Planning Scope
Plan Scope Management (guidance and direction)
- M: How the scope will be defined, validated and controlled
- IP: 3, I:4, T&T:2
- Output: Scope Management plan
- 1 Preparing a detailed project scope statement
- 2 Enables the creation of the WBS
- 3 Establish how the WBS will be maintained and approved
- 4 Specifies how formal acceptance of the completed deliverables will be obtained
- 5 How requeste for changes will be processed
- Output: Requirements management plan
- 1 How requirements activities will be planned, tracked and reported
- 2 Configuration management activities: changes to the product, impacts will be analyzed, traced and tracked, authorization levels
- 3 Requirements priorization process
- 4 Product metrics
- 5 Traceability structure: atributes on traceability matrix
- Context
- Project Charter: Project Statement of work and product characteristics
- Enterprise/Organization: Culture, Infraestructure, Marketplace conditions, polices and procedures, lessons learned
- Project Management Plan: influence the approach
Collect Requirements (the project scope including product scope)
- M:Stakeholders needs and requirements to meet project objectives
- IP: 4, I: 5; T&T: 11
- Output: Requirements documentation
- Outputs: Requirements traceability matrix
- Description
- Classification
- Project objectives
- WBS deliverables
- Associated attributes: complexity, acceptance criteria
- ID
- Context
- RMP: define and document stateholders needs
- SMP: which type of requirements?
- PCh
- Stakeholder mangement plan: understand stake holder communication requirements
- Stakeholder register: main expectations
- Classification
- Bussiness
- Stakeholder
- Functional: behavior of the product
- Nonfunctional: reliability, security, safety
- Transition
- Project
- Quality
T&T
- Expert Judgment
- Group decision-making
- Meetings
- Decomposition (100 percent rule)
Define Scope (Develop the project scope statement)
- IP: 4, I:4, T&T: 4
- Output: Project Scope Statement
- 1 Product Scope description (Characteristics)
- 2 Acceptance criteria (conditions/deliverables)
- 3 Deliverable (unique & verifiable)
- 4 Project exclusion (out of scope)
- 5 Constraints (restrictions, limitations)
- 6 Assumptions (without proof)
- M: which of the requirements collected will be included?
- Context
- OPA
- PCh
- RD: to select
- SMP: activities for developing, M&C the project scope
- Output: Project Documents Updates
- Stakeholder register
- Requirements documentation
- Requirements traceability matrix
Create WBS (structured vision. Subdividing deliverables and work)
- M: hierarchical decomposition, smaller, more manageable ($, t) components (delverables, results)
- IP:4, I:5, T&T:2
- Context
- SMP: how to create WBS, maintained and approved
- PSS
- RD: what needs
- EEF, OPA
- Output: Scope Baseline (approved version)
- Project scope statement
- WBS (unique identifier, code of accounts)
- WBS dictionary (about each component)
- Code of account identifier
- Description of work
- Assumptions & Constraints
- Responsible organization
- Schedule milestone
- Associated schedule activities
- Resources required
- Cost estimates
- Quality requirements
- Acceptance criteria
- Technical references
- Agreement information
- Output: Project Documents Updates (approved changes)