131. The first process involved in project time management is _____ .
- Aa. defining activities
- Bb. estimating activity durations
- Cc. planning schedule management
- Dd. sequencing activities
232. Which of the following processes in project time management involves identifying the specific tasks that the project
team members and stakeholders must perform to produce the project deliverables?- Aa. Defining activities
- Bb. Sequencing activities
- Cc. Developing the schedule
- Dd. Estimating activity durations
333. In project time management, which of the following processes generate the main outputs of an activity list, activity
attributes, and a milestone list?- Aa. Sequencing activities
- Bb. Defining activities
- Cc. Resource estimating activities
- Dd. Estimating activity durations
434. In project time management, which of the following processes primarily involve identifying and documenting the
relationships between project activities?- Aa. Defining activities
- Bb. Sequencing activities
- Cc. Planning schedule management
- Dd. Estimating activity durations
535. In project time management, which of the following processes involve calculating the number of work periods that are
needed to complete individual activities?- Aa. Defining activities
- Bb. Sequencing activities
- Cc. Planning schedule management
- Dd. Estimating activity durations
636. In project time management, which of the following processes involve analyzing activity sequences, activity resource
estimates, and activity duration estimates to create the project schedule?- Aa. Planning schedule management
- Bb. Developing the schedule
- Cc. Controlling the schedule
- Dd. Defining activities
737. In project time management, the process of_____ primarily involves checking and managing changes to the project
schedule.- Aa. estimating activity durations
- Bb. developing the schedule
- Cc. controlling the schedule
- Dd. estimating activity resources
838. In project time management, a(n) _____ is an output of controlling the schedule
- Aa. activity duration estimate
- Bb. project management plan update
- Cc. activity attribute
- Dd. milestones list
939. Which of the following documents is most likely to include planned project start and end dates which serve as the
starting points for a detailed schedule?- Aa. Resource breakdown structure
- Bb. Milestones list
- Cc. Organizational process assets update
- Dd. Project charter
1040. Which of the following is a difference between an activity list and an activity attribute?
- Aa. As opposed to an activity attribute, an activity list provides resource requirements and constraints related to
activities. - Bb. An activity list provides a more concrete list of milestones for a project than an activity attribute.
- Cc. An activity attribute is a tabulation of activities to be included on a project schedule whereas an activity list is
not - Dd. An activity attribute provides more schedule-related information about each activity than an activity list.
- Aa. As opposed to an activity attribute, an activity list provides resource requirements and constraints related to
1141. A(n) _____ on a project is a significant event that normally has no duration.
- Aa. milestone
- Bb. activity attribute
- Cc. activity sequence
- Dd. schedule baseline
1242. In project time management, the main goal of _____ is to ensure that the project team has complete understanding of
all the work they must do as part of the project scope so they can start scheduling the work.- Aa. defining activities
- Bb. estimating activity durations
- Cc. estimating activity resources
- Dd. controlling the schedule
1343. In project time management, the next step after defining project activities is:
- Aa. planning schedule management
- Bb. determining their dependencies.
- Cc. controlling the schedule
- Dd. estimating activity duration.
1444. Which of the following types of dependencies are inherent in the nature of work being performed on a project?
- Aa. Mandatory
- Bb. Discretionary
- Cc. External
- Dd. Random
1545. _____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later
scheduling options.- Aa. Mandatory
- Bb. Discretionary
- Cc. External
- Dd. Inherent
1646. Which of the following dependencies involve relationships between project and non-project activities?
- Aa. Mandatory
- Bb. Discretionary
- Cc. External
- Dd. Inherent
1747. In an AOA network diagram, _____ occur when two or more activities follow a single node.
- Aa. combinations
- Bb. buffers
- Cc. mergers
- Dd. bursts
1848. A network diagramming technique in which boxes represent activities is known as a(n) _____.
- Aa. PDM
- Bb. CPM
- Cc. ADM
- Dd. PERT
1949. AOA network diagrams use only _____ dependencies.
- Aa. start-to-start
- Bb. finish-to-start
- Cc. finish-to-finish
- Dd. start-to-finish
2050. Which of the following is a relationship in which the “from” activity cannot start until the “to” activity is started?
- Aa. Start-to-start
- Bb. Finish-to-finish
- Cc. Finish-to-start
- Dd. Start-to-finish
2151. Which of the following is true of a finsih-to-finish dependency?
- Aa. It is a dependency in which the “from” activity cannot start until the “to” activity or successor is started.
- Bb. It is a dependency in which in which the “from” activity must finish before the “to” activity or successor can
start. - Cc. It is a dependency in which the “from” activity must be finished before the “to” activity can be finished.
- Dd. It is a dependency in which the “from” activity must start before the “to” activity can be finished.
2252. Which of the following is true of dummy activities?
- Aa. They have long durations.
- Bb. They show logical relationships between activities.
- Cc. They have a large range of resources.
- Dd. They have limited time periods
2353. Which of the following is one of the main outputs of estimating activity resources process?
- Aa. Project documents update
- Bb. Milestone list
- Cc. Work breakdown structure
- Dd. Activity duration estimate
2454. After working with key stakeholders to define activities and calculate their resources, the next process in project time
management is to:- Aa. develop the schedule.
- Bb. control the schedule.
- Cc. determine their dependencies.
- Dd. estimate the duration of activities.
2555. In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the
time dimension of the project.- Aa. defining activities
- Bb. sequencing activities
- Cc. developing a schedule
- Dd. estimating activity resources
2656. _____ provide(s) a standard format for displaying project schedule information by listing project activities and their
corresponding start and finish dates in a calendar format.- Aa. Gantt chart
- Bb. Critical path analysis
- Cc. Arrow diagramming method
- Dd. PERT analysis
2757. Which of the following is a network diagramming technique used primarily to predict total project duration?
- Aa. Gantt chart
- Bb. Critical path analysis
- Cc. Resource breakdown structure
- Dd. Arrow diagramming method
2858. The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.
- Aa. longest; longest
- Bb. longest; shortest
- Cc. shortest; longest
- Dd. shortest; shortest
2959. The amount of time an activity can be delayed without delaying the early start date of any immediately following
activities is known as a _____.- Aa. forward pass
- Bb. backward pass
- Cc. fast tracking
- Dd. free slack
3060. _____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish
date.- Aa. Total slack
- Bb. Free float
- Cc. Backward pass
- Dd. Forward pass
3161. The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.
- Aa. early finish date
- Bb. late finish date
- Cc. late start date
- Dd. early start date
3262. Which of the following techniques involve doing activities in parallel that one would normally do in sequence?
- Aa. Critical chain scheduling
- Bb. Crashing
- Cc. Fast tracking
- Dd. PERT analysis
3363. The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the
least incremental cost is known as _____.- Aa. dependency
- Bb. crashing
- Cc. critical chain scheduling
- Dd. feeding buffers
3464. A similarity between the crashing technique and the fast tracking technique is that:
- Aa. both spread out tasks over a long period of time to ensure the quality of work is maintained.
- Bb. both invariably result in increases in total project costs.
- Cc. both can shorten the time needed to finish a project.
- Dd. both are network diagramming techniques used primarily to predict total project duration.
3565. Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of
additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.- Aa. critical paths
- Bb. feeding buffers
- Cc. dummy activities
- Dd. fast tracking
3666. _____ states that work expands to fill the time allowed.
- Aa. Murphy’s Law
- Bb. Miller’s Law
- Cc. Parkinson’s Law
- Dd. Einstein’s Law
3767. A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that:
- Aa. CPM addresses the risk associated with duration estimates whereas PERT does not.
- Bb. unlike CPM, PERT estimates only when there is no risk of uncertainty.
- Cc. CPM involves more work than PERT because it requires several duration estimates.
- Dd. PERT uses different duration estimates whereas CPM uses one specific duration estimate.
3868. Which of the following is a silimarity between scope control and schedule control?
- Aa. Both are initial processes of project time management.
- Bb. Both of their primary goals is to define project goals and miestones.
- Cc. Both are portions of the integrated change control process under project integration management.
- Dd. Both of these processes should occur before estimating activity durations.
3969. Which of the following is an output of schedule control?
- Aa. Lessons-learned reports
- Bb. Activity attributes
- Cc. Resource requirements
- Dd. Milestones list
4070. A draft schedule for a project is most likely to be found in a _____.
- Aa. project buffer
- Bb. project charter
- Cc. resource breakdown structure
- Dd. project’s dummy activities list
4171. In project procurement management, which of the following is an output of the executing process?
- Aa. Make-or-buy decisions
- Bb. Statements of work
- Cc. Source selection criteria
- Dd. Resource calendars
Informações
- Descrição
- CIS 4375 Quiz sobre Chapter 6 M/C, criado por . . em 27-09-2017.
- Autor
- . .
- Idioma
- English
- Visualizações
- 17
- Etiquetas
- Avaliação
- Ainda sem avaliações Avalie este quiz
Mais sobre Project Scheduling and Cost Management