Questão
Which of the following processes includes asking team members about the time estimates for their activities and reaching agreement on the calendar date for each activity?
Responda
  • Develop Project Charter
  • Develop Schedule
  • Sequence Activities
  • Define Scope

Questão 2

Questão
Which of the following is the BEST project management tool to use to determine the longest time the project will take?
Responda
  • WBS
  • Project charter
  • Network diagram
  • Bar chart

Questão 3

Questão
Lag means
Responda
  • The product of a forward and backward pass.
  • The amount of time an activity can be delayed without delaying the project finish date.
  • Waiting time
  • The amount of time an activity can be delayed without delaying the early start date of its successor.

Questão 4

Questão
Which of the following BEST describes product analysis?
Responda
  • Mathematically analyzing the quality desired for the project.
  • Gaining a better understanding of the product of the project in order to create the project scope
  • Determining if the quality standard on the project can be met.
  • Working with the customer to determine the product description.

Questão 5

Questão
The work breakdown structure can BEST be thought of as an effective aid for _______ communications.
Responda
  • Customer
  • Stakeholder
  • Project manager
  • Team

Questão 6

Questão
A project management plan should be realistic in order to be used to manage the project. Which of the following is the BEST method to achieve a realistic project management plan?
Responda
  • Project manager creates the project management plan based on input from the team
  • Sponsor creates the project management plan based on input from the project manager.
  • Project manager creates the project management plan based on input from senior management.
  • Functional manager creates the project management plan based on input from the project manager.

Questão 7

Questão
What is the duration of a milestone
Responda
  • Shorter than the duration of the longest activity
  • There is no duration
  • Shorter than the activity it represents
  • Same length as the activity it represents

Questão 8

Questão
Which of the following can create the MOST misinterpretation in the project scope statement?
Responda
  • Too much detail
  • Imprecise language
  • Small variation in size of work packages or detail of work
  • Poor pattern, structure and chronological order

Questão 9

Questão
During project executing, a large number of changes are made to the project. The project manager should:
Responda
  • Make only the changes approved by management.
  • Talk to management before any changes are made.
  • Wait until all changes are known and print out a new schedule.
  • Make approved changes as needed, but retain the schedule baseline

Questão 10

Questão
During project executing, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?
Responda
  • Activity list
  • Scope management plan
  • WBS dictionarry
  • Project scope statement

Questão 11

Questão
A poject manager may use ________ to make sure the team members clearly know what work is included in each of their work packages.
Responda
  • A schedule
  • A WBS dictionarry
  • The project scope statement
  • The product scope

Questão 12

Questão
During what part of the project management process is the project scope statement created?
Responda
  • Planning
  • Monitoring and controlling
  • Executing
  • Initiating

Questão 13

Questão
The WBS, estimates for each work package, and the network diagram are completed. Which of the following would be the NEXT thing for the project manager to do?
Responda
  • Create a preliminary schedule and get the team's approval.
  • Sequence the activities.
  • Verify that they have the correct
  • Complete risk management.

Questão 14

Questão
A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is:
Responda
  • Begin work on a project management plan.
  • Confirm that all the stakeholders have had input into the scope
  • Analyze project risk.
  • Create a project scope statement.

Questão 15

Questão
Which of the following is an output of the Collect Requirements process?
Responda
  • Requested scope changes
  • Project scope statement
  • Requirements traceability matrix

Questão 16

Questão
Which of the following is CORRECT
Responda
  • The network diagram will change every time the end date changes.
  • The critical path helps prove how long the project will take
  • A project can never have negative float.
  • There can be only one critical path.

Questão 17

Questão
Rearranging resources so that a constant number of resources is used each month is called:
Responda
  • Fast tracking
  • Crashing
  • Floating
  • leveling

Questão 18

Questão
Which of the following BEST describes a project management plan?
Responda
  • A bar chart
  • A printout from project management software
  • The project scope
  • Risk, staffing, process improvement and other management

Questão 19

Questão
A work breakdown structure numbering system allows the project staff to:
Responda
  • Use it in project management software.
  • Identify the level at which individual elements are found
  • Systematically estimate costs of work breakdown structure elements.
  • Provide project justification.

Questão 20

Questão
When would a milestone chart be used instead of a bar chart?
Responda
  • Reporting to management
  • Project planning
  • Reporting to team members
  • Risk analysis

Semelhante

NHS contract, Pharmacy, Personal Control & Responsible Pharmacist
Karo
The NHS (Pharmaceutical Services) Regulations 2012
Karo
ACENTUAÇÃO GRÁFICA
Viviana Veloso
Estilos de redação para concursos
Alessandra S.
Exame Nacional de Português 2
Sandra Franco
Dicas de Português para Concursos
Rodrigo Pizetta
O Renascimento
Professor Junior
Sistema Cardiovascular: Artérias, Veias e Capilares
Natália Abitbol
Desafio dos sinais: do sinal ao significado - Aula 03
Emannuelle Araújo
Revisão 2- PROVA DE SARGENTO - MARINHA - EA-HSG - ( Com Verificação )
Nilzeir Reis