- 1Critical Path AnalysisThe process that allows for the overall time of a project to be calculated.
- 2NodeRepresents the start or end of an activity.
- 3ESTThe Earliest time possible that a project or stage of production can start.
- 4LFTRefers to the latest time in which an activity can be completed without causing a delay to the next activity.
- 5Total FloatRepresents the longest time by which any activity's start may be delayed without affecting the length of the project as a whole .
- 6Free FloatRefers to the effect upon the next activity and not the project as whole .