TC_#70_Control Cost

  1. PMBOK

    • Knowledge Area: Cost Managemnt
    • Process Group: Monitoring & Controling
    • Proccess: Control Cost
  2. Progress Reporting

  3. EVM

    • Earn Value Measurement
    • Measure project performance against the ...
      • Scope base line (WORK)
      • schedule base line (TIME)
      • Cost Base line (COST)
    • Can be use to FORECAST of time, cost and work
    • TERMS
      • PV --> Planned Value
      • EV --> Earned Value
      • AC --> Actual Cost
      • BAC --> Budget At Completion
      • EAC --> Estimate At Completion
      • ETC --> Estimate To Complete
      • VAC --> Variance At Completion
    • Formulas
      • * --> comulative
      • PV ( Plan Value ) = BAC x Planned%Complete
      • Variance
        • CV (Cost of Variance) = EV -AC
          • NEGATIVE --> Over Budget
          • POSITIVE --> Under Budget
        • SV (Schedule Variance) = EV - PV
          • NEGATIVE --> Behind of Schedule
          • POSITIVE --> Ahead of Schedule
        • VAC ( Variance At Completion ) = BAC - EAC
      • Index
        • CPI (Cost Performance Index) = EV/AC
          • We are getting $X worth of work of every $1 spend
          • GREATER than 1 is good
          • LESS than 1 is bad
        • SPI (Schedule Performance Index) = EV/PV
          • Percent of progress
          • GREATER than 1 is good
          • LESS than 1 is bad
      • Forecast
        • EAC (Estimate At Competion)
          • AC + Buttom-up ETC
          • BAC / CPI*
            • Use if BAC have not variance
            • You will continue with the same rate of spending
          • AC + (BAC -EV)
            • used when current variance are thought to be ATIPICAL of the future
          • AC +(BAC -EV)/(CPI* x SPI*)
            • used when current variance are thought to be TYPICAL of the future
        • TCPI (To-Complete Performance Index)
          • ( BAC - EV ) / ( BAC - AC )
            • GREATER than 1 is BAD
            • LESS than 1 is GOOD
        • ETC ( Estimate to Complete )
          • EAC - AC = Reestimate
      • EV (Earned Value) = BAC x Actual%Complete
      • CPI < 1 or SPI < 1 or CV<0 or SV<0 --> TROUBLE
  4. Reserve Analysis

  5. Schedule Base line

  6. Cost Base line

  7. Scope Base line

  8. Data Work Performance

Imagens e arquivos do mapa

  • TC_#70_Control Cost

Informações

Descrição
Mapa Mental sobre TC_#70_Control Cost, criado por Paulino Valladar em 07-02-2016.
Visualizações
3
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?