1A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.
What should the project manager do?- AMeet with the project team to discuss internally whether they think cost is more important to the customer than the timeline
- BAdjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change
- CInform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline
- DAbsorb the additional cost for the additional resources internally so that the project completes within the timeline
2A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area What should the project manager do first?
- AIdentify an alternative site.
- BUpdate the issue log
- CIssue a change request
- DUpdate the risk register.
3An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?
- AAdd the competitor's functionalities to the product backlog to improve the product
- BAsk the sponsor to add more people to the team
- CHelp the team to find a new approach to launch the product as soon as possible
- DAsk the team to increase the velocity to launch the product as soon as possible
4Throughout an entire project, the project manager took notes at every meeting with team members. These notes provided useful insights from key stakeholders, which later resulted in increased value to the project. The project manager thought it would be helpful to keep these notes as a future reference for other project managers within the organization.
Where should the notes be located?- ALessons learned
- BOrganizational process assets (OPAs)
- CEnterprise environmental factors (EEFs)
- DProject management plan
5A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?
- AProject stakeholders and the team
- BExternal subject matter experts (SMEs) and the team
- CProject sponsor and the team
- DProject sponsor and the external SMEs
6A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically last 45 minutes with many misunderstandings due to language barriers.
How should the project manager resolve this issue for the next iteration?- ATransfer half of the backlog items to the next iteration to allow more time to complete the meetings.
- BExtend the meeting to 1 hour and request that all of the participants bring up all of the issues.
- CInstruct the meeting participants to speak only about blockers during the meeting.
- DTrain the three team leads to conduct a local meeting, then run an overall status meeting.
7A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?- ACreate a lessons learned register to include operations team training for future projects.
- BInclude knowledge transfer sessions between the project and operations teams at every stage.
- CChange the project management plan to add a final stage for product handoff to the operations team.
- DPrepare detailed documentation to be shared with the operations team during project closure.
8A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.
Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three)- APrioritize stakeholders based on the project phase and need.
- BDevelop a stakeholder impact influence matrix to determine the level of engagement
- CPerform a stakeholder assessment to align with the project objectives.
- DInclude all stakeholders in the stakeholder engagement plan and provide the same level of communication.
- EClassify and rank stakeholders based on their positions in the organization.
9A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.
What should the project manager have done to avoid this perception?- AInvolved the business stakeholders in the sprint review
- BDefined product backlog priorities with the sponsor and key stakeholders to deliver business benefits
- CImplemented a closing survey for key stakeholders
- DConfirmed that there is a communications management plan in place to make business stakeholders aware of the success
10A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation. How should the project manager approach this situation?
- AUnderstand the customer's perspective and provide mentoring on agile mindsets.
- BCall for an internal team retrospective and create an improvement action plan.
- CAsk the customer to work with the product owner to prioritize all requests.
- DWork with the team to receive customer directions and improve the process.
11A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

- AĐáp án

- BĐáp án ở trên
- AĐáp án
12The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?
- ASeek expert legal advice on the interpretation of the clauses in the contract
- BHold a meeting with the project team project sponsor and the client to agree to the further work required to close the project and add to lessons learned
- CClose the project and hand over the deliverables to the client
- DHold a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects
13At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?
- ADevelop a work plan for the project team member with the help of the resource manager
- BAdvise the functional manager and the project team member to review the resource management plan
- CTell the functional manager and the project team member to review the project charter
- DAsk the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member
14During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible What approach should be used in this situation?
- AThe team facilitator gets support from external team members.
- BThe team members bring in a specialist to help them
- CThe product owner moves it to the product backlog.
- DThe cross-functional team member work together to complete the activity
15An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the project manager do to help improve the team's collaboration approach?
- AMeet with the human resources (HR) department to ask for team support.
- BFollow the process of the most successful team in the organization.
- CCompare the team's velocity with other teams in the organization.
- DFocus on the team's engagement during the next retrospective meeting.
16During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?
- AAsk upper management for more funds and update the project budget
- BRevise the project scope accordingly to cope with the budget changes
- CUpdate the risk register and project log. and manage the budget closely.
- DSubmit a change request to accelerate the project as requested
17A company has agreed to run a transformation project using agile approaches.
During the implementation, there is pushback from the functional groups that the project is moving too fast.
What should the project manager have done at the beginning of the project to prevent this from happening?- ACirculated the project charter
- BAssessed the organizational culture
- CDetermined the level of maturity of the employees
- DCommunicated the project schedule
18A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team members and stakeholders who have contradictory opinions.
What should the project manager do?- AMeet with the stakeholders to determine the approach using the project goals and desired outcomes.
- BLeverage agile methods only as the project pertains to software implementation, which can be broken into increments.
- CLeverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods
- DDetermine what methods the team has been trained on and utilize those methods for the project.
19A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?
- AAn agreed-upon work method and tools that should fit the business need and project constraints
- BA detailed mitigation plan on the risks for each work method and the tools used
- CA consensus that everything will run as anticipated once the tools and work methods are identified
- DA technology roadmap for creating similar deliverables in the future with the same tools
20A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
- ARequire proper approval of all requirements from the marketing vice president and formally document the agreements.
- BFoster an environment of open communication where all parties can discuss issues and agree on objectives.
- CEstablish an executive review board where all stakeholders discuss and approve features and requirements.
- DLeverage the use of the review/demo sessions with the vice president to acknowledge that the agreements were met.
21During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization What should the project manager do first?
- AUpdate project documents to include adaptive tools and artifacts and plan the first iterative session
- BContact the project sponsor and request new team members who are familiar with adaptive projects
- CConfirm team capabilities before introducing adaptive tools and artifacts to the project
- DFreeze the design stage and look for an external resource to run iterative design at extra cost
22A project manager is appointed for the deployment of a new solution The solution will be integrated into the environment by a third-party vendor This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?- AAsk for expedited delivery of the component to mitigate the risk of schedule delays
- BEnsure that relevant stakeholders and expectations are identified and assess the component delay
- CPerform a detailed analysis of the release content for each component of the solution.
- DPropose a new design of the solution to replace the external component with an internal one
23A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right

- AĐáp án

- BĐáp án ở trên
- AĐáp án
24During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days. What should the project manager do next?
- AEscalate the issue to the engineer's functional manager.
- BDiscuss the issue with the engineer and determine how to prevent another problem.
- CDocument the task on the kanban board and make it the highest priority.
- DAssign another engineer to the task due to the urgency.
25A project team needs to follow regulatory compliance guidelines that are mandatory for the project. What should the project manager do to ensure compliance adherence?
- AAssess compliance when there is time in the project.
- BAssign a project team member to ensure compliance.
- CReview compliance adherence at the end of the project.
- DInclude compliance within the development tools.
26Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?
- ASent the meeting minutes to the stakeholders after the kick-off meeting
- BReviewed all the approvals immediately after the kick-off meeting was over
- CRan separate kick-off meetings for each culture and time zone
- DValidated each stakeholder's understanding during the kick-off meeting
27During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.
What should the project manager do?- AReview the procurement documentation and modify requirements as needed.
- BStudy the new regulations with the team and evaluate if there is any impact on the project variables.
- CUpdate the contingency plan to take this issue into account.
- DMeet with the stakeholders to update the risk register and risk management plan.
28The first task a project manager needs to complete on a new project is improving stakeholder engagement.
How should the project manager complete the power/interest grid based on the following scenario:
* The marketing director is the key stakeholder. as the project will create a new product for the company.
* The finance director is providing funding and does not have much time to follow the tracking of the project.
* The sales representatives assigned to the team provided some negative feedback on the requirements
* The human resources (HR) intern assigned to the team was satisfied with the new product interlace.
- AĐáp án

- BĐáp án ở trên
- AĐáp án
29A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications What should the project manager do?
- ASchedule a meeting with all stakeholders to understand what went wrong and who should be held responsible
- BReview the requirements traceability matrix with the team lead and the client to adequately resolve the issue
- CMeet with the client and discuss the project deadlines
- DSeek approval for more time for rework and resolve the issue
30A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.
Knowing that there are no additional funds available, how should the project manager proceed?- AAllocate the budget to the phases of the project and meet with upper management to consolidate the final funds.
- BEnsure that the budget is enough to cover the internal resources, since external supplies can be covered by procurement.
- CAllocate the budget to the deliveries that have higher business value for the organization than those with lower business value.
- DDecide to work on the small deliveries, leaving the big deliveries until the end of the project, and track critical expenses.
31A project manager for a government organization often deals with stakeholder engagement issues Drag the interpersonal skill the project manager should use on t he left to the correct situation on the right

- AĐáp án

- BĐáp án ở trên
- AĐáp án
32A project manager is appointed to manage an infrastructure project that spans across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.
What should the project manager do to ensure good collaboration between the remote project team members?- ADiscuss the concerns with the project sponsor and modify the project charter to include more budget for interactions.
- BPlan a communication method and allow the project team members to virtually interact.
- CCreate a social media group platform for the team to create a supportive environment.
- DSet the ground rules and identify a contingency plan in the risk register.
33There is a conflict on an agile project about following organizational processes, many of which do not add any value to the project. To resolve this, which one of the following should be regarded with the highest priority?
- ANeeds of the customer
- BNeeds of the project manager
- CNeeds of the agile lead
- DNeeds of the organization
34A contractor delivering construction services to a company is using agile principles to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design changes or performing rework.
What should the project manager do to minimize the cost?- APut the project on hold until all definitions are ready in order to avoid rework.
- BReview the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.
- CCapture the engineers' feedback at the daily meeting and communicate it to the product owner.
- DCancel the project release resources, then start again when all the definitions are ready.
35An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.
What should the project manager of the ongoing project do?- ASubmit new user stories to the product owner in order to put documentation in the product backlog.
- BIntroduce a document management tool to support the agile teams in preparing the documentation.
- CCheck with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.
- DAdd an additional team member to take up the role of scribe for the required documentation.
36A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?
- AAsk the leadership team for help obtaining the needed staff.
- BHave a direct talk with the functional manager to understand the reasons behind their attitude.
- CEvaluate the impact caused by the delay of forming the team and confront the functional manager.
- DCheck with human resources (HR) regarding the availability of staff.
37A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.
How should the project manager address the employee's request?- AEvaluate the employee's recommendation by reviewing the lessons learned from a similar project.
- BCreate a salience model to determine if the employee will have influence on the project.
- CAsk the project sponsor to revisit the project charter to consider the employee's recommendation.
- DAssess the influence and power of the employee to see if the employee will add value.
38A project manager prepared the base budget model to deliver a highly
customizable software solution. The solution will be delivered in multiple countries with significantly different cultures and will be staged over phases.
What should the project manager do next?- AReview the base model with the team leaders in each country to establish an independent budget for each phase.
- BOverestimate costs and underestimate revenues to include the impacts of different cultural elements.
- CApply the company's operational budgeting model.
- DAsk the project management office (PMO) to review the draft budget.
39A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages. This difficulty leads to missed deadlines.
What should the project manager do to enhance project team effectiveness?- AImplement team colocation to improve communication.
- BIdentify the root cause of communication issues
- CInitiate daily communication of project progress
- DSchedule a communications control board meeting
40A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment What should the project manager do?
- AInvite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team
- BInvite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment
- CInvite the product owner and the team to a discussion about the concept and expected performance of the equipment
- DInvite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting
41A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval How should the project manager approach this problem?
- APlan to address the issues through backlog grooming and incorporate them into the next sprint
- BRefer the product owner to the change management plan, then escalate to the steering committee
- CRefer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes
- DTell the product owner the issues will be addressed in the second version of the software
42A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now use a system running on a conventional dial-up service.
What should the project manager do next?- AEvaluate the impact of this decision and communicate with management.
- BAgree with management and continue working the project management plan.
- CMeet with management about their decision and ask them to get another project manager.
- DReplace some of the team members that work virtually to help the company save money
43A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.
Which stakeholders should the project manager include in the stakeholder engagement plan- AStakeholders who have been identified and who have needs and a potential impact on the project.
- BStakeholders who are selected by the project sponsor who have a potential impact on the project.
- CStakeholders who disagree with the project so as to proactively manage their expectations.
- DStakeholders who are supporting the project in order to obtain additional resources.
44A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.
What should the agile leader do?- AMove the solution designer to another team.
- BReview the process that resulted in this situation.
- CStop work until the design document is completed.
- DAsk the team to document the design.
45During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.
What should the project manager do?- ASchedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.
- BSchedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.
- CReview the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.
- DReview the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.
46In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?
- AReassign the task to another member of the team
- BSupport the team member by providing one more resource to complete the task immediately
- CAsk the team member if there is an impediment and help to remove the blockers
- DKeep the project sponsor informed about the delay
47A project manager is hired by a global company. The project manager is an agile specialist and is tasked with supporting the project team to reduce rework and dissatisfaction.
How should the project manager address these objectives?- ADecrease the scope of the portfolio and send new solutions to the customer.
- BDeliver a schedule with the portfolio timeline and delivery to the customer.
- CAdopt an incremental cycle of delivering value to the customer.
- DPrepare deliveries with more details to satisfy the customer.
48A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in one of the project teams.
What should the project manager do?- AApply a root-cause analysis on the data breaches.
- BEnsure that all team members complete the training.
- CRedesign the training courseware to make it interesting.
- DRetrain the team members responsible for the breaches.
49During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?
- AThe updated benefits management plan
- BThe updated scope management plan
- CThe updated project management plan
- DThe updated communications management plan
50As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
- AInclude this topic in the next iteration retrospective
- BReview this topic with the product owner before the next iteration planning
- CDiscuss this topic with the team in the next baily meeting
- DAsk the product owner to review this topic in the next iteration planning
51A project needs to purchase a specific piece of equipment, as stated in the project documents and approved by the project sponsor. The procurement division is questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.
What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?- ACommunicated the project charter to the procurement division
- BIncluded a procurement division member on the project team
- CReminded the project sponsor about the procurement division's reputation
- DCommunicated the project management plan to the procurement division
52A year after implementing a policy change to improve diversity and inclusion within two teams, there is increasing conflict within the company What should have been done to prevent this conflict?
- AThe organization should have introduced the concept of diversity broadly
- BThe leadership team should have worked closely with the marketing team to get insight on diversity
- COrganization-wide diversity training should have been provided to the workforce
- DThe critical departments in the organization should have been involved in this exercise
53A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?- AAllocated a dedicated handover team at early stages of the project
- BAllocated proper resources for training on BMS in the project plan
- CMade some adjustments to BMS to be more suitable for the teams
- DBrought both teams together in a joint meeting to resolve the issue
54A large and complex program in an agile environment has experienced an increase in escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process. What should be done to resolve this issue?
- AInvite the client and product owner to all planning, review, and retrospective meetings.
- BAccept the escalations and manage them so the working relationship with the client is not impacted.
- CReview and clarify roles, responsibilities, and the governance model at the next sprint review meeting.
- DInvite the product owner to attend all Scrum meetings and define the governance model and escalation path.
55A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.
What should the project manager do?- AShare project documentation in a repository with exclusive access.
- BSchedule weekly knowledge-sharing sessions with key stakeholders.
- CSend periodic emails to senior management with the latest project updates.
- DKeep project artifacts up-to-date and accessible to all stakeholders.
56A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.
What should the project manager do?- AMeet with the functional managers to align the expected frequency and results reporting for the team members.
- BProvide performance feedback to the learn members' functional managers at the end of the year.
- CAssure team members that this project is a high priority for the company and they will be evaluated accordingly.
- DRequest to be made responsible for the performance plans of those on this project team
57The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility activities that must commence immediately.
How should the project manager get these funds approved?- AWait until the next investment committee meeting to submit the request and include the delay in the schedule due to work that could not start.
- BContinue with the preliminary activities and inform the investment committee at the next monthly meeting.
- CExclude the preliminary scope from the full project scope and continue it as a new project that does not require investment committee approval.
- DSubmit the request to the project director for interim approval and include this approval for discussion at the next investment committee meeting.
58The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders This issue is putting the project schedule at risk What should the project manager do first to facilitate the approval of project requirements'?
- AReview the project charter
- BPerform a stakeholder analysis
- CIdentify the source of the disagreement
- DHold a team-building event
59A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?- ADuring the planning phase, when processes for scope definition and activity duration and sequencing will be performed
- BAs soon as possible, as project delays can be significantly avoided when a schedule is developed early
- CClose to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated
- DIn the initiation process, as it happens concurrently with the project contract and project charter creation
60The project team is planning a schedule with limited information. The team |s having issues identifying the detailed tasks and estimating task durations.
Which three techniques should the project manager use? (Choose three)- ARolling wave planning and an adaptive approach
- BRelative estimation to determine the task or deliverable sees
- CIterations and reviews to continuously keep adapting the plan
- DBottom-up estimating based on a work breakdown structure ABS)
- EGantt chart that includes milestones and deadlines
61A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.
What should the project manager do?- AInform the stakeholder that they must level their knowledge with other stakeholders.
- BUpdate the risk register with the potential impact and apprise the steering committee.
- CInform the project management office (PMO) that the team will use a predictive approach for this project.
- DAllocate time to mentor the stakeholder in the selected project approach.
62A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.
What should the project manager do in this situation?- AExplain to the management team that reporting and management dashboards are not effective agile practices
- BAsk the management team to review the endorsed agile concepts to prove that the old information s not relevant
- CHelp the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPIs)
- DRemind the management team that an agile approach empowers teams to be self- directed and therefore there is no need for reporting
63A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped How should the project manager handle the situation?
- ARemove the items no longer applicable from the backlog and present the backlog to the project team
- BContinue working on the defined scope and review the risk matrix
- CHave a discussion with the project sponsor and cancel the project
- DHave a discussion with the sponsor and recommend the project business value be reassessed
64A key team member has recently gone through some personal issues that has affected their performance. The project manager noticed that the team member's emotional situation has affected the rest of the team's performance.
How should the project manager handle this situation?- AHelp all team members learn to deal with their emotions by building a culture of empathy.
- BSeparate the key team member and replace them while they emotionally recover.
- CMeet with the team to discuss how to handle the performance problem.
- DAsk the human resources (HR) department for their support providing emotional help.
65A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.C of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage What should the project manager do?
- AInvestigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics
- BStop the project and kick off another project to apply alternative wires for the machine
- CMeet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider
- DMeet with the wire manufacturer to secure enough of the existing stock for the machine
66A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved. Which distribution list should the project manager use when sending out invitations?
- AFunctional managers, team members, and external consultants with experience in the field
- BTeam members, engineers, and weather experts
- CTeam members, consultants from outside the project with experience in the field, and the customer
- DWeather experts, functional managers, and team members
67Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings What should the project manager do?
- ASchedule a meeting for the project team to review the communications management plan.
- BTell the rest of the project team to continue discussions with the new team member
- CSend an email to the project team outlining the communications strategy.
- DMentor the new team member on the methodology the project team is using
68A company is working on a project and is using a hybrid approach to streamline a customer service process.
At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.
What should the project manager do to support the business analyst?- AAssign resources to coach the business analyst
- BAsk the business analyst to focus on their work allocation for the needs of the project
- CCreate reports to inform the business analyst about the schedule and project cost
- DProvide the business analyst with access to the financial and scheduling information
69A project manager is using a hybrid approach for project delivery. The
development team was sized, but is not yet fully resourced. The project manager is working on defining the project schedule.
What should the project manager do to address the issue of developer availability?- AOrganize a planning session with the development team and use their estimations to complete the schedule.
- BAsk the resource manager when the new contractor is available to start and change the delivery date for the project schedule.
- CAsk the sponsor to provide the desired completion date for project activities and complete the schedule.
- DUse expert judgment to estimate all of the tasks and complete the schedule in the allocated time.
70During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level What should the project manager do next with this opportunity?
- AShare this opportunity with another project
- BEstablish a contingency reserve to support the opportunity
- CFurther monitor the opportunity
- DNo more action is required
71A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?
- AProjects with the least duration
- BProjects that maximize the business value
- CProjects with maximum revenue generation
- DProjects with the least associated risks
72A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?
- ANotify the project sponsor that the budget reduction will require a schedule slip and scope reduction.
- BInform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope
- CMeet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack
- DCollaborate with the team to assess the impact of the change on the project and recommend an updated project plan
73During a meeting for product review, a key stakeholder announces that because they are receiving adequate information about the project they will not attend any further meetings. What should the project manager do?
- ALog this as an issue in the issue log and address it with the project sponsor.
- BIgnore the stakeholder as the product is almost complete.
- CExplain that the needs will be updated in the stakeholder engagement plan.
- DInform the stakeholder that changes can happen in this project.
74An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.
The team estimates the risk level as low. What should the project manager do?- ACapture all the backlog entries assessed by the development team to have evidence that risk management has been completed
- BCreate a risk register to identify, capture, review, and manage risks using a risk management process.
- CTrust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.
- DCreate a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.
75In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.
What should the project manager do?- AConsider cultural differences among stakeholders.
- BConduct an integration meeting among all stakeholders.
- CSchedule communication training for management-level stakeholders.
- DUnderstand how political aspects can affect the project.
76After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session What should the project manager do first?
- AShare the project documents and invite the key stakeholder to discuss any concerns
- BAsk the project sponsor to exert authority on the key stakeholder in order to maintain the approved timeline
- CProceed with a working session for teams that do not belong to that key stakeholder
- DInvite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy
77A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
- AMonitor all stakeholders.
- BKeep all stakeholders informed.
- CAnalyze the stakeholders.
- DEngage the stakeholders.
78A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.
What should the project manager do to ensure a successful project execution?- AInvite all resources to the project manager's location to form a cohesive team until all deliverables are completed,
- BSend emails with information about the project deliverables on the first day of the project.
- CConnect with every location and check their preferred methods of communication.
- DPlan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.
79For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product After collecting the new requirements, what should the project manager do?
- AAssess the impact of the new requirements and initiate the change request process.
- BWork with the product manager and the rest of the team to update the project backlog.
- CAssess the impact and communicate the updated product roadmap to the stakeholders.
- DFollow the change management plan to update the risk register so It accounts for the added scope.
80While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.
How should the project manager handle this situation?- ASuggest that the team member ignore the disruptive team member and focus only on the work.
- BEncourage both team members to meet as soon as possible and resolve the problem
- CMonitor the situation for a few weeks to determine if the disruptive team member's attitude changes.
- DReport the disruptive team member to the human resource (HR) department.
81A client comes to the company asking to copy a project that was executed 2 years ago in the same city, with the expectation that the new project will have the same cost and duration.
While finalizing the project management plan, the project manager realizes that the baseline costs are much higher than the original project.
What could the project manager have done to avoid this?- AVerified applicable budget inputs related to this project
- BAssigned the same project resources to this project
- CEstimated a budget for the project's quality management
- DDetermined a budget reserve for this project
82A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.
Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck
- AĐáp án

- BĐáp án ở trên
- AĐáp án
83During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule. What should the project manager do first?
- APerform an impact analysis with subject matter experts (SMEs).
- BInform the government representative about the impact of the separate project.
- CImplement a change request to increase the budget and schedule.
- DConsult and update the risk register with the project stakeholders.
84A project team is facing challenges understanding how to deliver a project's scope.
A senior subject matter expert (SME) from the organization's global office is in town for 1 week.
What should the project manager do to benefit from the SME's presence?- AAsk the SME to review the scope for alignment with the project charter.
- BOrganize a mentoring session with the team and the SME.
- CMeet with the SME to discuss the current challenges the team is facing.
- DReview the project scope statement with the SME.
85A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain.
What should the project manager do?- APlan for incremental and iterative delivery based on feedback from the marketing and sales team
- BReview and update the success criteria to ensure that the channel is not decommissioned.
- CInform the stakeholders that the list of channels to be decommissioned was approved by the CEO.
- DEscalate the objection to the steering committee and human resources (HR) as a personal intimidation incident.
86A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has doubts about the feasibility of the project.
What should the project manager do in this situation?- AValidate assumptions using appropriate tools to assess the risks.
- BRefer to the lessons learned to determine the impact on the external environment.
- CRecommend postponing the project until the uncertainty is resolved
- DHighlight the concern to the project sponsor in the next project review meeting
87An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

- AĐáp án

- BĐáp án ở trên
- AĐáp án
88A project to implement a new process is still in development. When implemented, the company will benefit by a reduction in utility costs. The project financial evaluation indicates a payback of 3 years.
What should the project manager do to expedite the project delivery?- AIncrease resources on the technical design to enable a decision to proceed as this is a quick return project.
- BIncrease the time spent on project development to improve the level of confidence to validate the financial evaluation.
- CConduct a stakeholder survey with the plant operators to establish the probability of this project reducing the cost of utilities.
- DStop any further project development and commence with the implementation as there is no need to seek further approval.
89A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months, but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities planned for that date were fulfilled.
How should the project manager inform the stakeholders of the project's progress?- AReport that the project has not fulfilled all the expected functionalities.
- BComplete the outstanding functionalities before informing the sponsor of the project progress.
- CCommunicate the benefit expectations and the action plan for the pending functionalities.
- DSend an email with the monthly project progress to all relevant stakeholders.
90An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country's unique requirements. The expected revenue for the product is the same for each country.
Which release strategy should the project manager recommend?- AA risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity
- BAn iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country
- CA quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues
- DA financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time
91One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate What interpersonal skill did the project manager use?
- ANetworking
- BEmotional intelligence
- CConflict management
- DInfluencing
92The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?
- AIncreased bum rate
- BIncreased cost
- CIncreased technical debt
- DDecreased efficiency
93A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle.
What should the project manager do in this situation?- AReject the workload back to the global team.
- BAssess the team's capacity to absorb the workload.
- CEvaluate and understand the cause of the conflict.
- DEscalate the situation to the project sponsor.
94At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?
- AProject audit
- BLessons learned
- COrganizational process assets
- DProcurement audit
95Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not delivered, the company could receive a fine from the government. What should the project manager do?
- ADiscuss the issue with the project sponsor.
- BReview the resources required for the tasks on the critical path.
- CReview and update the risk management plan.
- DAllocate resources to develop the competencies of the other team members
96During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?
- ATell the junior team member that the information is available in lessons learned
- BOffer guidance and follow up with some developmental activity for the junior team member
- CInform the junior team member that risk mitigation is not part of their work
- DRefer the junior team member to the senior team member who develops the risk mitigation strategy
97The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

- AĐáp án

- BĐáp án ở trên
- AĐáp án
98A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online, yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?- AAsk the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.
- BDirect the team to implement the benefits management plan and track achievements before the end of the project.
- CCoordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.
- DUpdate the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.
99An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager do with many tasks still open on the Kanban board?
- ADecompose the item immediately and begin work.
- BDiscuss the impact of starting the item with the team.
- CFinish the small tasks in progress before decomposing the item.
- DCommunicate the impact with the project sponsor.
100A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.
What is the next step for the project manager?- ADocument the lessons learned and implement improvements in the next sprint
- BFacilitate a daily standup with the team to track the implementation of changes
- COrganize a demonstration of the changes in the enterprise system
- DRequest that all team members think of ideas to improve processes.
Informações
- Descrição
- Công nghệ số Quiz sobre PMP exam 9, criado por Lê Hiếu em 30-07-2022.
- Autor
- Lê Hiếu
- Idioma
- English
- Visualizações
- 21
- Etiquetas
- Avaliação
- Ainda sem avaliações Avalie este quiz