RIBA Plan of Work
Karten in diesem Stapel (8)
- 1Stage 0 Strategic DefinitionIdentify the clients BUSINESS CASE and STRATEGIC BRIEF and other core project requirements
- 2Stage 1 Preparation & BriefDevelop PROJECT OBJECTIVES inc QUANTITY OBJECTIVES and PROJECT OUTCOMES, SUSTAINABLE ASPIRATIONS PROJECT BUDGET, others may be to develop INITIAL PROJECT BRIEF, FEASIBILITY STUDY and review SITE INFORMATION
- 3Stage 2 Concept DesignPrepare CONCEPT DESIGN inc outline proposals for structural design, building services, outline spec, preliminary COST INFORMATION, along with PROJECT STRATEGIES, in accordance with DESIGN PROGRAMME. Agree and issue FINAL PROJECT BRIEF.
- 4Stage 3 Developed DesignPrepare DEVELOPED DESIGN, inc coordinated and updated proposals for structural design, building services systems, outline specs, COST INFORMATION, and PROJECT STRATEGY in accordance with DESIGN PROGRAMME.
- 5Stage 4 Technical DesignPrepare TECHNICAL DESIGN in accordance with DESIGN RESPONSIBILITY MATRIX and PROJECT STRATEGY, to inc all architectural, structural and building services information, specialist subcontractor design and specs, in accordance with DESIGN PROGAMME
- 6Stage 5 ConstructionOffsite manufacturing and onsite CONSTRUCTION in accordance with CONSTRUCTION PROGRAMME and resolution of DESIGN QUERIES from site as they arise.
- 7Stage 6 Handover and CloseoutHandover the building and conclusion of the BUILDING CONTRACT
- 8Stage 7 In UseUnderline IN USE services in accordance with SCHEDULE OF SERVICES.
Informationen
- Beschreibung
- chartership T22 Design Economics and Cost Planning Karteikarten am RIBA Plan of Work, erstellt von Fred Fulford am 29/03/2015.
- Erstellt von
- Fred Fulford
- Aufrufe
- 21
- Bewertung
Mehr zu Construction Project Phases