Quiz
PRINCE 2 (Lecture 5)- Starting Up a Project (SU) / Initiating a Project (IP)
Crie uma conta grátis para terminar este quiz
Salve seu progresso e veja sua nota final.
Já tem uma conta? Inicie sessão
Perguntas do quiz (10)
1Which is NOT an objective of the Initiating a project process?
- AEnsure there is a common understanding of who will take significant project management roles within the project.
- BEnsure there is a common understanding of how and when the project's products will be achieved and at what cost.
- CEnsure there is a common understanding of the reasons for doing the project, the benefits expected and the associated risks.
2Which of the following is NOT a PRINCE2 management product?
- ARisk Management Strategy
- BConfiguration Management Strategy
- CCommunication Management Strategy
- DCost Management Strategy
3The Business Case will contain a summary of key risks, where will the details of all the risks be stored?
- AIssues Register.
- BConfiguration Item Records
- CRisk Management Strategy
- DRisk Register
4Which of the following is defined as part of setting up controls for the project?
- ATolerances for delegated authority.
- BQuality management procedure.
- CTools and techiques for managing risks
- DHow information from outside of the project environment will be sent or received.
5Information on project controls is included in which management product?
- AProject Brief
- BBusiness Case
- CStage Quality Plan
- DProject Initiation Documentation
6The Outline Business Case is prepared as part of which process?
- AControlling a Stage
- BStarting up a Project
- CInitiating a Project
- DDirecting a Project
7The information gathered in the Starting Up a Project process should answer what basic uestions?
- ADo we have a viable and worthwhile project?
- BDo we know who thought of this idea?
- CDo we care about the outcome at this stage?
- DDo we solve the problem now or later?
8What management product produced in Starting Up a Project is submitted to the Project Board with a request to initiate a Project?
- AProject Brief
- BRefined Business Case
- CProject Initiation Document (PID)
- DProject Plan
9How does the Starting up a Project process support the defined roles and responsibilities principle?
- ABy nominating the project manager responsible for project assurance.
- BBy appointing the executive, the project manager and the project management team.
- CIt doesn't.
- DBy ensuring lessons from previous projects are captured and analyzed.
10Who is responsible for creating the Initiation Stage Plan?
- AProject Manager
- BProject Board
- CTeam Manager
- DProject Assurance
Informações
- Descrição
- Quiz sobre PRINCE 2 (Lecture 5)- Starting Up a Project (SU) / Initiating a Project (IP), criado por Natalie Hallam em 23-02-2015.
- Autor
- Natalie Hallam
- Idioma
- English
- Visualizações
- 126
- Histórico
- Criado em 23 fev 2015 · atualizado em 19 fev 2016
- Avaliação
- Ainda sem avaliações Avalie este quiz