Weirs? 5
Reduces risk Maidenhead, Eton and Windsor
Why was it required Thames flood plain - low Protect Windsor Urbanisation caused flooding High property value Take overflow water
Issues - Social Some places have gained, less wealthy settlements have resulted in a higher flood risk
Issues - Economic Most expensive scheme, but after 1 year, weirs were damaged Small businesses will loose money
Issues - Environmental 2014 flooding downstream - fields were damaged and habitats disturbed Concrete weirs are ugly and algae collected behind them
Show full summary Hide full summary

Similar

Henry VII Rebellions, political power and control
hawkhigh
B1.2: Responses to a changing environment
benprice99
Algebraic Fractions
Olivia McKenzie
AS Biology Biochemistry and Cell Structure
sian_c_evans
GCSE Chemistry C2 topic notes
imogen.shiels
Edexcel Biology chapter 1
Anna Bowring
Globalisation Case Studies
annie
Algebra - Expansion of Brackets
jerick_hartono
World War I
Lydia Klein
Phrasal Verbs
Felipe Veintimilla
SFDC App Builder 1 (176-200ish)
Connie Woolard