- 1avoiding loss of beding sand-weeping holes placed at regular intervals through pored in place or precast concrete curbs
-place cloth over joints or weep holes to prevent sand from entering - 2cleaning and sealing joint stabalizationloss of joint sand can occur high slope high wind areas with high surface run off
-can be resolved with joint stablizers - 3step 1locate area to be remediated fixed
-mark shoulder
remove pavers 0.8ft behind excavation line - 4step 2remove first paver with paver extractor
- 5step 1-5remove remaining pavers
remove bedding sand
excavate base material and soil, repair damaged base or utility as needed - 6step 6compact soil base
compact base material
compact base 2-4 inches 50-100mm
lifts to required density - 7step7replace bedding sand layer
screed with notched screed board achieving a crown, crown compensates for minor settling - 8step 8reinstate pavers
adjust joint spacing and alignment - 9step 9compact reinstated pavers
first compaction occurs After pavers are placed with no joint sand at least 2 passes - 10step 10place and spread joint sand
- 11step 11vibrate till joints are filled with sand
second pass works sand into joints sweep left over sand away - 12first interstate highway segmental paversromans empire
2000 years ago - 13seg clay brick pavement1000 ad
- 14clay pavers used in streets of north America1800s
- 15concrete pavers developed in the Netherlands1950s
- 16first paver manufacturing machine in north America1973
- 17icpi components1.compact soil subgrade
2.geotextile as required by design
3.compacted aggregate
4.beding sand 1 inch 25 mm
5.concrete pavers with sand filled joints - 18factors effecting interlock1 paver thickness
2 laying pattern
3 consistent joint widths
4 stationary edge restraints
5 paver shape and size
6 crown in cross section - 193 types of interlockhorizontal
vertical
rotational - 20load distributionslight movement in soil and from seasonal changes in moisture does not change the way the load is distributed
- 21the 4 point system OSHA program components1.managment commitment and employee involvement
2.hazrd analysis
3.hazrd prevention and control
4.traning for employees supervisors and managers - 22hazards on a hardscape instalation project-heat
-eyes
-impact
-vibration
hearing loss
-knee-silica - 23hierarchy of controls1physically remove hazard
2.replace the hazard
3.isolate people from the hazard
4.change the way people work
5.protect the worker with PPE - 24Controls 1.Engenering 2.Administrative 3.PPE1.isolate people from the hazard
2.Change the way people work
3.protect the person with PPE - 25Tool Box talk include?-work practices
-machinery
-tools
-equipment
-materials
-attitudes - 26job jacket contents?-proposal
-drawing
-maps
job sheets
daily time sheets
job quantity sheets - 27perimeter stakes always ? outside excavation ..12 inches
- 28Flow of materials1.plan flow before job starts
2.base or bedding sand distributed by loader or wheelbarrow
3.cubes of delivery of pavers timed best as possible
4.move pavers on site as little as possible
5.on a slope, start at the bottom and work uphill to maintain consistent joint widths - 29soil characteristics and compaction1gradation
2soil classification
3soil compaction
-measurement
-methods equipment
-geotextiles - 30field identification of soils1.patty test
2.shake test
3.snake test - 31patty shake snake1.evaluates water holding capacity of soil
2.tests for reaction to shaking
3.tests for thread toughness of soil - 32soil compactionincrease density and load-bearing capacity of soil
3 factors effect extent of soil compaction capability's
soil type/moisture in soil/type and amount of compacting - 33measuring soil compaction1.squeeze handful of soil to the size of a tennis ball.
2. drop the ball about 1ft 0.3 meter from the ground on to a hard surface
3. if the ball breaks into a small amount of uniform fragments, it is close to optimum moisture - 34soil compaction methods and equipment1. rammer
2.reversible plate compactor
3.forward plate compactor
4.static roller - 35geotextiles do what?-they separate the base from the soil
-effective over clay and silts
-overlap by a minimum of 12 inches, 300mm
-used for overlays over concrete or asphalt
-do not increase the strength of the base
-does not change base thickness - 36base materials-gradation
-thickness
-base compaction
-base installation - 37gradation-blended crushed stone most common
-possible alternatives
recycled concrete(pedestrian or driveway only)
-existing asphalt or concrete
-cement treated or asphalt treated base
-overlay on existing asphalt or concrete - 38base thicknesspedestrian: minimum of 4 inches(100mm)
-residential driveway, 6 inches 150mm
-use thicker bases in colder climate on wet or weak/wet soils - 39base installation best practicesbase material conforms to local DOT specifications for road bases under asphalt
-moisture content optimized
1.in pile
2.in place
ensure integrity of geotextile with first layer - 40base installation best practicesinstall in lifts 2-4 inches (50 to 100mm) thick
-individual base lift and final overall thickness tolerances (3/4 to 1/2) - 41base installation best practices-use lute rake to optimize loader operations
- use flat side of lute rake to level aggregate
- set string lines above top of lift=thickness of rake. - 42base installation best practices-overlap passes with compactor.
-reversible plate compactor with at least 7,000 lbf (31 Kn) or vibratory roller is recommended.
-compact alternate passes perpendicular to previous pass.
-onsite indicators
for compaction.
-compactor crabbing
spike test. - 43role of edge Restraints-Hold pavers tightly together
-Enable consistent interlock
- help prevent horizontal movement from
1.braking
2.accelerating
3.minor settlement. - 44types of edge restraints-poured concrete and walls
-precast concrete and cut stone
- partial depth precast concrete
- aluminum and steel
-plastic
-troweled and submerged concrete. - 45sand functionsbedding
drainage
interlock
structural support - 46There important bedding sand propertiesmoisture content
-needs to be slightly moist to allow of proper compaction, but not too wet.
hardness
- needs to be very hard so that it is not broken down by traffic.
test hardness using a pocket knife
Angularity - 47bedding sand installation-stock piles close to laying face
-dig into pile from mid-height
screed rails 10 to 12 feet apart
aluminum screed rails preferd - 48installation tips,- only screed area of sand/chip for the area that will be paved or layed each day
-cover any exposed chip or sand that is screeded over night with a tarp
-avoid disturbing the screed area
- - 49joint sand-dry joint sand
-bagged or sun-dried
-bedding sand can be used for joint sand
-one sand reduces handling on another site
-concrete sand requires additional spreading and compaction into the joints - 50ratio-length/widthplan ratios between 2:1 and 3:1 provide best interlocking patterns
- 51aspect ratio for different applicationslegth of paver 12inch or 300mm by 2.375 thick.
aspect ratio=12 divide by 2.375
=5:1 - 52runner pattern1 parquet pattern2 herringbone pattern31soldier with inlay with sailor border
2one way 2 another
you no and then 45 as well - 53compacting paversuse a minimum 5,000lb force 22kn vibratory plate compactor
- 54compacting paversstart at edge of pavment and compact perimeter first
-overlap rows
-compact second time in opposite direction
-do not compact 6ft or 2m within unrestrained edge
-mark and remove broken pavers
-joint sand must be dry - 55—
Informationen
- Beschreibung
- horticulture Karteikarten am icpi study stuff, erstellt von joey steele am 05/04/2024.
- Erstellt von
- joey steele
- Aufrufe
- 0
- Verlauf
-
- Erstellt von Joseph Steele · 3 Apr 2024
- Kopiert von joey steele · 5 Apr 2024
- Kopiert von joey steele · 5 Apr 2024
- Bewertung