Project Mngt Chapter 8

damimgd2u 60 perguntas 8.465 visualizações

Fazer o quiz

Perguntas do quiz (60)

  1. 1Direct costs are those clearly assigned to the aspect of the project that generated the cost.
    1. AT/F
    2. BAnswer: TRUE
  2. 2Material is an example of a cost that is recurring, variable and direct.
    1. AT/F
    2. BAnswer: TRUE
  3. 3An expedited cost is one that does not vary with respect to their usage.
    1. AT/F
    2. BAnswer: FALSE
  4. 4The term expedited cost has the same meaning as crashing cost in the project management milieu.
    1. AT/F
    2. BAnswer: TRUE
  5. 5An order of magnitude estimate is usually more accurate than a ballpark estimate.
    1. AT/F
    2. BAnswer: FALSE
  6. 6Comparative estimates are more accurate than definitive estimates when applied to the same project.
    1. AT/F
    2. BAnswer: TRUE
  7. 7A learning rate of 90% means that for every doubling of output, the time required by the activity falls by 10%.
    1. AT/F
    2. BAnswer: TRUE
  8. 8Function point analysis is a system for estimating the size of software projects based on the number of lines of code a typical programmer can write in a day.
    1. AT/F
    2. BAnswer: FALSE
  9. 9A common reason for cost overruns in a project is a low initial estimate of project cost.
    1. AT/F
    2. BAnswer: TRUE
  10. 10There is a tendency for different departments or functions to compete for scarce resources in a zero-sum game when bottom-up budgeting is used to develop a project budget.
    1. AT/F
    2. BAnswer: FALSE

Informações

Descrição
Project Mngt Chapter 8 Test Questions
Idioma
English
Visualizações
8.465
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?