- 1In what stage would the client have the greatest influence on software production?Investigation and analysis BUT the client is heavily involved at every stage
- 2Explain 3 reasons why test plans are importantTest all possible routes through a system
Allow a third party to test the system
Ensure all parts of the system are tested - 3Explain the role of the project managerEnsure all project deadlines are met
ensure the project is sticking to budget
oversee all parts of the project
make gantt charts and other planning devices - 4What is the purpose of the evaluation stage?See how well the project has met its goal
get feedback from the customer
discuss improvement and changes to the team - 5Explain the role of the systems analyst in the investigation and analysis stageinvestigation techniques
interfaces with the client
writes the requirement specification