1Earned Value Management(EVM) is commonly used to :
- Aa. Analysis of the value of the equipment that has been installed as of the status date.
- Bb. Analysis of the sum of the labor costs, which have been incurred on the project to date.
- Cc. A method of project performance measurement.
- Dd. A method of measuring the amount of money that has been spent to date.
2An estimating technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines of code in software development) is known as:
- Aa. Parametric Estimating
- Bb. Analogous Estimating
- Cc. Bottom-up Estimating
- Dd. Historical Analysis
3Contingency Reserves are estimated costs to be used at the discretion of the project manager to deal with:?
- Aa. Inadequacies in the original estimate
- Bb. Anticipated but not certain events
- Cc. Unanticipated events
- Dd. Anticipated and certain events
4Activity cost estimates are used as an input into which process??
- Aa. Estimate Costs
- Bb. Determine Budget
- Cc. Cost Analysis
- Dd. Control Costs
5As a project manager, your BEST use of the project cost baseline would be to:?
- Aa. Measure and monitor cost performance on the project.
- Bb. Track approved changes.
- Cc. Calculate team performance bonuses.
- Dd. Measure and report on variable project costs.
6An activity cost estimate includes all of the following resource categories EXCEPT:?
- Aa. Labor
- Bb. Materials
- Cc. Equipment
- Dd. Time shortages.
7All of the following are true about estimate costs, EXCEPT:?
- Aa. Are generally expressed in units of currency (dollars, euro, yen, etc.), although in some instances other units of measure, such as staff hours or staff days ares used.
- Bb. The costs are estimated for all resources that will be charged to the project.
- Cc. Information in the risk register should not be used to adjust cost estimates.
- Dd. Cost estimates are quantitative assessments of the likely costs for resources required to complete project activities.
8The Project Manager is in the process of estimate costs. What will he get?
- Aa. The budget of the project
- Bb. Basis of estimates, cost estimates and project documents updates
- Cc. Cost estimates of the work packages
- Dd. Entire costs of the deliverables
9Analogous estimating:?
- Aa. Integrated bottom-up estimating techniques with relevant statistical relationship to estimate the cost of the current project
- Bb. Relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project.
- Cc. Is used most frequently in the later stages of a project.
- Dd. Summarizes estimates for individual work packages to estimate the cost of the current project.
10All of the following are required to establish cost baseline EXCEPT:?
- Aa. Plan Resources of everything xxxxxx
- Bb. Control Cost
- Cc. Estimate Cost
- Dd. Determine Budget