GoConqr has a new look! Let us know what you think.

Flashcards

Demolition Flashcards Week 7

Connor Benning Quantity Surveying English 5.0Average rating 5.0 out of 5 (1 rating) 24 cards

Cards in this deck (24)

  1. 1What are the four stages of demolition?1. Demolition Planning
    2. Health and Safety Planning
    3. Envrionmental Issues Planning
    4. Demolition Methods
  2. 2What documents are relevant to Stage 1 of demolition?BS 6187
    Buiding Act 80-83
  3. 3What documents are relevant to stage 2 of demoltion?HSE Report
    CDM 2015
  4. 4What documents are relevant at stage 3 of demoltion?BS 6187
    Industry best practise
  5. 5What doucments are relevant at stage 4 of demoltion?Observation exercises
    Industry Best Place
  6. 6What is BS 6187 and when was it last updated?BS 6187:2011 gives good practice recommendations for the demolition (both full and partial) of facilities, including buildings and structures. It applies to demolition activities undertaken as part of structural refurbishment and also covers decommissioning
  7. 7Summarise what is set out in BS 6187?Effective management
    Identifying and establishing responsibilities during all phases
    Acquiring a knowledge of the the site
    Structural stability, temporary structural support, deliberate structural collapse
    Managing environmental issues
    Managing health and safety hazards
    Carrying out risk assessments and planning the work accordingly
  8. 8What is section 80 of the building act?Notice of demolishion plans to local authorities
  9. 9What is section 81 of the building act?Local authorities power to serve notice for demoltion
  10. 10What is section 82 of the building act?Notices under section 81
  11. 11What is section 83 of the building act?Appeals against notice served by local authorities under section 81
  12. 12What should be contained within the notice given to local authorities for demolition?Plans, work description (nature, duration)
    Adjacent occupiers
    Gas, electricity and other utilities surveys
  13. 13When can a counter notice be issued and what will it contain?within 6 weeks of recieving the notice
    - Conditions
    - Shoring
    - Removal
    - Make good
    - Repair
  14. 14List some of the statuatory authorties that regulate demolition work?Highway
    Water
    Sewage
    Electrical
    Telecommunications
    Gas
    Rail
  15. 15Why are CDM regs are important to Health and Safety?Assign job roles under CDM
    Assign pre contract information PCI
  16. 16What is required in the HSE report for demolition?High risk suveys for premature collapse
    Mitigation - Structural design knowledge, methods and equipment selection
    Structral surveys
    Method statements and good planning
    Temporary structures
  17. 17What environmental strategies should be adopted?Waste managment strategies in accordance with regulations, prevention of undue consumption, reuse of concrete aggreagte, reducing land fill, recylcing softstrip, roofing and ties.
  18. 18What should all demo sites have in reference to waste managment?Audit of potential reclaimable and recycleable materials
  19. 19What should the waste managment audit allow for?Meet legislation requirments
    Reduce waste disposal and cost
    Maximise resources available and efficiency
    Reduce landfill use and tax payments
    Make better use of materials
  20. 20What are the 3 main forms of demoltion methods?Long reach
    Top down, floor by floor
    Demoltion
  21. 21What is Long reach demoltion?Use of machinery at ground level to reach up and strip buildings. Usually for 2-3 storeys max. Reduces needs for working at height and dangers of stripping the building from inside. Longest reaches of up to 43 metres, carrying weight of 3-4 tonnes
    Quicker than floor by floor, cheaper
  22. 22What is floor by floor demolition?Used on high rises where long reach is not suitable. Scaffolding and fall nets are erected, soft strip carried out (doors, windows, services. Asbestos removed if present. Tower crane often erected to lift machinery to working levels and lift heavy elements down. challenging and Requires lots of planning by engineers
  23. 23What is explosive demoltion?Use of controlled explosives on structural elememts, causes building to fall inwards, rubble is then removed. Takes many weeks to plan, requires exclusion zone, high security, quick once plans are agreed.
  24. 24What are the stages of an explosive demolition?Structural suvey
    Hazardous material survey
    Services investiagtion
    Test blasts
    Determining of exclusion zone
    Security requirments
    Viewing area managment
    Safety managment on day
    Demolition
    Post demo survey of area
    Post demolition client meeting

Information

Description
Quantity Surveying Flashcards on Demolition Flashcards Week 7, created by Connor Benning on 27/04/2019.
Created by
Connor Benning
Views
22
Rating
Average rating 5.0 out of 5 (1 rating)

Feedback

What is it about?

What do you think of the new look?

How do you like it?