1A daily standup Scrum meeting is BEST accomplished in a:
- Atelephone conference.
- Bgroup email.
- Cface-to-face meeting.
- Dvideo conference.
2A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?
- AProject communication plan
- BProject status report
- CProject management plan
- DProject backlog
3When an action is taken on a risk, which of the following is being done and which document needs to be updated?
- AMitigating risk, and the risk register should be updated
- BAccepting risk, and the risk review document should be updated
- CAvoiding risk, and the risk review document should be updated
- DExploiting risk, and the risk register should be updated.
4A project schedule lists a resource as 50% because it likely:
- Ais a shared resource.
- Bdepict a resource shortage.
- Csignifies overallocation of a resource.
- Dnotes underallocation of a resource.
5A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?
- ATeam Building
- BTeam Selection
- CResource loading
- DResource leveling
6Which of the following is a reason for assessing risk in a project?
- ATo identify new tasks
- BTo shorten the project timeline
- CTo avoid rework
- DTo establish a budget
7The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST likely to influence communication methods across the project?
- APersonal preferences and message content
- BLevel of message/report detail and confidentiality constraints
- CTime zones and language barriers
- DTechnological and criticality factors
8A project team is defining detailed risks. Which of the following project phases is taking place?
- AInitiation
- BMonitor and control
- CExecution
- DPlanning
9Which of the following statements are correct regarding project management? (Choose two.)
- AA project can be part of an organization's program management.
- BAn organization's portfolio will include programs.
- CA program has a defined start and finish.
- DAn organization's portfolio is a temporary and unique endeavor.
- EA project portfolio will be managed under program management.
10A client has provided a list of deliverables to include in the project scope. Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?
- ARequirements traceability matrix
- BGantt chart
- CSWOT analysis
- DProject charter
11A minor change to the baseline schedule is required. This change will be the second minor modification to the schedule. Which of the following is the appropriate version number?
- A0.3
- B1.2
- C2.0
- D3.0
12Which of the following is used to perform a root cause analysis?
- AIshikawa diagram
- BBar chart
- CPareto diagram
- DScatter plot
13Which of the following documents is typically signed by the vendor and includes a reference for how customers internal information will be protected?
- AMOU
- BNDA
- CSOW
- DSLA
14A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?
- AGo over the meetings objectives and agenda.
- BBrief the team on which tasks have fallen behind schedule and where the project has slack.
- CRefer to the risk register to map the risks to issues and mitigation strategies.
- DReview the issue log with the project team and identify potential risks.
- EReview an Ishikawa diagram with the project team to determine possible causes and effects.
15A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?
- ACrashing the schedule
- BPrioritizing tasks
- CDetermining milestones
- DDeveloping sprints
16A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?
- ADraft a C&D letter and send it to vendor.
- BReview the MOU with the vendor.
- CAsk the legal departments to draft a non-complete agreement for the vendor to sign.
- DMeet with the finance department to prevent the vendor from sending invoices.
17During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:
- Athere is unfamiliarity with the project structure.
- Bthere is a lack of trust among team members.
- Cthere are minimal team decisions.
- Dthere is no engagement of the team by the project manager.
18A project manager procures additional resources from a local company. Which of the following-describes this event?
- AReorganizing
- BOnboarding
- COffshoring
- DOutsourcing
19In which of the following situations is a project manager MOST likely to use a process diagram?
- AWhen describing a new business idea for the team to review
- BWhen describing a new business workflow for the team to implement
- CWhen describing a new business project for the team to implement
- DWhen describing a new business acquisition for the team to review
20A project has passed a phase-gate, and the new phase is ready to begin. Which of the following is the MOST appropriate method to communicate the transition to team?
- AKickoff meeting
- BOne-on-one meetings
- CVoice conferencing
- DInstant messaging
21A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications. Which of the following items BEST describes the unmet objective?
- ASchedule
- BMilestone
- CGate
- DTask
22A project manager at a projectized organization is finishing the objective goals for the appraisal process. Performance goals have been identified for colocated individuals working on the team. Which of the following is the appropriate communication method for relaying the goals to the team members?
- AEmail
- BDistribution of printed media
- CFace-to-face
- DVideo conferencing
23During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?
- AAsk the team member to move to a different test environment.
- BAsk the team member to refrain from testing the scenarios.
- CRevisit the risk management plan and provide corrective actions.
- DRevisit the contingency plan and provide corrective actions.
24A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of the following should the project manager do NEXT?
- ADetermine the expected duration of the rework and complete a charge request to modify the project baselines.
- BNotify the project sponsor to schedule and facilitate a team meeting to rework the design documentation.
- CDetermine the expected duration of the rework with any associated quality control activities and add the duration to an updated version of the WBS.
- DUpdate the master project schedule, and distribute it all stakeholders in accordance with the project communications plan.
25A project manager must create documentation before the project kickoff meeting. Which of the following documents will identify the project, introduce the project manager, and establish authority in the project?
- AResponsibility matrix
- BResource allocation plan
- CProject charter
- DStatement of work
26Which of the following are mutually binding project documents? (Choose two.)
- AQuotation
- BLetter of intent
- CProposal
- DEvaluation
- EWarranty
- FCharter
27An organization has determined that all projects must use a remote dashboard to allow portfolio management. Which of the following would enforce this directive?
- AProject management office
- BProject sponsor
- CProject manager
- DProject coordinator
28A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call. Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?
- ADefine the communications plan.
- BRecord the missed tasks on the issue log.
- CProvide meeting minutes after each call.
- DComplete a fishbone diagram.
29A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?
- AIncident response
- BQuality control
- CResource changes
- DBusiness continuity response
30A project manager wants to ensure that a detailed overview of a new kitchen fits the client's standards. Which of the following will the project manager MOST likely work to accomplish?
- ADetailed project schedule to deliver on time
- BGate reviews to capture the progress and feedback
- CReasonable number of changes to maintain quality
- DWide range of time between the start and end of the installation
31A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?
- AProcess diagram
- BChange control plan
- CBalanced scorecard
- DSWOT matrix
32Which of the following risk strategies prevents a risk from impacting a project?
- AAccept risk
- BMitigate risk
- CAvoid risk
- DTransfer risk
33An active project has a CPI of 0.92. Which of the following can be determined?
- AThe project is currently over budget.
- BThe project has a budget surplus.
- CThe project is ahead of schedule.
- DThe project is behind schedule.
34A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?
- ARisk identification
- BRisk quantification
- CRisk planning
- DRisk response
35A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations.
The project team must ensure completion of the:- Abusiness continuity plan.
- Bincident response plan.
- Cdisaster recovery plan.
- Drisk management plan.
- Equality management plan.
36While developing a project schedule, the project manager is attempting to sequence the following tasks:

- AF, C, A, E, B, D
- BF, E, C, B, A, D
- CF, A, B, C, E, D
- DD, B, E, F, C, A
37Which of the following represents additional unauthorized requirements from the client?
- AScope creep
- BChanging scope baseline
- CChange request
- DGold plating
38A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?
- AIssue log
- BStatus report
- CRisk register
- DSOW
39Which of the following describes KPIs? (Key Performance Indicators)
- AAnalyses of organizational strengths and weaknesses
- BGraphical representations of process flow
- CElements against which performance can be measured
- DCollaboration platform tools
40Before a team can start on a sprint, they will need to:
- Acreate a set of iterations to work on and prioritize.
- Bgenerate an icebox of work items to review.
- Creview the backlog of work items to prioritize.
- Dtake client requirements and draft them into a task list.
41A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
- ARevise the project plan.
- BUpdate the issue log.
- CRequest additional funding.
- DIssue a change request.
42Which of the following is the MOST appropriate communication method for a highly confidential message to a Multilanguage global project team?
- AEncrypted email
- BFace-to-face communication with a translator
- CSocial media communication through a secure connection
- DVoice conferencing
43Which of the following defines the minimum level of engagement of a stakeholder?
- APassive
- BInvested
- CContributing
- DInterested
44At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BEST accomplish this?
- ATeam contract
- BCorrective action plan
- CUser acceptance policy
- DMOU
- ESLA
45A company is in the process of combining the human resources and marketing departments. Which of the following describes this change?
- ABusiness process change
- BBusiness merger
- CInternal reorganization
- DInterorganizational change
46A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the following should the team consult to determine which actions to take?
- AIncident response plan
- BRegression plan
- CProgress plan
- DBusiness continuity plan
47A senior developer abruptly resigned without notice. Because of the senior developer's expertise, the active task workload was substantial.
This would likely impact the project's: (Choose two.)- Aenvironment
- Bscheduling
- Crequirements
- Dquality
- Escope
- Fbudget
48Which of the following information does the project risk register typically contain?
- AType of risk, identified risk, risk response, impact of risk, severity of risk
- BType of risk, project task, risk response, impact of risk, severity of risk
- CType of risk, identified risk, risk response, project schedule risk, severity of risk
- DType of risk, identified risk, risk response, impact of risk, risk avoidance
49A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?
- AIssues log
- BChange log
- CStatus report
- DMeeting minutes
50Which of the following documents ensures two parties do not share contractually binding information?
- AC&D letter
- BRFI
- CNDA
- DMOU
51Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task
B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed.
Following are the durations of all tasks:
- AA, D, C, G
- BA, B, H, G
- CA, D, E, F
- DA, B, C, G
52Which of the following documents should be used FIRST when addressing a vendor that is not complying with the project deliverables?
- ASLA
- BProject charter
- CRisk register
- DRFP
53A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?
- AIndividually call all project team members.
- BSend an email to all project team members.
- CSchedule a conference call.
- DSchedule a face-to-face meeting.
54A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale.
Which of the following is the MOST likely reason the project manager would be unaware of the team member's decreased morale?- AThe project manager did not pay attention to visual cues.
- BThe project manager did not perform active listening.
- CThe project manager did not prioritize team member concerns.
- DThe project manager did not visit the project's international office locations.
55A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?
- ADescription, cost difference of the replacement, and WBS
- BDescription, justification, and cost
- CCost difference of the replacement, justification, and communications plan
- DDescription, quality impact, and cost
56Which of the following documents serves the primary purpose of requesting details about a vendor's capabilities?
- ARFP
- BRFI
- CRFQ
- DNDA
57A Chief Executive Officer (CEO) has approached a project team member to request a project change.
Which of the following would be the BEST step for the project manager to take to prevent scope creep?- ADeny the CEO"™s request.
- BImplement the project change.
- CSubmit the request to the CCB.
- DAsk the CEO to follow the communications plan.
58Which of the following is a characteristic of a project?
- AIt solves a business problem.
- BIt created a unique service.
- CIt has a definite beginning and end.
- DIt adheres to a formal framework.
59A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager.
Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?- ASend an email to quality assurance and copy the project team.
- BCall a meeting to hand off the deliverable to quality assurance.
- CHold a conference call to a review the next deliverable with the project team.
- DSend an email to the project sponsor and copy the project team.
60A project manager has been experiencing resistance from a group of stakeholders.
With which of the following should the project manager consult to reduce friction going forward?- AProject scheduler
- BProject coordinator
- CProject sponsor
- DProject management office
61New requirements were introduced during the execution phase of a project, and the team believes this will impact the project cost but not the timely completion of project deliverables.
Which of the following is the BEST way for the PM to validate the assessment?- AAsk the team for estimates, and review the project schedule and budget.
- BAsk the team to review the product scope and validate its impact on the schedule and quality.
- CAsk the team for estimates, and review the cost management plan.
- DAsk the team to perform a SWOT analysis, and validate the assessment.
62Which of the following conflict resolution techniques relies on establishing areas of agreement rather than disagreement?
- ASmoothing
- BCollaborating
- CCompromising
- DAvoiding
63During the planning phase of a construction project, the project team discovers the site is the nesting area of rare birds, and construction could disrupt the birds' patterns. Lobbyists would like the team to move the project down the road.
Which of the following constraint and influencer types are involved in this scenario?- AEnvironmental; resources
- BEnvironmental; stakeholders
- CDeliverables; resources
- DDeliverables; stakeholders
64Which of the following features describe a projectized organization? (Choose two.)
- AThe project manager has less authority over the project team than in a strong matrix.
- BTeam members are solely dedicated to project activities.
- CThe functional manager has full authority over the project team members.
- DThe project manager has full authority over the project team members.
- ETeam members from various departments are assigned to the project.
65Which of the following are the BEST risk analysis tools to determine a project's risk level? (Choose two.)
- AFishbone diagram
- BRACI matrix
- CMonte Carlo
- DProcess flowchart
- EExpert judgment
- FProject dashboard
66A project manager is procuring new equipment from a vendor. The vendor requires a physical signature on all purchase orders. Which of the following should the project manager do to order the equipment quickly? (Choose two.)
- AMail the purchase order and follow up with a phone call.
- BFax the purchase order and follow up with a phone call.
- CDrive to the vendor if local and provide a signed purchase order.
- DScan and send the purchase order and follow up with a phone call.
- ERequest a courier from the vendor to pick up the purchase order.
67Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.
Which of the following MOST likely explains this issue?- ARisks were not identified.
- BRisks were not mitigated.
- CRisks were not exploited.
- DRisks were not communicated.
68A new contractor joining the project team is an example of:
- Aoffshoring
- Boffboarding
- Crightsizing
- Doutsourcing
69A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
-> Project description
-> Draft project timeline and schedule
-> Rough milestones
-> Draft project budget
-> Draft resources required
-> High-level risk review
Which of the following sections should be included in this document?- ABusiness information
- BFull risk assessment results
- CDraft work breakdown structure
- DFull resource requirements
70A primary work location is unsafe due to a gas leak. The project manager has implemented the business continuity plan and authorized relocation to an alternate site.
Which of the following should be notified?- ASponsor
- BPMO
- CAffected team members
- DProject team
71A resource is assigned to two projects with two scheduled tasks that complete at the same time.
This is known as:- Ashared resource contention
- Bintraproject resource contention
- Cinterproject resource contention
- Ddedicated resource contention
72A PM is reviewing bids from vendors and has a question.
Which of the following documents should the PM use to obtain a response?- AProject schedule
- BRFP
- CQuotation
- DRFI
73A team member has completed a project task. Which of the following is the FASTEST method to communicate the task completion?
- ASocial media
- BEmail
- CInstant messaging
- DTeam meeting
74Which of the following describes some of the features of the Agile methodology?
- AIt uses a direct approach, Gantt charts, and a ticketing system.
- BIt uses an indirect approach, spreadsheets for documentation, and change request documents.
- CIt uses an iterative approach, backlogs, and burndown charts.
- DIt uses a step-by approach, an issue log, and pie charts.
75An organization needs a vendor to provide a solution. The organization can only describe its goals but not how to accomplish the work.
Which of the following types of procurement should be used?- ARequest for information
- BRequest for quote
- CRequest for bid
- DRequest for proposal
76Which of the following captures unforeseen activities throughout the project that need attention and resolution?
- AGantt chart
- BAction items
- CProject schedule
- DMeeting minutes
77Which of the following project phases would MOST likely include creating a transition plan?
- AClosing
- BInitiation
- CExecution
- DPlanning
78The Chief Executive Officer (CEO) has announced that the hardware division will be sold to another company.
The sale of this division is an example of which of the following?- AOutsourcing
- BRelocation
- CBusiness process change
- DBusiness merger
79When closing a project, which of the following must be completed to allow team members to return to their designated departments?
- APerform retrospective
- BRelease resources
- CObtain sign-off from the sponsor
- DClose contracts
80A project manager has received numerous complaints from staff concerning poor service provided by a vendor.
Which of the following steps should the project manager take FIRST to correct the problem?- AReview the SOW with the vendor and terminate the vendor
- BNotify the key stakeholders of the problem and send a C&D letter to the vendor
- CNotify the vendor of the complaints and review the SLA with the vendor
- DReview the acceptable use policy with the vendor before requesting termination of the vendor's employee.
81Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project's current status.
Which of the following types of reports should the project sponsor use to quickly summarize the status report data?- APie chart
- BRun chart
- CProject schedule
- DDashboard information
82A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities.
The constraint described in this scenario is:- Acost
- Benvironmental
- Cscope
- Dscheduling
83A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it.
Which of the following steps of the control was missed?- ACommunicate the change
- BQuality check
- CImplementation
- DEvaluate impact and justification
84Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work.
Which of the following management styles is the project manager MOST likely using?- AExploitive
- BRetrospective
- CParticipative
- DAuthoritative
85Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Choose two.)
- APlanned value
- BSchedule variance
- CAcceptable variance
- DCost variance
- EEarned value
86The project manager needs to motivate the team; however, there is an insufficient budget for awards.
Which of the following motivating agents is the MOST appropriate option the project manager can utilize?- AReduce the workload
- BReplace resources
- CExtend the timeline
- DProvide additional responsibility
87A project manager needs status on the project timeline.
Which of the following team members should provide an update?- AProduct owner
- BBusiness analyst
- CScheduler
- DSponsor
88A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays.
Which of the following is the BEST risk response strategy?- AExploit
- BEnhance
- CMitigate
- DCommunicate
89Under an Agile methodology, standup meetings occur:
- Adaily
- Btwice daily
- Cweekly
- Dad hoc
90A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.
Which of the following are MOST likely missing from the project? (Choose two.)- AProject charter
- BOrganizational chart
- CScope document
- DStatus report
- EBusiness case
- FProject plan
91A project manager is required to maintain various documents and procedures.
Which of the following require ongoing attention and periodic updates?- AProject charter
- BChange requests
- CProject management plan
- DCommunication plan
- EProject SOW
92A meeting has taken place with quality assurance tram members and the project manager.
Which of the following events would MOST likely have triggered the meeting?- AAudit
- BRisk register update
- CTask completion
- DResource change
93A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:
- Aproject management plan
- Bscope statements and issue log
- Cproject dashboard and status report
- Daction items and meeting minutes
94A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter:
-> Project title description
-> Preassigned resources
-> Budget
-> WBS
-> Measurable project objectives
Which of the following components should be a part of the project management plan instead of the project charter?- AProject title and description
- BPreassigned resources
- CBudget
- DWBS
- EMeasurable project objectives
95Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?
- AEmail and instant messaging to project team members and the project team members and the project sponsor
- BText messages to and voice conferences with all stakeholders and project team members
- CVideo conferences with key stakeholders and the project champion
- DInstant messaging to the project coordinator and project scheduler
96A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project.
The project manager must schedule the review of the phase and have the stakeholders present.
This review is referred to as:- Achange management
- BA milestone
- Ca tollgate
- Dan incident response
97A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported.
Which of the following is MOST appropriate for the project manager to do NEXT?- ARefer to the contingency plan
- BConduct an immediate emergency team meeting
- CPerform a SWOT analysis
- DImplement the risk response plan
98As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if the project manager has a true management plan.
Which of the following documents should be reviewed FIRST to uncover the issue?- ACommunications plan
- BScope statement
- CProject management plan
- DOrganizational chart
99Two companies have merged. Which of the following may impact the project manager's communication methods after the merger?
- AUpdates to issues logs
- BIncrease in change requests
- CChanges to stakeholder requirements
- DUpdates to the WBS
100Despite receiving regular updates, a sponsor learns a project recently slipped.
Which of the following documents can the sponsor review to determine the project"™s performance? (Choose two.)- AStatus report
- BCommunication plan
- CIssue log
- DProject schedule
- EAction items list
- FRisk register
101A new corporate policy was approved that will positively affect the project.
Which of the following should the project manager do FIRST?- ASchedule the change
- BReview the communication plan
- CUpdate the issue log
- DUpdate the risk register
102Given the following sprint:
Which of the following charts BEST demonstrates the decreasing number of Not Started items for the sprint depicted above?
- AGantt chart
- BPareto chart
- CScatter chart
- DBurndown chart
103When developing a project schedule, which of the following tools would be MOST beneficial?
- AGantt chart
- BNetwork diagram
- CFishbone chart
- DChain diagram
104Based on the table below:
Which of the following is the critical path if Task B has extended to ten days?
- A21 days
- B23 days
- C24 days
- D26 days
105Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?
- ARFP
- BRFQ
- CRFI
- DSOW
106Which of the following charts is a mathematical diagram used to display values for two variables for a set of data?
- AHistogram
- BFishbone
- CGantt
- DScatter
107Expenditure tracking helps with cost:
- Areporting
- Bscheduling
- Cdiscounting
- Dfloating
108On an OBS chart, there is a dashed line between some team members and the project manager, and there is a solid line connecting other members to the project manager. Additionally, some employees at a lower level on the chart have no connection to the project manager.
Which of the following does this signify?- AHorizontally aligned organization
- BVertically aligned organization
- CMatrix aligned organization
- DProject aligned organization
109A project manager is determining a project's critical path to report the projected completion date to stakeholders.
Which of the following information will be required? (Choose two.)- ACosts
- BDependencies
- CSchedules
- DDurations
- EHolidays
- FMilestones
110A project manager has developed the initial schedule for an upcoming project.
Using the attached schedule, which of the following is the critical path?
- A12 days
- B14 days
- C16 days
- D17 days
111A diagram or chart is required to illustrate data differences given the following:
1. The diagram or chart must track at least two variables to determine the relationship between independent variables and include a regression or trend line.
2. The diagram or chart should include cause and effect analysis and investigate historical information.
Which of the following should be used given these requirements?- APareto Chart
- BIshikawa Diagram
- CHistogram
- DProbability distribution
- ERun chart
- FScatter chart
112During the planning phase, the project manager meets with the project team to determine the tasks and their relationship.
Which of the following should the project manager receive from the team members? (Choose two.)- ADurations
- BStart/finish dates
- CDependencies
- DResources
- EBaseline
113Project status meetings have poor attendance. A SME from the hardware team dominates the meetings when questions are asked, not allowing input from other members.
Which of the following steps should the PM take to make the meetings more productive? (Choose two.)- AFacilitate the meetings by adhering to the agenda.
- BEncourage interaction among team members during the meetings.
- CEnsure meetings minutes are accurately recorded.
- DAdjust the number of meetings.
- EChange the number of action items.
- FSchedule impromptu meetings when the SME is absent.
114A project team is identifying, rating the probability of, and determining the impact on potential problems throughout the project. The team is also including the corresponding actions to take.
Which of the following activities does this describe?- ARisk identification
- BRisk quantification
- CRisk planning
- DRisk qualification
115A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days.
Which of the following characteristics classifies this as a project?- ARepetitive
- BOngoing
- CIterative
- DTemporary
116Given the information in the table below, which of the following is the total project cost?

- A$40,000
- B$70,000
- C$95,000
- D$120,000
117The design team and development team disagree about what technology should be used for a major requirement. A brainstorming meeting takes place, where both teams focus on the mutually agreed-upon deliverables.
Which of the following conflict resolution techniques did the teams use?- ACompromising
- BSmoothing
- CConfronting
- DForcing
118A project manager is analyzing the cost variances produced when comparing two different projects completions.

- AIncreased resource productivity
- BIncreased resource allocation
- CIncreased schedule variance
- DIncreased labor cost
- EIncreased labor overhead
119One of the tasks on a project's critical path is progressing too slowly. The team member who is responsible for completing the task is assigned to multiple projects with aggressive deadlines.
Which of the following roles has the responsibility of resolving the issue?- ACCB
- BPMO
- CProject sponsor
- DProject scheduler
120A project manager is meeting with top management executives and presenting a project status report. The Chief Information Officer (CIO) and other executives complain that the meeting is taking too long and not providing summary information on the project"™s progress.
Which of the following should the project manager be presenting?- AProject issue
- BProject dashboard
- CProject schedule
- DProject milestone
121During an ad-hoc meeting, the PM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances.
The company, however, receives numerous stakeholder complaints.
Which of the following is the MOST likely cause of these complaints?- AThe quality of the deliverable decreased due to the rising material cost.
- BThe PM did not follow the project communication plan.
- CQuality assurance actions were not adjusted for the vendor change.
- DThe change was not documented and approved.
122A new project manager is working in an environment where resources report to another supervisor. The project manager is having difficulty with a particular member and wants to escalate the issue. Which of the following documents should the project manager consult?
- AIssue log
- BRACI chart
- CRisk management plan
- DOrganizational chart
123The Chief Executive Officer (CEO) has changed the direction of a business and no longer needs one of the divisions. A deal is reached to sell the division to a company in another state. Which of the following BEST describes this type of organizational change?
- ABusiness process change
- BInternal reorganization
- CRelocation
- DDemerger
124The anticipated funding level for an approved project was reduced. The sponsor has met with the project manager to identify several scope reductions. Which of the following is the NEXT step the project manager should take?
- AUpdate the documentation.
- BImplement the change.
- CClose the project.
- DEvaluate the impact.
125Which of the following describes a project's budget overrun?
- AThe project spends only half of the funds.
- BThe project spends only the allocated funds.
- CThe project spends none of the funds.
- DThe project spends in excess of the funds.
126A PM has notified the project team of an immediate project relocation. Of which of the following triggers is this MOST likely a result? (Choose two.)
- ABusiness continuity response
- BResource changes
- CDisaster recovery response
- DRisk response
- EGate review
127A project can be defined as:
- Apermanent and ongoing.
- Btemporary and unique.
- Ctemporary and standard.
- Dpermanent and unique.
128Two critical members have approached the project manager separately regarding personality conflicts. The project manager cannot remove either from the project or separate their work activities. To help resolve the conflict, which of the following would be BEST for the project manager to do?
- ASend an email to the entire project team encouraging proper etiquette.
- BDiscuss the problem during the next daily status update.
- CPerform an in-person meeting involving both parties.
- DSchedule a mandatory team-building activity.
129A project manager is archiving of project documents.
Which of the following phases does this describe?- AInitiation
- BPlanning
- CExecution
- DClosing
130Which of the following are MOST essential to developing an effective project team? (Choose two.)
- ATeam building by mixing in-house and remote human resources
- BDedicating the junior resources to the shortest tasks
- CSharing senior resources with other projects
- DSelecting team members with the appropriate skill sets
- EBuilding trust through honesty and good communication
131A local company is part of a hostile takeover by a multinational conglomerate. The Chief Executive Officer (CEO) directs that all meetings be conducted via video conference to save costs and expedite communication. This scenario is an example of:
- Aoutsourcing
- Bcorporate acquisition.
- Cinternal reorganization.
- Dprocess change.
- Erelocation
- Fresource management.
132A company's management team is in a meeting to review all the products and services delivered in the first quarter of the year for profitability. They are requesting information on payback period, return on investment, and total cost of ownership. The project manager is checking the project repository for available documentation. In which of the following documents is the project manager MOST likely to find the required information?
- ABusiness case
- BProject charter
- CRisk management plan
- DScope of work
133A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance.
Which of the following should the PM do NEXT?- ACrash the schedule.
- BNotify the project team.
- CInitiate a change request.
- DAccept the risk.
134A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?
- ARisk identification
- BGate review
- CResource allocation
- DResource leveling
135Which of the following make up a company's portfolio? (Choose two.)
- APeople
- BProcedures
- CProjects
- DProcesses
- EProfit
- FPrograms
136A recently added stakeholder is unaware of critical changes that will affect the department. Which of the following should the project manager do FIRST to ensure all parties have the same level of information?
- AThe project manager should check the project management plan to determine how the project should be managed and controlled.
- BThe project manager should check the communications plan to ensure stakeholders are included on any key messages.
- CThe project manager should check the meeting agenda to ensure the stakeholder is invited to all meetings.
- DThe project manager should ensure meeting minutes are distributed to all project members.
137A key stakeholder asked several members of the project team to make project changes without submitting them for approval. Because the stakeholder is related to the Chief Executive Officer (CEO), the team members are reluctant to deny these requests. Which of the following should the project manager do FIRST to control this situation?
- AHave the team members deny all change requests from this stakeholder
- BAsk the project sponsor for more funding to anticipate the change requests from the key stakeholder
- CContact the key stakeholder to encourage the submission of written change requests
- DRequest additional resources from the project team to complete the change requests from the key stakeholder
138Which of the following resources outlines consequences of non-performance?
- AProject sponsor
- BProject team
- CCustomer
- DProject management office
139During a risk review session, the project team identified the percentage probability that a particular risk will occur. This is known as:
- Arisk identification
- Brisk prioritization
- Crisk qualification
- Drisk quantification
140An organization wants assurance that the specialty tools necessary for operation will function as intended for a specific minimum time period. Which of the following documents BEST provides this assurance?
- APurchase order
- BNon-disclosure agreement
- CRequest for proposal
- DWarranty
- EService level agreement
141Based on the table below:
Which of the following is the float of Task B?
- A-2
- B0
- C2
- D5
142Which of the following network scheduling techniques is focused mainly on the duration and stack of each activity?
- AProgram evaluation review technique
- BPrecedence diagramming method
- CArrow diagramming method
- DCritical path method
143Based on the table below:

- A0
- B1
- C2
- D3
144An active construction project must make immediate changes when it is discovered that the designated project area contains protected wetlands.
Which of the following is the MOST likely impact to the project?- AThe project quality will decrease
- BThe project scope will decrease
- CThe project timeline will increase
- DThe interproject dependencies will increase
145A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well. Which of the following stages BEST explains this situation?
- ANorming
- BPerforming
- CForming
- DStorming
146Which of the following primary factors are used to prioritize the development of risk response strategies? (Choose two.)
- ALikelihood
- BTimeline
- CImpact
- DQuality
- ECost
147Which of the following job roles is MOST responsible for providing input on the project requirements, steering the project, providing expertise, and having vested interest in the project?
- AProject scheduler
- BProject stakeholder
- CProject team
- DProject coordinator
148Which of the following project phases occurs when requirements are detailed?
- AInitiation
- BMonitor and control
- CPlanning
- DClosing
149Which of the following documents will provide the MOST detailed information regarding the work a vendor will perform during a project?
- ARFI
- BSLA
- CSOW
- DPO
150A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?
- AAnalyze the critical path and update the WBS with the new feature
- BAdd the new feature and reprioritize the product backlog
- CAdd the new feature to the next sprint and move the old feature to the following sprint
- DConduct a retrospective with the team to discuss the change and introduce the feature
151A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types of organizational structure does this scenario BEST describe?
- AFunctional
- BProjectized
- CStrong matrix
- DFlat
152Severe weather has impacted a construction project, delaying scheduled work for five days. Which of the following project changes is the project manager most likely to consider FIRST?
- ARequirements change
- BFunding change
- CTimeline change
- DRisk event
153The following tasks are required to complete an IT project that is behind schedule:

- A3, 2, 4
- B4, 2, 3
- C3, 2, 1, 4
- D4, 1, 2, 3
154A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and requested a project manager to work with the firm.
The PMO declines to assign a project manager and refers to another department within the company. Which of the following is MOST likely the reason for this?- AThere are not enough project managers available for additional work
- BThe work does not align with the strategic objectives of the organization
- CThis is ongoing work the vendor has been hired to perform
- DThe third party has a reputation for expertise in this area
155A project manager is scheduling activities and determines one activity cannot be completed until another activity is completed. Which of the following dependency relationships is represented?
- AFF
- BSS
- CSF
- DFS
156Which of the following are MOST likely the responsibilities of the PMO? (Choose two.)
- ASteer the project
- BProvide governance
- CJustify the business case
- DProcure hardware
- EIdentify key performance indicators
- FAct as an approval authority
157Which of the following is the MOST important component against which the project manager can analyze project performance?
- ABurn rate
- BProject baselines
- CKPIs
- DBudget
158Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
- ARequirements
- BLessons learned
- CBudget
- DEnvironment
159In a Scrum retrospective, which of the following categories are used to classify the feedback from the team?
- ADirect and indirect
- BPros and cons
- CPluses and minuses
- DLikes and dislikes
160While preparing to plan a project, the project manager meets with the key stakeholders to determine the flexibility between the project constraints. Which of the following techniques should the project manager consider to reduce personal bias and increase buy-in?
- ASend the stakeholders a survey about the project constraints to complete anonymously
- BWatch and determine which constraint is most important
- CCompare the constraints two at a time and have the stakeholders
- DLook at historical information regarding the flexibility preferences of key stakeholders
161Which of the following will identify the MOST potential project risks?
- ACost-benefit analysis
- BPast project documentation
- CProject budget
- DBenchmarking
162A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?
- AStakeholders
- BScrum master
- CProject sponsor
- DProject team
163A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?
- AChange validation with quality checks
- BRegression planning
- CIdentify approval authority
- DChange implementation
164An employee is assigned to a project and is developing a project charter. Which of the following are some of the constraints the employee would typically face at this stage of the project?
- AEnvironment, resources, requirements, and quality
- BBudget, quality, resources, and schedule
- CDeliverables, scope, and budget environment
- DBudget, scope, quality, and schedule
165A team member has reported Task 3 will be completed ahead of schedule.
Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?
- A8 days
- B10 days
- C11 days
- D12 days
166Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?
- AFive days
- BSix days
- CSeven days
- DEight days
167A PM is asked to keep the Chief Information Officer (CIO) informed of a project's health at a high level on a daily basis. Which of the following is the BEST way for the PM to provide this information?
- AStatus report
- BMeeting minutes
- CDashboard
- DEmail
168A project team is working on a project with high public visibility and excitement. The project sponsor is concerned the public may lose interest due to the long delivery timeline. Which of the following is the BEST way to keep the external stakeholders informed and engaged throughout the project?
- AVideo conferencing
- BInstant messaging
- CSocial media
- DEmail
169A project scheduler has calculated the project's critical path. Which of the following activities would most likely occur NEXT?
- AAdditional task decomposition
- BResource allocation
- CDependency determination
- DTask duration identification
170Which of the following provides tools and standard documentation for the project team?
- AProject management office
- BProject manager
- CProject coordinator
- DProject steering committee
171The PMO is confused by an entry in the risk register and would like the project manager to provide clarification regarding strategy. Based on the following entry:
Which of the following should be modified to BEST eliminate confusion?
- AChange the status to issue and include it in the issue log
- BChange the strategy to mitigate
- CChange the name to identify the problem clearly
- DChange the owner to sponsor
172In the review of a project status report, the slack is negative. Which of the following should the project manager tell the stakeholders?
- AThe project is behind schedule
- BThe project is over budget
- CThe project has float available
- DThe project needs a gate review
173Which of the following should be included in an effective SOW?
- ALessons learned
- BProcurement process
- CCorrective action plan
- DProject objectives
174A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)
- AUpdate the project charter to include the functional manager as a key stakeholder
- BPublish the project schedule to the functional manager
- CReview the communications plan to ensure proper involvement
- DAdd the incident to the issue log and seek resolution
- EEnsure the functional manager is on the status report distribution list
175The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project's success. Only personnel who need to know the information will have access. Which of the following site types is the PM requesting?
- AWiki page
- BIntranet
- CExtranet
- DInternet
- EKnowledge base
176Which of the following documents are considered mutually binding? (Choose two.)
- ANDA
- BPO
- CRFP
- DWBS
- EKPI
177A project sponsor has requested documentation to determine the scheduled activities for a project that is running behind schedule. Which of the following documents should the project manager send to the sponsor to quickly identify the project activities?
- ARACI
- BSWOT
- CSOW
- DWBS
178Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
- ADetermine the flexibility between the project constraints
- BHold a kick-off meeting with the project team
- CDetermine procurement needs to meet the project demands
- DCreate the risk register
179A project manager is reviewing project performance. Which of the following would be the BEST indicator of the total project cost?
- AAC
- BEAC
- CCPI
- DETC
180According to the communication management plan, the project scheduler is required to post weekly status reports on the project's intranet site. From the stakeholders"™ point of view, accessing the weekly report is an example of:
- Ainterorganizational preferences
- Bpersonal preferences
- Cthe interactive method
- Dthe pull method
181The project team is moving from high-level risks to detailed risks. Which of the following project phases is the project team moving between?
- AExecution to monitor and control
- BInitiation to planning
- CInitiation to monitor and control
- DPlanning to execution
182A project manager determines deliverables are not meeting customer specifications. During which of the following project phases is this determination MOST likely to happen?
- AMonitor and control
- BExecution
- CClosing
- DPlanning
183During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated?
- AIncident response
- BProject plan
- CRisk register
- DBusiness continuity plan
184Which of the following represents the order of the team development stages?
- AForming, storming, norming, performing
- BForming, performing, storming, norming
- CForming, norming, storming, performing
- DForming, norming, performing, storming
185A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation.
Which of the following actions has the PM omitted?- AIdentifying the risk
- BObtaining approval from the CCB
- CEvaluating the impact of the risk
- DCommunicating to stakeholders
186Which of the following should a project manager consider as part of a make or buy analysis?
- AOrganization type
- BKPIs
- CProject charter
- DTrade secrets
187A project manager is assigned a project that is part of the company's strategic objectives. Of which of the following is the project a part?
- AProject management office
- BPortfolio
- CProgram
- DMission statement
188A project needs two more months of work to be completed, but the deadline is in 35 days. The project manager heard the company recently hired an experienced person. The project manager scheduled a meeting with the functional manager to negotiate bringing the experienced person to the team. Which of the following strategies is the project manager trying to apply?
- AExploit
- BMitigate
- CAccept
- DTransfer
189There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being delayed. Which of the following project management tools would help?
- AIssue log
- BProject charter
- CDashboard
- DMeeting minutes
190Which of the following are the roles involved in a Scrum project?
- AScrum master, development team, quality coach
- BScrum master, business analyst, product owner
- CScrum master, product owner, development team
- DScrum master, project sponsor, business analyst
191Ann, a project manager, is working for a new company. On her first project, the assigned project resources do not follow her direction. She is not allowed to authorize contractors because they say she does not have the authority. Which of the following is the MOST likely explanation for what is happening?
- AAnn is new to the organization so no one trusts her
- BAnn has not developed a communications plan
- CThe project team is functional
- DThe project has not started
192In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:
- Aa dedicated resource pool
- Ban allocated resource pool
- Ca shared resource pool
- Da benched resource pool
193A fire alarm goes off in the building where the project team works. Employees are instructed to leave the premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside the building for further instructions. This is known as a:
- Abusiness change response
- Bchange management response
- Cbusiness continuity response
- Drisk management response
194A PM has a complex project that requires coordination among numerous stakeholders. Which of the following is the MOST appropriate type of meeting for the stakeholders to hold?
- AVirtual
- BImpromptu
- COne-on-One
- DIn-Person
195A project sponsor approaches the project manager with a change request. During the conversation, the project sponsor claims to understand the impact of the change to the project length and has the budget to handle the cost. The sponsor also tells the project manager to send whatever needs a signature. The project manager's NEXT step should be to:
- Adocument the change
- Bimplement the change
- Ccommunicate the change
- Dprioritize the change
196The managing director of a law firm has asked the project manager to create a scope statement for a new contract. Which of the following should be included in the scope statement? (Choose two.)
- AScope creep
- BDeliverables
- CBusiness requirements
- DProject schedule
- EGate review
- FKey performance indicators
197Risk ID 2 has occurred.
Which of the following ways should the project manager update the risk register?
- AAdd a column for probability and set risk 2 at 100%
- BChange the risk 2 response to backups restored
- CChange the risk 2 status to issue
- DChange the risk 2 owner to PM
198A company purchased a parachute supplier and is now sending parachutes to the research and development department. Which of the following has occurred?
- ARisk avoidance
- BOutsourcing
- CBusiness demerger
- DBusiness acquisition
199Which of the following tasks are responsibilities of the project manager role?
- AProvide inputs, estimate tasks, and manage a team
- BManage the budget, perform quality assurance, and be accountable for artifacts
- CSet deliverables, control risk, manage risk, and create a project charter
- DManage a team, marketing, roadblocks, and project steering
200A company was originally organized using a functional structure; however, the company has decided to go forward with a matrix structure to get the most utilization of resources. This is an example of:
- Aa business process change
- Bpersonal preference
- Cinternal reorganization
- Dintraorganizational differences
Informações
- Descrição
- Quiz sobre Project + Part 2 , criado por Nope Nope em 23-12-2020.
- Autor
- Nope Nope
- Idioma
- English
- Visualizações
- 3
- Etiquetas
- Avaliação
- Ainda sem avaliações Avalie este quiz