Task 4: Plan Schedule MgMt

asem.latif Englisch 14 Karten

Karten in diesem Stapel (14)

  1. 1TimeIs a period for completing the project
  2. 2Plan Schedule MgmtProcess requires establishing procedures and documenting the methods of tracking, planning, developing, executing and controlling the project schedule
    input: PC, PMP, EEF, OPA
    Tools: Expert Judgement, Analystical tech, Meetings
  3. 3Defining ActivitiesActivity Definition is providing deliverables at the lowest level of (WBS) which is work package
    Inputs: SMP, Scope Baseline, EEF, OPA. EEF are PMIS and scheduling software. OPA are historical info and policies
    Tools: Decomposition, Expert Judgement, Rolling wave plan
    Output: activity list, Activity attributes and milestones
  4. 4Control Accountis planning component in which scope, budget, cost are integrated at the management control point and compared to the EV (earned value)
  5. 5Planning PackageIs the package above a work package but below control account planning known work that does nto have detail.
  6. 6Output of Definig ActivitiesActivitiy List
    Activity Attributes
    Milestone List
    Mandatory Milestones and Optional Milestones
  7. 7Sequencing ActivitiesProcess of identifying and documenting dependencies among scheduling activities
    input: SMP, Act list, act attribute, milestone list, scope statement, EEF, OPA
    tools: PDM, depencies relationship, lead and lags
    output: Schedule network diagram, project document updates
  8. 8Precedence relationshipsFinish Start - Act b cannot start until act a finishes
    Start Finish Act b cannot finish before Act A begins
    Start start Act B cannot start before Act A starts
    finish finish Act B cannot finish before Act A finishes
  9. 9DependenciesMandatory: inherent nature of the work
    discretionary: knowledge of best practices
    external: based on establishing sequence of acts
  10. 10Lagdelay in successor activity
  11. 11LeadTime to begin work beforehand acceleration of successor activities
  12. 12Estimate Activities ResourceIs process of estimating the resources required for the project
    input: SMP, AL, AA, Risk Reg. Resource Calendar, Act Cost Estimate, EEF, OPA
    Tools: Expert Judgement, Alternate Anaylsis, Published Estimating data, Bottom up estimating, Proj MS
    Output: Resource Req, RBS, Doc update
  13. 13Activitiy DurationIs the process of estimating the duration of a work period from start to finish
    input: SMP, AL, AA, RR, RC, RBS, Resource Require, Scope Statement, EEF, OPA
    Tools: Expert Judgement, Analgous (historical), Parametric (Resource quantity x Productivity rate), 3-point (likely, worst, best case avg), Group decision making (Delphi or nominal group technique), Reserve Analysis (contingency and reserve is percentage)
    Output: Activity duration estimate, doc update
  14. 14Develop Scheduleinput: SMP, AL, AA, RR, RBS, Act Duration E, Resource Staff assignment, SCope S,EEF,OPA,
    Tools: CPM, SC, CCM, Modelin tech, resource optimaitzation tech, Scheudle Network Diagram
    Ouitput: Schedule Basleine, ,Proj Schedule, Scheulde data, Project Calendar, PMP, Doc Up

Informationen

Beschreibung
Karteikarten am Task 4: Plan Schedule MgMt, erstellt von asem.latif am 08/09/2015.
Erstellt von
asem.latif
Aufrufe
0
Bewertung

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck