O GoConqr está de visual novo! Conte para nós o que você achou.

Mapa mental

PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT

RUBEN MINAS Espanhol

PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT

Conteúdo do mapa

PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT

  1. INTRODUCTION

    • A practice standard is a document that describes established norms, methods, processes, and practices
    • The information in this practice standard evolved from the recognized good practices of earned value management
    • The practice standard provides guidelines for managing individual projects.
  2. PURPOSE OF THIS PRACTICE STANDARD

    • Identifies a subset of project management practices that are used for earned value management
    • Promotes a common vocabulary .
    • There are many different methodologies and tools for implementing the processes described in this practice standard.
  3. RELATIONSHIP TO THE PMBOK ® GUIDE

    • It is assumed that a project has been initiated following the processes outlined in the Initiating Process Group
    • High-level requirements documentation has been gathered along with other information in the project charter
    • Stakeholders have been identified
    • Enterprise environmental factors
      • Government or industry standards
      • Infrastructure
    • Organizational Process Assets
      • Processes and procedures
      • Corporate knowledge base
  4. ASSUMPTIONS

    • The organization has the corporate policies and procedures to support EVM.
    • The organization has the integrated information systems necessary to implement EVM
    • The project management team has the knowledge and skills needed to plan, execute, and control projects using EVM.
    • Project team members and other stakeholders have suffi cient training and understanding of EVM concepts to plan their work accordingly
  5. STRUCTURE OF THE PRACTICE STANDARD

    • Introduction
    • Inputs
    • Description
    • Outputs
    • Considerations
    • Summary
  6. EARNED VALUE PROJECT MANAGEMENT OVERVIEW

    • Earned value management is a management methodology for integrating scope, schedule, and resources.
    • EVM can play a crucial role in answering management questions
      • Are we delivering more or less work than planned?
      • When is the project likely to be completed?
      • Are we currently over or under budget?
      • What is the remaining work likely to cost?
  7. EVM AND THE PROJECT MANAGEMENT PROCESS

  8. 3 BASIC EVM TERMINOLOGY

    • Actual Cost (AC)
    • Budget at Completion (BAC).
    • Contingency Reserve
    • Distributed Budget
    • Earned Value (EV)
    • Estimate at Completion (EAC)
    • Estimate To Complete (ETC).
    • Management Reserve (MR).
    • Performance Measurement Baseline (PMB)
    • Summary Level Planning Budget (SLPB)
  9. CONSIDERATIONS

    • EVM is scalable, and implementing the approach depicted in the EVM system diagram
    • Measuring and comparing the value of the work performed (earned value) with the value planned and actual costs expended to accomplish that work as the project progresses.
    • Developing forecasts, for example, EAC, ETC, VAC, etc.
  10. BASIC EVM CONCEPT

    • EVM facilitates the planning and control of cost and schedule performance, thus improving project management visibility and understanding.

Imagens e arquivos do mapa

  • PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT
  • PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT
  • PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT
  • PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT
  • PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT
  • PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT

Informações

Descrição
Mapa Mental sobre PRACTICE STANDARD FOR EARNED VALUE MANAGEMENT, criado por RUBEN MINAS em 28-05-2018.
Criado por
RUBEN MINAS
Visualizações
0
Histórico
  • Criado por jonathan villalba huaman · 28 mai 2018
  • Copiado por RUBEN MINAS · 28 mai 2018
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?