It refers to finding ways to adjust the use of resources
Resource leveling
- It is used to procude a resource_limited schedule
- Leveling lengthens the schedule and increases cost in order to deal with a limited amount or resources, resource availability and other resource constraints
Resource smoothing
- It is a modified form of resource leveling, where resources are leved only within the limits of the float of their activities, so the completition dates of activites are not delayed