Chapter 7 T/F

. 30 perguntas

Fazer o quiz

Perguntas do quiz (30)

  1. 11. Overrun is the additional percentage amount by which estimates exceed actual costs.
    1. AVerdadeiro
    2. BFalso
  2. 22. The primary output of the planning cost management process is a change request.
    1. AVerdadeiro
    2. BFalso
  3. 33. IT project managers must be able to present and discuss project information both in financial and technical terms
    1. AVerdadeiro
    2. BFalso
  4. 44. Project managers must conduct cash flow analysis to determine net present value.
    1. AVerdadeiro
    2. BFalso
  5. 55. Intangible costs can be easily measured in monetary terms.
    1. AVerdadeiro
    2. BFalso
  6. 66. When deciding what projects to invest in or continue, one should include sunk costs
    1. AVerdadeiro
    2. BFalso
  7. 77. It is important for project managers to focus on indirect costs because they can be easily controlled.
    1. AVerdadeiro
    2. BFalso
  8. 88. If an important supplier goes out of business, management reserves can be set aside to cover the resulting costs.
    1. AVerdadeiro
    2. BFalso
  9. 99. Contingency reserves are also known as unknown unknowns.
    1. AVerdadeiro
    2. BFalso
  10. 1010. A cost management plan can include organizational procedures links, control thresholds, and process descriptions.
    1. AVerdadeiro
    2. BFalso

Informações

Descrição
CIS 4375 Quiz sobre Chapter 7 T/F, criado por . . em 27-09-2017.
Autor
. .
Idioma
English
Visualizações
3
Etiquetas
cis 4375
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?