1Which of the following statements about contract termination is FALSE?
- AA Early terminations are handled in the Close Project or Phase process.
- BB Contract termination may result from mutual agreement to terminate the contract.
- CC Termination conditions should be documented in the contract.
- DD Contract termination may result from default of one party.
2Which of these statements about contracts is FALSE?
- AA A contract is a mutually binding legal agreement.
- BB A contract can include change request handling.
- CC Contracts are used only for complex procurements.
- DD A contract is a legal relationship subject to remedy in the courts.
3Greg needs a good understanding of planned work to determine project purchases. What document will be the most helpful?
- AA WBS
- BB WBS dictionary
- CC Project scope statement
- DD Procurement management plan
4An independent estimate used when conducting procurements is sometimes used to:
- AA Establish a budget estimate.
- BB Serve as a benchmark of proposed responses.
- CC Build an order of magnitude estimate.
- DD Confuse prospective sellers.
5Which of the following is an objective of the Control Procurements process?
- AA Set limitations of liability
- BB Assess and invoke penalties
- CC Monitor contract performance
- DD Issue individual performance reports
6Which of the following statements about selecting a seller is TRUE?
- AA Project teams should select the lowest cost seller.
- BB The selection process should produce one seller for each product.
- CC Selection criteria can be limited to price if the item is available from multiple sellers.
- DD The project manager selects the sellers.
7What is a structured review of the seller's progress to deliver project scope and quality, within cost and on schedule?
- AA Inspection
- BB Procurement performance review
- CC Walkthrough
- DD Audit
8Which of the following terms indicates that the buyer will evaluate the response based on technical factors?
- AA Bid
- BB Quote
- CC Tender
- DD Proposal
9Inputs to Conduct Procurements include all of the following EXCEPT:
- AA Make-or-buy decisions.
- BB Source selection criteria.
- CC Procurement documents.
- DD Selected sellers list.
10The Project Procurement Management Knowledge Area includes all of the following processes EXCEPT:
- AA Plan Procurement Management.
- BB Control Procurements.
- CC Identify Risks.
- DD Conduct Procurements.
11Outputs of the Conduct Procurements process do NOT include:
- AA Selected sellers.
- BB Qualified sellers.
- CC Agreements
- DD Resource calendar.
12Where can Baird look to find a qualified sellers list?
- AA Yellow pages
- BB Project management plan
- CC Procurement management plan
- DD Organizational process assets
13Which of the following is a TRUE statement?
- AA T&M contracts are for a fixed amount
- BB T&M contracts can be open-ended
- CC T&M contracts do not reimburse costs
- DD T&M contracts are unilateral
14Which of the following is NOT an organizational process assets update associated with the Close Procurement process?
- AA Procurement management plan
- BB Procurement file as a complete set of indexed contract documentation including the closed contract
- CC Deliverable acceptance
- DD Lessons learned documentation
15Which of the following is NOT usually included in a procurement document?
- AA Description of need
- BB Response instructions
- CC Price
- DD Preferred contract type
16Company policy requires you to advertise contract needs in your local paper. How does this benefit your project?
- AA It can expand the list of potential sellers
- BB It speeds up the source selection process
- CC It makes it easier to contact vendors
- DD It is always a legal requirement
17CPFF is the abbreviation for:
- AA Cost Plus Fixed Fund.
- BB Contract Plus Fixed Fee.
- CC Cost Plus Floating Fee.
- DD Cost Plus Fixed Fee.
18Which of the following is NOT a tool or technique used with the Close Procurements process?
- AA Procurement audits
- BB Performance reporting
- CC Records management system
- DD Procurement negotiations
19Your sponsor wants to know if your contractor has finished a set of deliverables. Where will you find that information?
- AA Procurement management plan
- BB Performance reports
- CC Approved change requests
- DD Contract
20Which of the following is NOT an input to the Conduct Procurements process?
- AA Source selection criteria
- BB Seller proposals
- CC Procurement contract award
- DD Procurement documents
Information
- Description
- PMP Preparación Certificación PMP Quiz on DGAP04 Adquisiciones, created by Ruben Lopez on 07/04/2016.
- Author
- Ruben Lopez
- Language
- Español
- Views
- 18
- Tags
- Rating
- No ratings yet Rate this quiz