  1. 1The work of the first phase of your project has come to end. What should you ensure is done BEFORE beginning the next phase?
    1. Aa. Verify that the resources are available for the next phase
    2. Bb. Check the project´s progress compared to its baselines
    3. Cc. Confirm that the phase has reached its objectives, and have its deliverables formally accepted
    4. Dd. Recommend corrective action to bring the project results in line with project expectations
  2. 2The project is in the planning process group when three stakeholders come to the project manager asking for information on the company’s new project management methodology, where it came from and why it is different from how they manage projects. These stakeholders are also friends of the project manager and the entire group has worked together for years. The project is using some new terms like “corrective action” that are making some stakeholders nervous as they are unsure if the way the project will be managed is going to change along with new terms. What should the project manager do??
    1. Aa. Advise the stakeholders that he will keep them in the communication loop for the project.
    2. Bb. Supply a list of new terms and their definitions.
    3. Cc. Notify the project management office.
    4. Dd. Make sure he maintains his authority as the project manager even though they are friends.
  3. 3If you have to choose one of the following as NOT being a project, which one will it be??
    1. Aa. Building a 10 ft. x 15 ft. shed in your backyard.
    2. Bb. Creating a project management office in the IT department.
    3. Cc. Increasing parking spaces from 300 to 400 in a parking lot.
    4. Dd. Shipping 10 times larger than usual order received through internet.
  4. 4A project team member is talking to another team member and complaining that many people are asking him to do things. If he works in a functional organization, who has the power to give direction to the team member?
    1. Aa. The project manager
    2. Bb. The functional manager
    3. Cc. The team
    4. Dd. Tight matrix
  5. 5Two project managers have just realized that they are in a weak matrix organization and that their power as project managers is quite limited. One figures out that he is really a project expediter and the other realizes he is really a project coordinator. How is a project expediter different from a project coordinator??
    1. Aa. The project expediter cannot make decisions.
    2. Bb. The project expediter can make more decisions.
    3. Cc. The project expediter reports to a higher-level manager.
    4. Dd. The project expediter has some authority
  6. 6Which is the main difference between project expediter and project coordinator??
    1. Aa. The expediter have more responsibility than the coordinator
    2. Bb. A project expediter works as staff assistant and coordinator works in operational activities.
    3. Cc. Project coordinators have power to make some decision, have some authority
    4. Dd. Project coordinator have less work than project expediter.
  7. 7The project team has just completed the initial project schedule and budget. The NEXT thing to do is:?
    1. Aa. Identify risks
    2. Bb. Begin iterations
    3. Cc. Determine communications requirements
    4. Dd. Create a bar (Gantt) chart
  8. 8In creating the project management plan for a construction project, a team would typically be involved in creating all of the following EXCEPT.?
    1. Aa. Cost Management Plan
    2. Bb. Risk Management Plan
    3. Cc. Schedule Management Plan
    4. Dd. Information Distribution Plan
  9. 9What will the project team create as a result of performing monitoring and controlling on a project??
    1. Aa. Charter
    2. Bb. Controlling Stakeholders
    3. Cc. Work performance reports
    4. Dd. Project product
  10. 10A project manager has confided in you that he is struggling with the whole concept of project management. He is constantly being handed down unreasonable demands by the customer and is trying to balance that with unreasonable and often opposing demands from senior management and stakeholders. He is worried that the two projects he is managing may fail and asks you for help. What is the BEST thing you can do in this case?
    1. Aa. Provide your friend with a copy of the PMBOK.
    2. Bb. Encourage your friend to get project management training.
    3. Cc. Tell your friend that he should not be managing projects.
    4. Dd. Have a private talk with your friend’s boss about the problem.

Informações

Descrição
Intro 3
Idioma
Español
Visualizações
29
Etiquetas
intro 3avza
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?