PRINCE 2 (Lecture 7)- Directing a Project / Managing Stage Boundaries / Closing a Project

Natalie Hallam 13 perguntas

Fazer o quiz

Perguntas do quiz (13)

  1. 1In which process is the initiation of the project authorised?
    1. AStarting up a Project
    2. BInitiating a Project
    3. CDirecting a Project
    4. DManaging a Stage Boundary
  2. 2When does the process of Directing a Projectformally begin?
    1. ABefore Starting up a Project
    2. BAfter Starting up a Project
    3. CAfter Initiating a Project
    4. DAfter Managing a Stage Boundary
  3. 3Which of the following products is NOT reviewed by the Project Board when authorising project closure?
    1. AProject Initiation Document (PID)
    2. BProject Brief
    3. CEnd Project Report
    4. DBenefits Review Plan
  4. 4Which role recommends the project closure?
    1. AThe Executive
    2. BThe Senior User
    3. CThe Senior Supplier
    4. DThe Project Manager
  5. 5Which management product is provided to the Project Board with a request to authorise initiation?
    1. AProject Brief
    2. BProject Mandate
    3. CDraft Project Initiation Document
    4. DIssues Register
  6. 6What is the purpose of an Exception Report?
    1. AWhere there is a forecast to exceed tolerance, it is prepared to inform the Project board of the situation.
    2. BIt provides the Project Board with a summary of stage staus at intervals defined by them.
    3. CIt contains the description, impact assessment and recommendations for a request for change or off-specification.
    4. DWhen there is a forecast to exceed tolerance, it replaces the plan which is no longer valid.
  7. 7How often is the Managing Stage Boundary process invoked?
    1. AAt the end of the Starting Up a Project process.
    2. BAt the end of each project.
    3. CAt the end of each stage, except the final one.
    4. DAt the end of each Work Package.
  8. 8Who needs the information gathered in Managing a Stage Boundary to assess the continuing viability of a project?
    1. ACorporate/Programme Manager
    2. BProject Board
    3. CProject Manager
    4. DStakeholders
  9. 9Which of the following plans listed below is NOT produced or updated in the Managing a Stage Boundary process?
    1. AException Plan
    2. BNext Stage Plan
    3. CTeam Plan
    4. DProject Plan
  10. 10The Project Board may request that the current stage is replanned, and the output from replanning is... which is submitted for Project Board approval?
    1. Aa Stage Plan
    2. Ba Project Plan
    3. Ca Team Plan
    4. Dan Exception Plan

Informações

Descrição
Quiz sobre PRINCE 2 (Lecture 7)- Directing a Project / Managing Stage Boundaries / Closing a Project, criado por Natalie Hallam em 23-02-2015.
Idioma
English
Visualizações
50
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?