PMP exam 4

Lê Hiếu 100 perguntas

Fazer o quiz

Perguntas do quiz (100)

  1. 1During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement. What should the project manager do next?
    1. AEscalate the situation again to the project sponsor.
    2. BReview this obstacle during the daily standup meeting.
    3. CRequest a new resource to execute the activities.
    4. DProvide feedback to the resource at the sprint review.
  2. 2A retail company identifies that it is losing sales because customers are not promptly informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.
    Considering the objective to deploy customer value, which project life cycle approach should be chosen?
    Imagem da pergunta 2
    1. AĐáp ánImagem da opção A
    2. BĐáp án ở trên
  3. 3A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?
    1. AEnsure the stakeholder engagement plan is accurate and properly documented.
    2. BReview the lessons learned from the previous project
    3. CIdentify the risk of implementing the new solution and evaluate the impact on the project.
    4. DCreate a lessons learned document for the initiation phase
  4. 4After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.
    What should the project manager do to prevent this frustration going forward?
    1. ARequest the human resource (HR) department to provide the key performance indicators (KPIs) that were defined for this project.
    2. BSet team performance goals and explain how the team receives the same performance scores.
    3. CReview the key performance indicators (KPIs) for this team member and remind the team member how they are determined.
    4. DProvide the team member with velocity tracking tools and explain how the team member can see and track performance.
  5. 5A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.
    What strategy should the project manager implement to deal with this situation?
    1. AAsk the team.to accelerate the iterations and avoid interruptions.
    2. BDiscuss the problem with the team and decide how to do the work together.
    3. CVerify team performance and ask for improvement during daily standup meetings.
    4. DRecommend that the project sponsor increases the budget to bring new resources.
  6. 6A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?
    1. ABe clear with directions and assignments so people stay focused and engaged with their work.
    2. BPromote an environment where everybody knows what their contribution means to the project as a whole.
    3. CDesign a reward system to get people motivated by recognizing significant individual contributions from the last sprint
    4. DEncourage continuous rotation of roles among team members to keep people motivated throughout project delivery.
  7. 7There is a problem with a project because some features are not in compliance with regulations. Some stakeholders do not believe compliance is a priority, while others disagree. What should the project manager do?
    1. AReview the stakeholder engagement assessment matrix to determine next steps.
    2. BSet up some time with the stakeholders to explain the importance of compliance.
    3. CMeet with the sponsor to discuss how to handle the stakeholders' differing opinions.
    4. DSend out documentation to align stakeholder expectations and project objectives.
  8. 8A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.
    When should the value be demonstrated?
    1. AAfter full development is completed
    2. BWhen a major feature is completed
    3. CAt the end of each and every iteration
    4. DWhen the sponsor approves the increment
  9. 9A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process, What should the project manager do?
    1. ADescope low-priority features that were not explicitly requested and add this feature as a high priority.
    2. BInform the senior manager that they will need a new project management plan for this feature
    3. CComplete the most current feature and release the resources for the new feature.
    4. DAnalyze the impact of this change and present the options to the senior manager.
  10. 10As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.Imagem da pergunta 10
    1. AĐáp ánImagem da opção A
    2. BĐáp án ở trên

Informações

Descrição
Công nghệ số Quiz sobre PMP exam 4, criado por Lê Hiếu em 17-07-2022.
Idioma
English
Visualizações
29
Etiquetas
công nghệ số
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que a gente deve adicionar?