Quantitative risk analysis the probability and impact (the amount at stake or the consequences).
Also looks at how risks could affect the objetives of the Project.
Sensitivity Analysis
Sensitivity analysis is a
technique to analize
and compare the
potencial impacts of
identified risk
Annotations:
Sensitivity analysis is all about looking at the effect one variable might have if you could completely isolate it.
People generally use tornado diagrams to look at a project’s sensitivity to just one risk factor.
Process: Perform Quantitative Risk
Analysis
Process Group: Planning
Knowledge Area: Risk Management
Monte Carlo Analysis
A monte carlo analysis
uses the network
diagram and estimates
to "perform" the project
many times and
simulate the cost or
schedule results of the
project
The propose of Quiantitive Risk Analysis
Determine wich risk event
warrant a response
Determine overall Project risk (risk
exposure)
Determine the quantified
probability of meeting Project
objetives
Determine the cost and schedule
reserves
Create realistic and achievable cost,
schedule, or scope targets