Chapter 1: Starting up a Project

Lynsey Dalgleish Prince 2 Professional Inglês 10 slides

Slides do conjunto (10)

  1. Starting up a Project

    • Activities completed before the project starts:
    • Appoint the exec and Project Manager
    • Capture previous lessons
    • Design and appoint the Project Management Team
    • Prepare the outline business case
    • Select project approach and create project brief
    • Plan the Initiation Stage
    • 2. Capture Previous Lessons
    • Project Manager captures useful experiences and reviews Lesson Log/Reports from previous projects
    • Project Manager activity:
    • Create Lessons Log which the Project Manager refers to throughout project life
    • 3. Design & Appoint the Project Management Team
    • Exec and Project Manager creates the structure which covers 3 perspectives:
    • Business/User/Supplier
    • Senior User: represents the end user
    • Senior Supplier: controls resources that creates outputs
    • Project Assurance: monitors project activities
    • Team Manager: manages the teams involved
  2. Starting up a Project

    • 4. Prepare the Outline Business Case
    • Exec creates outline business case and is approved by CPM
    • Project Manager creates the Project Product Description
    • Business Case:
    • Sets out justification
    • Details cost v benefit
    • Project funding
    • Project Product Description
    • Products that will deliver benefits
    • Customer quality expectations
    • PM/SU set measurable expectations - Acceptance Criteria
    • 5. Select the Project Approach & Assemble Brief
    • Project Approach:
    • Created by Project Manager
    • How product will be delivered
    • May look at the technical approach
    • Species any supplier, org or industry standards
    • Project Brief:
    • Project definition/approach
    • Outline business case
    • Project Management Team structure
    • Role descriptions
    • 6. Plan the Initiation Stage
    • Once the project is authorised initiation begins
    • Project Manager creates detailed stage plan
    • Project Board reviews to decide whether to authorise
  3. Initiating a Project (Project Begins)

    • Authorising Initiation
    • Project Manager sends request to Project Board who considers request (Directing)
    • Project Board uses project brief to make decision
    • Project Assurance may review the material to test validity
    • If approved:
    • Exec authorises Project Manager to proceed with Initiation Stage
    • Stakeholders are informed the project is proceeding
    • Main focus is to plan the project
    • Main output is the Project Initiation Documentation which is used to by the Project Board to authorise the next stage
    • "to establish solid foundations for the project, enabling the organisation to understand the work that needs to be done to deliver the projects products before committing to significant spend"
    • Project Initiation Documentation contains:
    • Risk Management Strategy
    • Quality Management Strategy
    • Configuration Management Strategy
    • Communication Management Strategy
    • Project controls
    • Project Plan
    • Refined business case
  4. The Strategies

    • There are 4 strategies:
    • Risk Management Strategy
    • Quality Management Strategy
    • Configuration Management Strategy
    • Communication Management Strategy
    • Strategies show the Project Management Team how to:
    • manage risks and quality
    • manage change
    • track projects products
    • communicate with stakeholders
    • 6 components to each strategy:
    • Procedure: activities to deliver products
    • Timing: when activities need to happen
    • Roles & Responsibilities: who needs to do what
    • Tools & Techniques: how it will be done
    • Reporting: what reports, when & to who
    • Records: what needs to be recorded
  5. Preparing the Strategies

    • 1. Risk Management Strategy
    • Project Manager creates to show how the project should manage risk & reduce likelihood of threats materialising
    • Risks can be opportunities & strategy looks at how to leverage these
    • CPM sets RISK TOLERANCE levels and how risks will be assessed (Probability, Impact, Likelihood)
    • Specifies any dedicated budget
    • Project Manager creates RISK REGISTER and any issues in the DAILY LOG are transferred over
    • 2. Quality Management Strategy
    • Project Manager creates using Project Product Description in Starting up a Project
    • Shows how the Project Management Team will ensure the end product(s) are suitable for the intended purpose
    • Contains high level specifications for products
    • Project Manager creates QUALITY REGISTER to record quality checks to be carried out and results
    • 3. Configuration Management Strategy
    • Project Manager creates to show how the Project Management Team will manage product(s)
    • Covers all parts that make up final product and aims to keep track of all component parts
    • Focuses on 3 areas:
    • IDENTIFYING: all components to create products
    • TRACKING: track all components throughout project
    • PROTECTING: change control processes
    • 4. Communication Management Strategy
    • Project Manager creates last and shows how the project will manage communications between stakeholders - internal/external
    • Takes into account reports identified in preceding strategies
    • Stakeholder analysis reviewed/completed
  6. Preparing the Strategies

    • 5. Set up Project Controls
    • Project Manager creates to ensure the project is heading in the right direction
    • Controls are defined in the strategies
    • Monitoring is the most important aspect of control
    • 6. Create Project Plan
    • Project Manager creates to show how major products will be delivered
    • Covers the time directly after the Initiation Stage to the end of the project, based on work completed during Starting up a Project
    • Project brief specifies important delivery dates and project approach
    • Includes Product Description for major deliverables
    • 7. Refine the Business Case
    • Add details to the business case with estimates on time. resources and costs
    • Project Manager creates Benefits Review Plan which specifies how achievements will be measured
    • 8. Assemble Project Initiation Documentation
    • Project Manager creates using documents created to date
    • Authorising the Project & Stage
    • Project Board reviews the Project Initiation Documentation and decides whether to authorise the project
    • Process moves to Directing a Project
    • Authorise the project
    • Authorise the stage plan
  7. Themes Used to Start a Project

    • 1. Business Case Theme
    • How to ensure the project is viable and achievable throughout the project lifecycle
    • Business case structure and responsibilities
    • Project mandate is updated
    • Starting up a Project:
    • CPM appoints the exec who represents business viewpoint and created business case
    • Initiating a Project:
    • Project Manager refines outline business case and creates Benefit Review Plan
    • Directing a Project:
    • Project Board reviews business case and authorises initiation stage, project and first stage
    • 2. Organisation Theme
    • Sets out Project Management Team structure with associated Roles & Responsibilities
    • Starting up a Project:
    • CPM - Exec - Project Manager - Project Management Team are appointed
    • Initiating a Project:
    • Project Manager carries out stakeholder analysis
    • Output is included in Communication Management Strategy
  8. Themes Used to Start a Project

    • 3. Quality Theme
    • How the project will be managed to ensure it creates the right products
    • How to specify what products to build, how to check quality and who will be involved
    • Starting up a Project
    • Project Manager creates Project Product Description which contains quality expectations and acceptance criteria
    • Initiating a Project
    • Project Manager creates Quality Management Strategy, Project Plan and Product Descriptions
    • 4. Plans Theme
    • 3 types of plans including:
    • Project Plan - Stage Plan - Team Plan
    • Starting up a Project
    • Stage plan for initiation stage created and added to Project Initiation Documentation
    • Initiating a Project
    • Project plan is created for the project
    • Managing a Stage Boundary
    • Occurs at the end of initiation and first stage plan is created
  9. Themes Used to Start a Project

    • 5. Risk Theme
    • Identifies, assesses & controls potential threats & opportunities
    • Starting up a Project
    • Project Manager logs issues in the Daily Log
    • Exec summarises the risk situation in business case
    • Initiating a Project
    • Project Manager creates Risk Management Strategy which shows how risk will be managed
    • Project Manager creates the Risk Register
    • Project Manager summarises risk position in detailed business case
    • 6. Progress Theme
    • How the project will be controlled and kept on track
    • How stages will be used (Manage by Stages)
    • Sets out Tolerances and Constraints (Manage by Exceptions)
    • Initiating a Project
    • Project Manager creates Project Controls and adds to Project Initiation Documentation
    • Defines how the project will be split into stages
    • Specifies decision making responsibilities
    • Sets tolerances and constraints
  10. Using Principles to Start a Project

    • 1. Continued Business Justification
    • Implemented through business case
    • Exec represents business interest
    • Project justification throughout project (Directing a Project)
    • 2. Learn From Experience
    • Implemented during Starting up a Project by creating the Lessons Log which documents experiences in the project
    • 3. Defined Roles & Responsibilities
    • Implemented through the Project Management Team during Starting up a Project
    • 4. Manage by Stages
    • Implemented by creating a project plan divided into management stages - authorised one at a time
    • 5. Manage by Exception
    • Implemented by Project Board by defining tolerances
    • CPM/PM also sets defined tolerance and constraints
    • 6. Focus on Products
    • Implemented by specifying overall output of the project in Project Product Description
    • specifies major products and creates Quality Management Strategy
    • 7. Tailor to Environment
    • Implemented in Project Initiation Documentation and shows how it will be tailored to the project

Informações

Descrição
Professional Prince 2 (Prince 2 Study Cards) Slides sobre Chapter 1: Starting up a Project , criado por Lynsey Dalgleish em 02-07-2016.
Visualizações
3
Avaliação

Mais sobre PRINCE2 Processes

Fale Conosco

Sobre o que é sua mensagem?

O que a gente deve adicionar?