Perguntas do quiz (23)

  1. 1The owner request changes which will cause the contractor $2,500 in labor and material and $700 in overhead cost. With the change, the contractor would be relieved of $1000 in labor cost and $280 in overhead cost from the original contract. The original bid included profit of 10% of all cost. The contractor wants to make a profit of 10% of all costs on the changes. The amount of the change orders include a
    1. A$1,820
    2. B$2,112
    3. C$3,200
    4. D$3,500
  2. 2A lump sum contract on a project has a total contract price of $200,000. Retainage has been held back at 10%. The contractor has received payments of 90% of the project. The contractor submit a request for the final payment for the now complete project. The final payment amount should be for
    1. ALess than $25,000
    2. BBetween $25,000 and $35,000
    3. CBetween $35,000 and $45,000
    4. DMore than $40,000
  3. 3A contractor agrees to unit price contractor to Product A for $50 per unit, product B for $50 per unit, and Product C for $375 per unit. The contractor is also to add 30% for overhead and profit. How much the contractor should be paid for producing 27 units of Product A, 56 units Product B and 78 units Product?
    1. ALess than $40,000
    2. BBetween $40,000 and $45,000
    3. CBetween $45,000 and $50,000
    4. DMore than $50,000
  4. 4A contractor calls for liquidated damages of $500 per day. The project completed five late because it was delayed by rain. The completion would have been ten earlier if it were not for the rain delay. There was $500 bonus per day for the contractor for completion. NO EXTENSION OF TIME WAS REQUESTED OR GRANTED. How much does the contractor earn or owe?
    1. AOwes $2,500 in Liquidated damages
    2. BOwes $500 in Liquidated damages
    3. CIs due $2,5000 bonus from the owner
    4. DIs due a $500 bonus from the owner
  5. 5A job had a bid price of $165,000 after the direct cost and overhead are factored. What will the final bid be if the profit markup is 11.5%
    1. A$186,440
    2. B$183,975
    3. C179,545
    4. D$189,874
  6. 6Given the following information, is it advantageous to purchase or rent this particular piece of equipment if it has 3 useful tears?
    Purchase. Rent

    Initial Cost. $10,000. $0
    Rental. $0. $500
    Salvage values $2,000. $0
    Insurance. $40. $0
    Operating cost. $200. $0
    1. ARenting saves $840
    2. BRenting saves $2,280
    3. CPurchasing saves $840
    4. DPurchasing saves $3,160
  7. 7In a cost plus contract, the contractor receives direct cost for labor and materials with a 40% mark up, a 10% bonus if the total cost to the owner is less than $100,000, and a $500 bonus for each day the work is complete early. The final cost of labor and materials is $60,000 in the work is done five days early. How much is the Contractor due?
    1. ALess than $85,000
    2. BBetween $85,000 and $90,000
    3. CBetween $90,000 and $95,000
    4. DGreater than $95,000
  8. 8What is the bid for the following when there is a combined profit and overhead of 30%?

    -10 units at $75.00 each
    -20 units at $200.00 each
    -30 units at $290.00 each
    1. A$13,450
    2. B$16,379
    3. C$17,485
    4. D$19,214
  9. 9A firm has current assets of $68,000, fix assets of $162,000, current liabilities of $45,000, and long-term liabilities of $72,000. The firm’s financial position would be considered to be
    1. Aadequate for taking on a major project
    2. BSufficient to overcome a slow period
    3. COne that could result in cash flow problems
    4. DExtremely inadequate
  10. 10The cost of equipment is $1,000, the cost of materials is $6,000, and direct labor is $3,000. Project overhead is 20% of direct labor, general overhead is 10% of direct labor and materials, and profit is 10% of all cost. The owner offer to pay $12,000. If the contractor accept the offer, what would be the contractor’s anticipated profit or loss?
    1. AProfit $1,100
    2. Bprofit $500
    3. CLoss $500
    4. DLoss $650

Informações

Descrição
Quiz sobre Sem título, criado por Andrew Ervin em 05-05-2022.
Idioma
English
Visualizações
0
Histórico
Criado em 5 mai 2022 · atualizado em 5 mai 2022
Etiquetas
advanced
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?