O GoConqr está de visual novo! Conte para nós o que você achou.

Mapa mental

PROJECT TIME MANAGEMENT

rocy lucero paredes vargas Espanhol

PROJECT TIME MANAGEMENT

Conteúdo do mapa

PROJECT TIME MANAGEMENT

  1. 1. Plan schedule management

    • Process of stablishes polices, procedures and documentation
    • Inputs
      • Project management plan
        • Project scope statement
        • Wbs
        • Wbs dictionary
      • Project charter
      • Enterprice enviromental factors
      • Organizational process assets
    • Tools and techniques
      • Expert judgment
      • Analytical technique
        • Scheduling methodology
        • Scheduling tools and techniques
        • Estimating approaches
        • Formats
      • Meetings
    • Outputs
      • Schedule management plan
        • Project schedule model development
        • Process description
        • Reporting formats
  2. 2. Define activity

    • Process of identifying and documenting the specification to produce the project deliverables
    • Inputs
      • Schedule management plan
      • Scope baseline
        • Project scope statement
        • WBS
        • WBS dictionary
      • Enterprise enviromental factor
      • Process organization assets
    • Tools and techniques
      • Decomposition
        • Work package
      • Rolling wave planing
      • Expert judgement
    • Outputs
      • Activity list
      • Activity attributes
      • Milestone list
  3. 3. Sequence activity

    • Process of identifying and documenting relationships between project activities
    • Inputs
      • Activity list
      • Schedule management plan
      • Activity attributes
      • Milestone list
      • Project scope statement
      • Enterprise environmental factors
      • Organizational process asstes
    • Tools and techniques
      • Procedence diagramming method
        • Finish to star
        • Finish to finish
        • Star to star
        • Start to finish
      • Dependency determination
        • Mandatory dependencies
        • Discretionary dependencies
        • External dependencies
        • Internal dependencies
      • Leads and lage
    • Outputs
      • Project schedule network diagramas
      • Project documents update
        • Activity list
        • Activity attributes
        • Milestone list
        • Risk register
  4. 4. Estimate activity resource

    • Process of stimating the type and quantities of material, human, resources, tec requered each activity
    • Inputs
      • Schedule management plan
      • Activity list
      • Activity attribute
      • Resource calendars
      • Risk register
      • Activity cost estimates
      • Enterprise environmental factors
    • ools and techniques
      • Expert judgement
      • Alternative analysis
      • Published estimating data
      • Bottom-up estimating
      • Project management software
    • Outputs
      • Activity resource requirement
      • Resources breackdown structure
      • Project document update
  5. 5. Estimate activity duration

    • Process of estimating the numbre of work periods needed to complete individual activities
    • Inputs
      • Schedule management plan
      • Activity list
      • Activity attribute
      • Activity resource requirement
      • Resource calendar
      • Project scope statement
        • Available skilled resource
        • Contract terms and requirement
      • Risk register
      • Resource breackdown structure
    • Tools and techniques
      • Expert judgement
      • Analogous estimating
      • Parametric estimating
      • Three point estimating
        • Most likely
        • Optimistic
        • Pesimistic
      • Group decision making
        • Brainstorming
        • Delphi
        • Nominal
      • Reserve analysis
    • Outputs
      • Activity duration estimate
      • Project document update
  6. 6. Developed schedule

    • Process of analyzing activity squences, duration, resources, needed to complete the individual activities
    • Inputs
      • Schedule management plan
      • Activity list
      • Activity attribute
      • Project schedule networking diagram
      • Activity resource requirement
      • Activity duration estimate
      • Project scope statement
      • Project staff assigment
      • Risk register
    • Tools and technique
      • Critical path method
      • Critical chain method
      • Modeling technique
      • Resource optimization technique
        • Resource leveling
        • Resource smoothing
      • Schedule compression
    • Outouts
      • Schedule baseline
      • Project schedule
      • Schedule data
      • Project calendars
      • Project management plan update
  7. 7. Control schedule

    • Inputs
      • Project management plan
      • Project schedule
      • Project calendars
      • Schedule data
      • Work performance data
    • Tools and techniques
      • Performance reviews
      • Project management software
      • Leads and lags
      • Resource optimization technique
      • Modeling technique
      • Scheduling tools
    • Outputs
      • Work performance information
      • Schedule forecasts
      • Change requests
      • Project management update plan
      • Project document update
    • Process of monitoring the status of project activities to update project progess and manage change to the schedule baseline

Imagens e arquivos do mapa

  • PROJECT TIME MANAGEMENT

Informações

Descrição
Mapa Mental sobre PROJECT TIME MANAGEMENT, criado por rocy lucero paredes vargas em 18-09-2017.
Visualizações
21
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?