NDC Basement Construction (Top Down)

Karten in diesem Stapel (9)
- 1—- Create retaining wall with ring beam - diaphragm, secant, continuous or sheet pile etc.
- bore piled to foundation depth
- cast concrete to foundation level with reinforcement cage
- 2—- Insert steel plunge columns in to concrete foundation

- 3—- Excavate to below ground floor level

- 4—- Cast ground floor slab (also provides lateral support to retaining wall)

- 5—- Excavate to second level
- Concurrently superstructure can be constructed
- 6—- First basement level slab constructed

- 7—- Excavate and cast floors repeating

- 8—- Cast concrete around plunge columns and inside face of retaining wall with reinforced concrete

- 9BOTTOM UP (JUST IN CASE)• Retaining wall – diaphragm walling or piling
• Capping beam
• Excavation for the basement to required depth (or formation level)
• Augured piles or other forms of foundation with holding down bolts in pile caps
• Basement floor slab
• Waterproof floor and retaining wall
• Establish grids for structural elements (column and shear wall) from the basement level
• Basement walling and tanking
• Establish steel column on the main support/bases (pile caps/pad/concrete mat on the basement floor) depending on the foundation type