  1. 1After the schedule is approved by the sponsor, customer, and key stakeholders, what has just happened?
    1. AThe critical path is finalized.
    2. BThe task start and end dates are finalized.
    3. CThe schedule baseline is established.
    4. DThe resources are assigned.
  2. 2What are the most commonly used forms to display project schedules? Choose two.
    1. AGantt charts
    2. BPERT charts
    3. CA spreadsheet
    4. DCPM diagrams
  3. 3The Initiating phase includes which task?
    1. ACreating a work breakdown structure
    2. BApproving a project and authorizing work to begin
    3. CCoordinating resources to complete the project work
    4. DIdentifying and planning for detailed risks
  4. 4Which of these activities occur during the Planning phase? Choose three.
    1. ABusiness case
    2. BBudget
    3. CHigh-level scope definition
    4. DResources
    5. EChange control
    6. FSchedule
  5. 5This component of the project charter describes the characteristics of the product, service, or result of the project.
    1. AGoals and objectives
    2. BMilestones
    3. CDeliverables
    4. DProject Description
  6. 6Stakeholders have come to you to tell you they want to change the scope. Before agreeing to the change, what things should you do? Choose two.
    1. ADiscuss the proposed scope change with the sponsor.
    2. BAsk team members what they think about the scope change.
    3. CDefine alternatives and trade-offs that you can offer the stakeholders.
    4. DImplement the change.
    5. EDetermine which project constraint (time, budget, quality) is most important to stakeholders.
  7. 7After a change request is submitted, all of the following steps occur prior to being reviewed by the change control board except for which one?
    1. ASpecific elements of the project, such as additional equipment needs, resource hours, quality impacts, and more, are analyzed.
    2. BAnalysis of the impacts of the change is performed.
    3. CThe change request is recorded in the change log.
    4. DUpdate the appropriate project planning document to reflect the change.
  8. 8Which of the following is not a type of change?
    1. APreventive actions
    2. BPerformance corrections
    3. CDefect repairs
    4. DCorrective actions
  9. 9This document contains the details of a procurement item in clear, concise terms and includes the project objectives, a description of the work of the project, and concise specifications of the product or services required.
    1. ARFP
    2. BRFQ
    3. CSOW
    4. DRFI
  10. 10You are in the Monitoring and Controlling phase of the project. Several problems have come to light, and you want to know what the causes of the problems are that are generating the effect. You hold a brainstorming meeting with key team members and plot the cause-and-effect scenarios on this type of chart.
    1. APareto chart
    2. BHIstogram
    3. CFishbone diagram
    4. DScatter diagram

Informações

Descrição
Quiz sobre Project+ 004, criado por Brandon Gagon em 28-07-2019.
Idioma
English
Visualizações
1
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?