  1. 1Which of the following statements about contract termination is FALSE?

    1. AA Early terminations are handled in the Close Project or Phase process.
    2. BB Contract termination may result from mutual agreement to terminate the contract.
    3. CC Termination conditions should be documented in the contract.
    4. DD Contract termination may result from default of one party.
  2. 2Which of these statements about contracts is FALSE?
    1. AA A contract is a mutually binding legal agreement.
    2. BB A contract can include change request handling.
    3. CC Contracts are used only for complex procurements.
    4. DD A contract is a legal relationship subject to remedy in the courts.
  3. 3Greg needs a good understanding of planned work to determine project purchases. What document will be the most helpful?

    1. AA WBS
    2. BB WBS dictionary
    3. CC Project scope statement
    4. DD Procurement management plan
  4. 4An independent estimate used when conducting procurements is sometimes used to:
    1. AA Establish a budget estimate.
    2. BB Serve as a benchmark of proposed responses.
    3. CC Build an order of magnitude estimate.
    4. DD Confuse prospective sellers.
  5. 5Which of the following is an objective of the Control Procurements process?

    1. AA Set limitations of liability
    2. BB Assess and invoke penalties
    3. CC Monitor contract performance
    4. DD Issue individual performance reports
  6. 6Which of the following statements about selecting a seller is TRUE?

    1. AA Project teams should select the lowest cost seller.
    2. BB The selection process should produce one seller for each product.
    3. CC Selection criteria can be limited to price if the item is available from multiple sellers.
    4. DD The project manager selects the sellers.
  7. 7What is a structured review of the seller's progress to deliver project scope and quality, within cost and on schedule?
    1. AA Inspection
    2. BB Procurement performance review
    3. CC Walkthrough
    4. DD Audit
  8. 8Which of the following terms indicates that the buyer will evaluate the response based on technical factors?

    1. AA Bid
    2. BB Quote
    3. CC Tender
    4. DD Proposal
  9. 9Inputs to Conduct Procurements include all of the following EXCEPT:


    1. AA Make-or-buy decisions.
    2. BB Source selection criteria.
    3. CC Procurement documents.
    4. DD Selected sellers list.
  10. 10The Project Procurement Management Knowledge Area includes all of the following processes EXCEPT:
    1. AA Plan Procurement Management.
    2. BB Control Procurements.
    3. CC Identify Risks.
    4. DD Conduct Procurements.

Informationen

Beschreibung
PMP Preparación Certificación PMP Quiz am DGAP04 Adquisiciones, erstellt von Ruben Lopez am 07/04/2016.
Sprache
Español
Aufrufe
18
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck