SAB8#70 Control Cost

Conteúdo do mapa
SAB8#70 Control Cost
- The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline. Project cost control seeks out the causes of positive and negative variances and is part of the Perform Integrated Change Control process.
Inputs
- Project management plan
- Cost baseline
- Cost management plan
- Work performance data
- Project funding requirements
- Organizational process assets (OPAs):
- Project management plan
Outputs
- Work Performance Measurements
- Calculated CV, SV, CPI, and SPI values for WBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders
- Budget Forecasts
- ETC, EAC
- Organizational Process Assets Updates
- Change Requests
- To adjust the cost performance baseline, project management plan,corrective, or preventive action.
- Project Management Plan Updates
- Cost performance baseline
- Cost management plan
- Project Document Updates
- Cost Estimates
- Basic of Estimates
- Work Performance Measurements
Tools and Techniques
- Earned value management (EVM)
- Is the most common tool which help project managers measure project performance and determine where the project stands in relation to the budget and the schedule at a point in time.
- Forecasting
- To-Complete Performance Index (TCPI)
- – Answers the question, “How efficiently are you using your remaining resources?” – How well your project must perform to stay on budget
- Performance Review
- Compare cost performance over time, schedule activities or work packages over-running and under-running the budget, and estimated funds needed to complete work in progress. If EVM is used, the following is determined: - Variance analysis. compares actual project performance to planned or expected performance. -Trend analysis. examines project performance over time to determine if performance is improving or deteriorating ( EAC vs. BAC ) - Earned value performance. compares the baseline plan to actual schedule and cost performance ( CPI & SPI )
- Variance analysis
- – Identify differences between the work results and the project management plan: CV, SV – Determine what caused the variances (root cause) and plan a corrective actions
- Project management software
- Project management software is often used to monitor the 3 EVM dimensions (PV, EV, AC) to display graphical trends, and to forecast a range of possible final project results.
- Earned value management (EVM)
PM is Responsable
Imagens e arquivos do mapa
Informações
- Descrição
- Mapa Mental sobre SAB8#70 Control Cost, criado por Alfonso Hernandez em 10-12-2015.
- Criado por
- Alfonso Hernandez
- Visualizações
- 21
- Avaliação