Fluxograma
Sem título
Conteúdo do fluxograma
welding engineer makes a WPS for the welder to follow as it is a small test of the WPQR.
the welder makes the test sample with the WPS. a welding inspector records all of the welding conditions made to make the sample. an independent examining body may be requested to monitor the procedure.
the sample is subjected to NDT in accordance to the methods specified, Eg visual inspection, dye penetrant, magnetic particle.
then the sample is destructively tested Eg tensile, bend, macro etch. the client may require additional tests such as hardness and toughness.
the WPQR is made from the welding engineer. it gives details of.:
welding run conditions
resuilts of NDT
results of destructive tests
welding conditions allowed for production welding.
welding engineer makes a WPS for the welder to follow.
the welder then makes a test weld following the WPS. the welding inspector monitors them to ensure they are following the WPS.
the test sample is subjected to NDT in accordance with the methods specified by the standards. some destructive tests may be required.
the welders qualification is prepared showing the welding conditions used to test the sample.
Informações
- Descrição
- Fluxograma sobre Sem título, criado por ryan taylor em 08-02-2017.
- Criado por
- ryan taylor
- Visualizações
- 0
- Avaliação
Mais sobre Welding Processes and Qualification