1A project manager is attempting to establish the proper sequencing and duration of project activities.
Which of the following would be the MOST beneficial?- ANetwork diagram
- BIshikawa diagram
- CWBS
- DGantt chart
2Which of the following are characteristics of a project? (Choose two.)
- AOngoing
- BTemporary
- CStart and finish
- DAchieving a goal
- EConsisting of milestones
- FRestricting the budget
3A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?- ARFO
- BRFI
- CRFP
- DRFQ
4The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)- AThe issue log to show why the vendor should be replaced.
- BThe team action items to show why the vendor should be replaced.
- CThe scope statement to show why the vendor should be replaced.
- DA procurement plan to show why the vendor should be replaced.
- EA change management plan to have the vendor replaced.
5A project manager is creating the WBS. In which of the following phases is the project?
- AInitiation
- BPlanning
- CExecution
- DClosing
6Which of the following is a characteristics of a matrix organization?
- AAuthority lies solely with the project manager.
- BAuthority is directed by the project architect.
- CAuthority is shared between the project manager and project coordinator.
- DAuthority is shared between functional and project managers.
7A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?- AProject team members
- BProject sponsor
- CProject manager
- DProject scheduler
8A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?- AProject schedule
- BBalanced scorecard
- CIssue log
- DStatus report
9A stakeholder is unaware of a projects status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)- AStatus report
- BOrganizational chart
- CRACI matrix
- DMeeting minutes
- ECommunication plan
10There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks -
A, B, F: 8 weeks -
D, E, H: 12 weeks -
D, B, F: 7 weeks -
Which of the following tasks are on the critical path?- AA, C, G
- BA, B, F
- CD, E, H
- DD, B, F
11A project team is comprised of a mix of in-house and virtual team members.
When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?- AComposing a project team email with the details of the announcement is the best method. It gives the project manager the opportunity to explain but not be overcome with questions from the team.
- BUsing text messaging to make the announcement is the best method. It allows the project manager to reach the project team members wherever they are located.
- CSending a fax is the best method. It gives the project manager the opportunity to explain the announcement and come up with questions and answers the team may have.
- DHosting a web conference meeting is the best method. It gives the project manager the opportunity to explain the announcement and answer any questions from the team.
12A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?- ABacklog
- BStandup
- CKickoff
- DRetrospective
13A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps.
Which of the following conflict resolution techniques is the project manager using?- AForcing
- BNegotiating
- CCompromising
- DAvoiding
14A project manager is justifying a required change with the associated impact on the project.
Which of the following is the NEXT step?- AImplementation
- BApproval
- CValidation
- DAuditing
15The PMO is responsible for: (Choose two.)
- Amanaging the project plan, scope, risk, and budget.
- Bcontributing expertise, deliverables, and estimates of costs.
- Csetting standards and practices for the organization and providing governance.
- Doutlining consequences of non-performance and coordinating between disparate projects.
- Eapproving funding, developing the project schedule, and gathering high-level requirements.
16A critical stakeholder has requested additional status updated beyond the schedule.
Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?- AConfidentiality
- BCriticality
- CFrequency
- DCultural differences
17Which of the following activities are associated with the closing phase of a project? (Choose two.)
- ARisk mitigation
- BArchiving of project documents
- CTracking of expenditures
- DLessons learned
- EQuality assurance
18Which of the following describes a burn rate?
- AThe rate at which project documents are disposed.
- BThe rate at which project personnel leave the project.
- CThe rate at which the project budget is used.
- DThe rate at which the timeline increases.
19The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Which of the following should the project manager do NEXT?- AEvaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
- BEvaluate the risk, fill in the issue log, and communicate it according to the communication plan.
- CEvaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
- DEvaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
20One deliverable failed during testing, and this has already happened several times.
Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?- ARun chart
- BFishbone diagram
- CScatter diagram
- DGantt chart
21During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?- ABusiness case
- BRequirements document
- CProject timeline
- DTask plan
22A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.
Which of the following should a project manager update to document this information?- AA list of realized risks
- BA list of decomposed activities
- CA sequenced list of project tasks
- DA document describing agreed-upon communication methods
23The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?- ACost baseline
- BBurn rate
- CCost variance report
- DTotal project cost
24Which of the following defines a group of projects that work together to achieve a common goal?
- AProduct
- BPortfolio
- CProgram
- DProject plan
25A company hires an outside vendor to provide 24/7 support.
Which of the following documents would determine the contractual obligations?- APO
- BSLA
- CLOI
- DMOU
26A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.
Which of the following techniques is MOST likely to be used to complete the project on time?- AThrottling
- BCrashing
- CResource leveling
- DResource smoothing
27A project manager is unsure if the quality of a deliverable from a SME meets specifications.
Which of the following is the BEST way for the project manager to address the issue?- AConduct a face-to-face or telephone meeting with the team member.
- BSend an email outlining the concerns to the team member.
- CSend a project team meeting to obtain feedback from everyone.
- DPost the issue on the wiki page for input from stakeholders.
28Which of the following is a key aspect of the Agile project management methodology?
- ATest-driven
- BDaily standup meetings
- CShort project durations
- DDefined list of requirement
29A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?- AAssess the risk registers new items.
- BReview the task start and finish dates.
- CObtain additional resources.
- DAnalyze the assigned hours.
30A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements.
Which of the following actions would be BEST for the project manager to take?- AAsk the client to provide additional language resources to the team.
- BPurchase a language translation program.
- CHire a translator to help the key team member
- DAsk the client to provide requirements in the native language of the team.
31After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?- AUse milestones identified in the project charter.
- BUse data based on past knowledge.
- CHold a full team workshop to review the complete WBS.
- DCollaborate with other project managers.
32A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.
Which of the following terms describe this requirement?- AOutsourcing
- BBusiness acquisition
- CBusiness process change
- DInternal reorganization
33A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved.
Which of the following constraints are MOST likely to be affected? (Choose two.)- AQuality because the existing system is now outside the threshold.
- BRequirements because this is a change to initial scope.
- CCost because replacing the system incurs additional expense.
- DSchedule because this was an unscheduled task and will impact the timeline.
- EStakeholders because they will need to understand the modification and provide buy-in.
34Assuming an iterative approach, which of the following will be conducted at the end of each iteration?
- ASCRUM retrospective
- BKickoff meeting
- CBudget baseline
- DRisk review
35The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendors areas of poor performance?- ABalanced score card
- BWBS
- CPost-project evaluation
- DPERT
36Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:- Aforcing
- Bavoiding
- Csmoothing
- Dcompromising
37Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
- AEAC
- BBAC
- CCPI
- DETC
38The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.
Which of the following should the project manager do to obtain the resources?- AThe project manager should identify and document the reasons for the additional resources in a change request.
- BThe project manager should hire additional resources temporarily to complete the project.
- CThe project manager should terminate the project until additional resources are added to the project.
- DThe project manager should ask the project team members to take on more tasks to complete the project on time.
39An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?- APMO
- BProject sponsor
- CProject coordinator
- DHR
40When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?
- AIssue log
- BRisk management plan
- CCommunications plan
- DRisk register
- EStatus report
41A milestone task on the critical path has been completed.
Which of the following should the project manager notify?- AOwner of predecessor task
- BProject team
- CProject sponsor
- DProject steering committee
42During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.
Which of the following actions should the project manager take?- AAlert the project sponsor of the situation.
- BContact the customer and request more funding.
- CAnnounce the project will end early due to lack of funds.
- DAttempt to save money in downstream activities.
43Which of the following is the primary purpose of an MOA or an MOU?
- AState expectations of all signatory parties to reduce potential misunderstandings.
- BFacilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.
- CEnumerate a detailed code of conduct for all employees, contractors, and subcontractors participating in the program.
- DProvide transparency to competitors regarding all signatory parties.
44Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized?- ASmoothing
- BForcing
- CCompromising
- DAvoiding
45The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?- AExecution
- BKickoff
- CClosure
- DPlanning
46A project manager is working on the project charter.
Which of the following phases does this describe?- AInitiation
- BPlanning
- CExecution
- DClosing
47A project in the execution phase is over budget, and tasks on the critical path are on schedule.
Which of the following should the project manager do NEXT?- AUpdate the project management plan.
- BIssue a change request.
- CRevise the project charter.
- DEvaluate the impact to the baseline.
48Several team members report that meeting objectives are not being met.
Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)- ACreate an SOW prior to each meeting and adhere to it.
- BCreate a meeting agenda prior to each meeting and adhere to it.
- CCreate a lessons learned list prior to each meeting and adhere to it.
- DCreate a project charter prior to each meeting and adhere to it.
- ECreate an action item list during the meeting and adhere to it.
- FCreate a corrective action plan prior to each meeting and adhere to it.
- GCreate a WBS prior to each meeting and adhere to it.
49Which of the following documents should be used to provide high-level reporting to key stakeholders?
- ADashboard
- BCommunication plan
- CStatement of work
- DProject charter
50A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?- ASponsor
- BProject manager
- CProject management office
- DProject team
51Which of the following project documents should be used to record the occurrence of an unplanned event?
- AAction log
- BRisk log
- CChange log
- DIssue log
52Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?
- ASOW
- BPO
- CSLA
- DMOU
53Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
- AEAC
- BBAC
- CTCPI
- DETC
54A customer will have ongoing changes to project requirements.
Which of the following is the BEST project management methodology for this requirement?- AWaterfall
- BAgile
- CPRINCE2
- DBottom-up
55Which of the following describes risk mitigation?
- AThe transfer of the risk to another entity or project inside or outside the organization, along with associated costs.
- BThe understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence.
- CThe quantification of the risk in terms of how much the risk could potentially cost the project or parent organization.
- DThe weighting or prioritization of the risk against all other identified risks within this project or others associated with it.
56Which of the following is a definition of an RFP?
- AA document sent to potential vendors to solicit a bid for a project.
- BA document sent to potential vendors to request information for skills and experience for a project.
- CA document sent to potential vendors to request a commitment for a project.
- DA document sent to potential vendors to solicit information that excludes pricing information for a project.
57A customer has requested additional features for an active project.
Which of the following steps should take place NEXT?- AImplement the requested changes.
- BEvaluate the impact of the changes.
- CUpdate all project documents.
- DSubmit the requested changes to the CCB.
58A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the projects success.
Which of the following risk strategies should the project manager adopt?- AExploitation
- BAvoidance
- CAcceptance
- DMitigation
59A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?- ABusiness case
- BProject charter
- CScope statement
- DProject management plan
60Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?
- ASales clerk
- BMarketing representative
- CTeam lead
- DProduct item
61During the execution phase of a project, a project task has run longer than anticipated.
Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
- A12 days
- B14 days
- C16 days
- D19 days
62A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference.
Which of the following is MOST likely to be the main challenge the influences this decision?- AGeographical factors
- BLanguage barriers
- CCultural differences
- DTechnology factors
63A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project.
Which of the following would the project manager MOST likely do?- APlace a risk on the risk register and arrange a risk review with the appropriate stakeholders to accept and/or mitigate the risk.
- BRaise a purchase order to purchase the licensing and ask the team member to install it.
- CAmend the project scope and raise a project change request to obtain approval of the amendment.
- DAmend the project schedule and work breakdown structures to remove the use of the software from the project.
64A vendor is unable to deliver an order by the specified date.
Which of the following should be the project managers NEXT steps? (Choose two.)- AThe project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.
- BThe project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.
- CThe project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.
- DThe project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.
- EThe project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.
65A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes.
Which of the following should the project manager do NEXT?- AGain approval for the changes.
- BIdentify the approval authority.
- CImplement the changes.
- DCreate an emergency change request.
66A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable.
Which of the following factors will MOST likely influence the communication methods used in the project?- APersonal preferences
- BTechnological factors
- CLanguage barriers
- DCultural differences
67A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions.
Which of the following strategies is the project manager applying?- AAccepting
- BMitigating
- CAvoiding
- DTransferring
68A business has implemented a new online performance management tool that allows functional and project managers to rate employees online.
This action is known as which of the following?- ABusiness process change
- BOrganizational change
- CInternal reorganization
- DBusiness continuity planning
69A project manager needs to track the actual and estimated start and finish dates of all WBS work packages.
Which of the following is a necessary step to record the actual durations?- AEstablish each WBS work package resource.
- BEstablish and set the baseline.
- CEstablish and set the quality gates.
- DEstablish the tollgates.
70Which of the following describes how a project is related to a program?
- AA program is a combination of multiple projects.
- BA program contains an element of the project.
- CA program is a part of a project.
- DA program uses half of the projects budget.
71Which of the following are examples of organizational change? (Choose two.)
- ARelocation
- BScope
- CBusiness process
- DSchedule
- ERisk event
72A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?- AProject schedule
- BCost plan
- CScope statement
- DImpact assessment
73A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?- ACost, schedule, organizational chart, and risks/issues
- BRisks/issues, cost, RACI chart, and action items
- CSchedule, cost, risks/issues, and milestones
- DAction items, organizational chart, schedule, and NDA
74During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendors tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.
Which of the following should have occurred to prevent this issue?- ADuring the planning phase, the project manager should have recognized the relationship between the vendor"™s and project team"™s tasks and adjusted the schedule for the project team to begin activities two months later.
- BThe project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.
- CDuring the project team"™s regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.
- DDuring the project team"™s regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.
75A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies.
Which of the following documents should the project coordinator use?- ARisk register
- BIssue log
- CCommunication plan
- DStatus report
76A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority.
Which of the following effects is this MOST likely to have on the project?- AThe deliverables and quality will remain the same, but the cost will increase.
- BThe deliverables and quality will remain the same, but the cost will decrease.
- CThe deliverables and cost will remain the same, but the quality will increase.
- DThe cost and quality will remain the same, but the deliverables will increase.
77A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.
Which of the following should the project manager do to resolve this issue?- AUpdate the scope management plan.
- BModify the project baselines.
- CImplement change control management.
- DInform the stakeholders of the issue.
78The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.
To alter the pace of the project, which of the following should the project manager do FIRST?- AGive approval for the change requested by the project sponsor.
- BDeny the request from the project sponsor.
- CDocument the change request from the project sponsor.
- DAsk the project sponsor to change the request.
79Which of the following is a schedule that illustrates the duration of an activity?
- AProcess diagram
- BIshikawa diagram
- CGantt chart
- DPareto chart
80Team members have reported that meetings are poorly attended and unproductive.
Which of the following steps can the project manager take to make the meetings more productive?- ADiscontinue the meetings with the poorest attendance.
- BDecrease the length of the meetings.
- CDistribute an agenda before each meeting.
- DDocument team member attendance and report it to management.
81Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.
The project manager should:- Afollow the change process flow and notify the legal department after the change is implemented.
- Bextend a formal invitation to the legal department representative to join the CCB.
- Chold a separate meeting with the legal department representative and ask for approval.
- Dnotify the legal department representative in the event of an upcoming audit.
82A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.
Which of the following is the MOST likely reason?- AEstablished communication plan
- BScope creep
- CResource constraints
- DIterative approach
83In which of the following organizational structures would a project manager have the MOST authority?
- AProjectized
- BStrong matrix
- CBalanced matrix
- DFunctional
84A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility.
Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?- AEmail
- BSocial media
- CText messaging
- DFace-to-face
85A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule.
The project manager is concerned that the requests will lead to:- Aquality control issues.
- Badditional risks.
- Cscope creep.
- Dtime constraints.
86A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?- AProject charter
- BProject management plan
- CProject statement of work
- DProject schedule
87A project manager has noticed poor attendance as status meetings.
Which of the following strategies should the project manager use to improve attendance? (Choose two.)- AProvide an agenda before the status meeting.
- BAdhere to an agenda and scheduled time.
- CAdd non-project-related items to the agenda.
- DAdd and discuss new agenda items throughout the meeting.
- EDiscard the action items at the conclusion of the meeting.
88Which of the following events would MOST likely trigger communications to the largest audience for a given organization?
- ABusiness continuity response
- BQuality audit
- CReplacement of a subcontractor
- DCompletion of a task
89If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?
- AThe project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
- BThe scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.
- CThe scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
- DThe scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.
90Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?- ACompromising
- BSmoothing
- CWithdrawing
- DAccepting
91An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called:
- Aan RFP.
- Ban NDA.
- Can SLA.
- Dan MOU.
92Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
- AProject manager and project scheduler
- BProject coordinator and project sponsor
- CProject champion and project scheduler
- DProject stakeholders and project team
93An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?- ASubmit a new change request.
- BInitiate the regression plan.
- CAdd remediation to the schedule.
- DAccept the new power output.
94A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?- ATell the senior manager the estimation is not available yet.
- BUse the budget from a similar project to generate estimates.
- CAsk a SME for an opinion and propose an estimate.
- DGather the team to immediately generate estimates.
95A program manager informs a project manager that a new, high-priority project has been approved and will need the current projects resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)- AScope management plan
- BConfiguration management plan
- CNetwork diagram
- DProject schedule
- EProject plan
96A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?
- AQuality
- BRegulations
- CSchedule
- Dproject team
97A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the projects success?
- AReduce the scope
- BIncrease the budget
- CDecrease staff
- DUpdate the WBS
98A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?
- ATransfer
- BAccept
- CAvoid
- DMitigate
99A company is hired to perform some of another organizations work. Which of the following types of organizational change is described?
- AOutsourcing
- BBusiness process change
- CShared resources
- DSplit
100A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
- AAdditional resources
- BA gate review
- CA risk register update
- DA performance audit
101A projects key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed?
(Choose two.)- ACost performance parameter
- BProject schedule
- CKPI
- DCorrective action plan
- EWBS
102A project has activities on the critical path that must be completed before other activities can start.
Task A is dependent on Task C before Task D can be completed.
Task A requires task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?- AB, A, D
- BC, B, D, A
- CD, A, C
- DB, C, A, D
103During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.
Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?
- A12 days
- B16 days
- C17 days
- D22 days
104Which of the following job roles is primarily tasked with communicating the project timeline changes?
- AProject scheduler
- BProject manager
- CProject sponsor
- DProject coordinator
105A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early.
Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).
- ACost
- BPredecessors
- CLag
- DDurations
- EResource loading
- FSubtasks
- GFloat
106A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?
- AWait until the change requests are approved by the CCB.
- BApprove the changes because the additional functionality is required to complete the process.
- CSpeak with the project sponsor and provide a detailed analysis of the changes and impacts to the project budget.
- DSchedule the changes as part of the second phase of the project when additional funding will be available and work can be completed.
107The chairperson of the board is visiting from another country and wishes to meet the project team members. The next project team meeting will be held next week, but the chairperson is leaving before the meeting. Which of the following actions should the project manager take?
- ASchedule a conference call for the team meeting and invite the chairperson.
- BArrange an impromptu team meeting with the chairperson.
- CEmail the chairperson the meeting minutes from the scheduled meeting
- DInvite the chairperson to the next project team meeting
108Which of the following are characteristics of a project? (Choose two.)
- AA project is a temporary endeavor.
- BA project provides a unique product, service, or result.
- CA project is an ongoing endeavor.
- DA project involves scheduled maintenance.
- EA project includes life-cycle cost management.
109A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?
- ATransfer
- BShare
- CMitigate
- DAvoid
110Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?
- ASCRUM retrospective meeting
- BSprint planning meeting
- CDaily standup meeting
- DReview meeting
111The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?
- APersonal preference
- BIntra-organizational differences
- CCulture
- DTime zone
112A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?
- ARisk register
- BPost-mortem analysis
- CIssue log
- DProcurement report
113A company decides to give a large section of its development project to another firm to manage and complete because that firm has the appropriately skilled resources to execute the work. This approach is referred to as:
- AResource leveling
- BStaff Augmentation
- CWork relocation
- DOutsourcing
114An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast- tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?
- AMOU
- BMOA
- CSOW
- DSLA
115Which of the following roles has approval authority for project funding?
- AChampion
- BChief Financial Officer (CFO)
- CProject Management Office (PMO)
- DSponsor
116A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?
- AAccept risk
- BMitigate risk
- CAvoid risk
- DExploit risk
117The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis. Which of the following would be the MOST effective means to do this?
- AInstant messaging
- BVideo conference
- CPhone call
- DCollaboration website
118Which of the following is an example of a project?
- APurchasing pedometers from local retail stores for employees
- BImplementing a health awareness program at an organization
- CConducting semi-annual blood drives at an organization
- DPresenting a scripted workshop at an organizations three locations
119A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?
- AUpdate
- BScheduling
- CKickoff
- DReview
120A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?
- AIssue log and process diagram
- BResource analysis and Gantt chart
- CStakeholder analysis and communication plan
- DScatter chart and scope analysis
121A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?
- AZero
- BOne
- CTwo
- DThree
122A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do NEXT?
- ARF1
- BRFP
- CRFQ
- DChange request
- ERequest for bid
123A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?
- AReview the PERT chart and evaluate if the task is a critical dependency.
- BReview the PERT chart and evaluate if the task is a discretionary dependency.
- CReview the PERT chart and evaluate if the task is a real dependency.
- DReview the PERT chart and evaluate if the task is an external dependency.
124A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The PM approaches one team member to determine why people are declining. The team member indicates the project manager scheduled the meeting at a time when employees typically have permission to take a nap. Which of the following is the project manager facing?
- ALanguage barriers
- BTime zones
- CCultural differences
- DPersonal preferences
125Which of the following vendor documents specifically address quality? (Choose two.)
- ALOI
- BSLA
- CWarranty
- DPO
- ENDA
126A project manager has been assigned a complex project and does not know all the activities required to complete it.
Which of the following if the BEST approach to determine the work packages for the WBS?- ABrainstorming
- BAnalogous
- CBottom-up
- DForward pass
127Which of the following documents need to be updated as events occur during a project? (Choose two.)
- AChange request
- BRisk register
- CMeeting minutes
- DIssue log
- EStatus report
128During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?
- AChange request
- BRisk mitigation
- CChange control
- DScope creep
129A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?
- AProject schedule
- BAction items
- CProject charter
- DCommunication plan
130A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?
- AAdd durations.
- BAdd the start and finish dates
- CAdd tasks.
- DAdd resources.
131A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:
-> Coordinate project schedule
-> Manage to the triple constraint
-> Provide performance feedback to team members"™ managers
Which of the following types of organizational structures did the new project manager MOST likely join?- ABalanced matrix
- BStrong matrix
- CFunctional
- DProjectized
132Which of the following shows projected project expenditures?
- AWork breakdown structure
- BCash flow schedule
- CCash burn rate
- DBudget milestone
133A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would
BEST communicate the need for a WBS to the other managers? (Choose two.)- AUsing the WBS will help prevent work from slipping or being forgotten.
- BThe WBS will be required on very large projects.
- CThe WBS will be required if the project manager has the time available to complete it.
- DThe WBS will aid in determining which resources are required for the project.
- EThe WBS is the best way to determine risks of the project.
134A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?
- AIssue log
- BAction items
- CDashboard information
- DCommunication plan
135Which of the following elements should be included on a responsibility assignment matrix?
- AResponsible, accountable, consulted, informed
- BResource, accountable, signoff, input
- CResponsible, accurate, confidential, informed
- DResource, accountable, consulted, informed
136The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes.
Which of the following best describes what the PM should work on FIRST?- AProject charter
- BProject schedule
- CMeeting agenda
- DResponsibility assignment matrix
- ERisk register
137Which of the following charts is a graphical representation of the causes of a specific event?
- AHistogram
- BScatter
- CFishbone
- DGaant
138While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:
- Aquality plan.
- Bproject management plan.
- Crisk register.
- Dprocess diagram.
139A project team on a four-year project has a shortage of workspace within an office. Which of the following is the MOST viable solution for the project team while ensuring work hours are not wasted?
- ASecure a new facility, permit remote work, and reduce staff.
- BReduce staff, implement BYOD, and permit remote work.
- CImplement BYOD, secure a new facility, and utilize shared workspaces.
- DPermit remote work, utilize shared workspaces, and implement BYOD.
140A project is in the initiation phase. Which of the following tasks will take place during this phase?
- ADevelop a WBS.
- BDefine the project requirements.
- CCreate a project charter.
- DAcquire the project resources.
141A team member has completed an assigned task. Which of the following roles should be notified FIRST?
- AProject sponsor
- BKey stakeholders
- CProject manager
- DProject team
142A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?
- ASLA
- BSOW
- CChange Request
- DRFP
143A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?
- ASubmit a change request.
- BEvaluate the impact of the change.
- CGet approval from the CCB.
- DCommunicate the change to stakeholders.
144Using Scrum, which of the following are discussed in a daily standup meeting?
- AWhat was done yesterday, what is planned for today, and what roadblocks need to be removed
- BWhat was done yesterday, what is planned for the week, and what issues were resolved
- CWhat was done yesterday, what is planned for today, and what deliverables were completed
- DWhat was done yesterday, what is planned for this week, and what items from the backlog are priority
145A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.
Which of the following calculations accurately shows the critical path?
- A20 days
- B39 days
- C49 days
- D52 days
146New stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
- AIdentify and document the risk.
- BEvaluate the impact and justification.
- CImplement the change.
- DUpdate the documents and plans.
147A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?
- AVendors
- BKey stakeholders
- CProject team
- DBusiness analysts
148Which of the following inherently affects quality standards?
- ASLA
- BMOA
- CMOU
- DWBS
149At a weekly project team meeting, it is apparent the project is over budget. The project manager needs to determine the reason for this issue. Which of the following documents should MOST likely be analyzed to obtain the answer?
- AProject charter, organization chart, scope statement, and issue log
- BDashboard information, action items, project schedule, and status report
- CProject management plan, scope statement, communication plan, and meeting agendas
- DProject schedule, project management plan, communication plan, and issue log
150A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?
- AFast-track the tasks.
- BUtilize positive float.
- CCrash the schedule.
- DRemove the critical path
151A project is taking more effort than anticipated. Which of the following constraints will MOST likely be affected?
- AScope
- BTime
- CQuality
- DCost
152A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:
- Ainternal project team.
- Bkey stakeholders.
- Caffected team members.
- Dfull project team.
153An industry leader may be joining the project team and can potentially provide additional expertise. Which of the following strategies should the project manager employ?
- AExploitation
- BAcceptance
- CValidation
- DTransfer
154A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?
- AReduced quality
- BReduced scope
- CReduced risk
- DReduced timeline
155The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?
- AAhead of schedule and over budget
- BBehind schedule and under budget
- CAhead of schedule and under budget
- DBehind schedule and over budget
156A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?
- ATime
- BSchedule
- CScope
- DCost
157A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?
- AResource loading
- BResource leveling
- CPrioritizing tasks
- DAllocating resources
158Which of the following would indicate a project manager is working in a matrix-based organization?
- AThe project manager has full authority over resources and the project.
- BThe project manager has no authority over the project resources and limited-to-no authority over the project.
- CResources align to the project, report to the project manager, and have no functional home at the end of the project.
- DResources report to business area functional managers and return to the functional area at the end of the project.
159A project team is spread between two countries on different continents. Which of the following factors are MOST likely to influence communication methods selected for the communication plan? (Choose two.)
- AInterorganizational constraints
- BPersonal preferences
- CLanguage barriers
- DCultural differences
- EConfidentiality constraints
160Two team members approach a project manager with different ideas for completing a task. After listening to the team members' ideas, the project manager does not choose either one and requires both members to finish the task as originally planned. Which of the following conflict resolution techniques is the project manager applying?
- AAvoiding
- BSmoothing
- CForcing
- DCompromising
161A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:
- Adurations
- Btasks
- Ccritical path
- Dresources
162A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?
- APareto chart
- BFishbone diagram
- CProcess diagram
- DRun chart
163A project has a Ð’ÐС of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do
NEXT?- AAdd the required work to complete the project behind $892,500.
- BEvaluate the impact and justify adding new work to the project.
- CObtain approval from the CCB.
- DRequest a budget increase of $170,000.
164A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?
- AInitiation
- BPlanning
- CMonitor and control
- DClosing
165A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project.
Which of the following MOST likely occurred?- AThe company received a C&D.
- BA higher-priority project needed the expertise.
- CThe new member did not sign an NDA.
- DAn SLA prevented new team members.
166In which of the following categories does a business process change fit?
- AProject change
- BOrganizational change
- CGeneral change
- DDepartmental change
167A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon. Which of the following is the BEST explanation?
- AIn the beginning, projects entail a degree of uncertainty that needs to be specified.
- BIn the beginning, projects have start and finish dates that require elaboration.
- CIn the beginning, projects are part of a program that requires coordination.
- DIn the beginning, projects start with detailed inputs that need to be explained.
168A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is the
MOST likely reason for the failed inspection?- AThere were insufficient resources assigned to the task.
- BThe prior document version was not reviewed.
- CVersion control processes were not applied.
- DThe CCB was not contacted.
169A project manager has received a change order that will reduce a project's timeline and budget. However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?
- AThe reduced timeline will impact the quality of the deliverables because the amount of time to test will be reduced.
- BThe reduced budget will result in reduced resources, which will lead to a strong matrix organizational structure being used.
- CThe reduced timeline will decrease risk, resulting in an increased contingency reserve.
- DThe reduced budget will cause the project manager to reject the change order.
170A risk with a high probability and medium consequence to a project has been identified. In response, the project manager has purchased an insurance plan with the intent to provide additional funds if the risk is realized. There is no risk to the schedule or scope. Which of the following types of risk strategies is this an example of?
- AAccept risk
- BTransfer risk
- CMitigate risk
- DExploit risk
- EAvoid risk
171Which of the following is described as placing responsibility for addressing the potential effects of an uncertain future event on an entity outside the organization?
- ARisk avoidance
- BRisk transfer
- CRisk exploitation
- DRisk mitigation
172Team members have reported poor sound quality during critical, time-sensitive conference calls. Which of the following may be a more effective means of communication?
- AOne-on-one meetings
- BProject wiki
- CText messages
- DSocial media
173A project manager is creating the monthly report for top management. The project manager has collected the information below:
AC = 100 -
PV = 80 -
EV = 120 -
Based on this information, the CPI reflects which of the following about the project?- AIt is under budget.
- BIt is over budget.
- CIt is ahead of schedule.
- DIt is behind schedule.
174In a project with a Ð’ÐС of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?
- AThe project is under budget and ahead of schedule.
- BThe project is over budget and ahead of schedule.
- CThe project is under budget and behind schedule.
- DThe project is over budget and behind schedule.
175Which of the following risk strategies is represented by the purchase of insurance?
- AMitigate
- BAccept
- CTransfer
- DAvoid
176Which of the following is a team-building stage that involves the team learning to trust one another's abilities and begin working together as a productive group?
- ANorming
- BForming
- CStorming
- DPerforming
177When forming a project team, there are a number of phases.
When a project team is productive and effective this phase is known as which of the following?- AForming
- BNorming
- CPerforming
- DStorming
178The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders's business unit.
Which of the following actions should the project manager take?- AInitiate change control.
- BFollow communications plan.
- CManage project quality.
- DPrepare a performance report.
179A project has just finished performance testing and found that the application can only handle 100 concurrent users where the requirement was to handle 500 concurrent users.
In which of the following components of the project plan should this be documented?- AScope statement
- BIssues log
- CWBS
- DChange form
180A project team has determined it will need to source data from a system that was not part of the project scope.
The role of the project manager is to analyze which of the following impacts?- ATechnical design, schedule, and budget
- BBusiness process impacts and resourcing
- CNew software and hardware requirements
- DSchedule, budget, and quality
181A project manager has identified a minor skills gap in the operational team that will end up supporting the project solution.
Which of the following is the BEST risk mitigation strategy that the project manager should use?- AOrganize adequate training and have one of the operational staff as part of the project team.
- BRaise a risk in the risk register, identify the likelihood and the consequence of the risk occurring.
- CHave the project adequately document the solution and ensure a transition is in place.
- DEscalate this as an issue to the project control board and ensure that there is adequate discussion.
182The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project.
Which of the following schedule compression techniques should be used by the project manager?- ARescheduling
- BCrashing
- CRebaselining
- DControl scope
183The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.
This type of analysis is an example of which of the following?- ACost performance index
- BRisk mitigation
- CSchedule variance
- DCost variance
184A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis.
This type of modeling relies on:- APrioritizing the specific event.
- BVariance in the process over time.
- CCauses of a specific event.
- DDetermining the number of events.
185The design activity of a project has the following cost attributes:
PV = 100,000 -
EV = 20,000 -
AC = 90,000 -
Based on this scenario, calculate the schedule variance.- A-80,000
- B-70,000
- C10,000
- D120,000
186Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account.
Which of the following should the project manager do to ensure stakeholder expectations are met?- AEnsure that Ann is involved during the testing phase of the project so she can call out functional gaps.
- BOrganize a walkthrough of the solution and ensure face-to-face updates occur every two weeks.
- CEscalate the issue to the project steering committee that Ann is criticizing the project quality.
- DOrganize a requirements workshop to capture any gaps.
187A post implementation review is being performed as a part of project closure. Which of the following are applicable areas that the review should cover? (Choose two.)
- ALessons learned during the project.
- BProduce operational support documentation.
- CGathering and centralizing project documentation.
- DOrganizing the communication of project closure.
- EIdentify the key project achievements.
- FProvide a recap of the overall solution.
188Which of the following techniques modifies the schedule based upon resource constraints?
- ACritical Chain Method
- BCritical Path Method
- CArrow Diagramming Method
- DPrecedence Diagramming Method
189Resources for a project report to a project manager and a functional manager.
The organizational structure is:- AMatrix
- BAd hoc
- CFunctional
- DProjectized
190The final project report should contain which of the following?
- AMinutes of all the project meetings
- BProject design documentation
- CDetailed breakdown of the schedule
- DSummary of the project cost
191Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
- AManaging change
- BFast tracking
- CRolling wave planning
- DCrashing
192The project team is not comfortable moving an expensive material.
A third party is hired to move the material. This is an example of risk:- ATransference
- BSharing
- CAvoidance
- DAcceptance
193The project's network map has a loop with multiple project outcomes.
This is the result of which of the following scheduling tools?- AEstablishing project schedule baselines
- BCritical Path Analysis
- CCritical Chain Method
- DGraphical evaluation and review technique
194Which of the following tools would a project manager use to determine the root cause of an issue?
- APareto Chart
- BIshikawa Diagram
- CHistogram
- DMonte Carlo Analysis
195Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?
- ACritical Path Method
- BArrow Diagramming Method
- CCritical Chain Method
- DPrecedence Diagramming Method
196Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?
- ACritical Path Method
- BCritical Chain Method
- CArrow Diagramming Method
- DGantt Chart Method
197A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?
- AAssign a different team member to resolve the issue before the next status meeting.
- BReview the issue with the assigned team member to determine a due date.
- CSet a due date to resolve the issue and inform the assigned team member.
- DReport the team member to a functional manager for disciplinary action.
198Three IT companies have agreed to summarize their efforts as a common organization to generate new businesses in the IT cloud computing industry. Which of the following is the type of organizational change described?
- AExpansion
- BRightsizing
- CMerger
- DOnboarding
199A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?
- AProjectized
- BBalanced matrix
- CFunctional
- DStrong matrix
200A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.
Which of the following represents the cost variance for both project completions?
Which of the following represents the cost variance for both project completions?
- A-$4.8K and -$7K
- B-$4.9K and $7K
- C$4.8K and -$7K
- D$4.8K and $7K
Informações
- Descrição
- LPI IT Quiz sobre Project + Part 1, criado por Nope Nope em 21-12-2020.
- Autor
- Nope Nope
- Idioma
- English
- Visualizações
- 18
- Etiquetas
- Avaliação
- Ainda sem avaliações Avalie este quiz