  1. 1What is Risk?Any uncertain event or condition that might affect your project
  2. 2How you deal with risk?AVOID
    MITIGATE
    TRANSFER
    ACCEPT
  3. 3Explain Avoid?Prevent the risk from ever happening
  4. 4Explain MitigateTake some sort of action that will cause it to do as little damage to your project as possible.
  5. 5Explain TransferPay someone else to accept your risk, most common way is insurance.
  6. 6When can risk management be considered Cost - Effective?Only when the cost of risk management is considerably less than the loss incurred if the risk happens.
  7. 7Risk Management: -Risk Assessment -Risk ControlRisk Assessment:
    -Risk identification
    -Risk analysis
    -Risk prioritization
    Risk control:
    -Risk management planning
    -Risk resolution
    -Risk monitoring
  8. 8What is Risk Identification?-Any condition, situation or event that would jeopardize the project is a risk
    -It is to envision what can go wrong
    -Methods are checklist of possible risk,surveys, meetings, reviews of the plan and product
  9. 9Techniques for Risk IdentificationBrainstorming
    Checklist
    Questionnaires
    History data (Lessons learned, data)
    Critical path analysis
    Goal review
  10. 10Risk Identification GuidelinesStart with open brainstorming
    Perform focused brainstorming
    Use checklist to ensure sufficient coverage
  11. 11What is Risk Analysis?Estimate:
    Probability
    impact
    Severity
    of the problem.
  12. 12What is Risk PrioritizationDetermining where the extra effort of risk management should be spent to get the maximum benefit.
    - The chance of a risk occurring
    -The effect of the risk
  13. 13Risk ProbabilityThe likelihood that the event will occur.
    Measured from 0 (impossible) to 1
    (certainty).
  14. 14Risk ImpactThe loss associated with the event (time, quality, money, control, understanding,...)
    Measured by level of consequences from 0 to 10
  15. 15Risk Exposure= Risk probability x Risk impact
    > ( 0 to 1) x (Cost) = Risk Exposure in money
  16. 16Risk Control and what is a contingency plan?To which degree we can change the outcome.
    Is a plan of action that are shelved for possible use later.
  17. 17when are Contingency Plan implemented?The anticipated problem occurs, or becomes imminent.
    The contingency plan requires advance preparation
  18. 18Risk Monitoring and TrackingSince Risk analysis is perform during planning phase and risk are based on events then we must monitor and track these risk for changing events.
  19. 19BOEHM's TOP TEN RISK1.Personnel shortfalls
    2.Unrealistic schedules and budgets
    3. Developing the wrong functions
    4.Developing the wrong user interfaces
    5. Gold-Plating
    6. Continuing stream of requirements changes
    7. Shortfalls in externally-performed tasks
    8. Shortfalls in externally- furnished components
    9.Real-time performance shortfalls
    10. Straining computer science capabilities
  20. 20Biggest RiskNot knowing what the risks are!
  21. 21UML Unified Modeling Language Use Casesits a way of communication with u, ur team and ur customer.
    Better understanding of the system across the board of teams.
  22. 22what is a Use CasesA description of sequences of actions performed by a given system to produce a result for an actor.
    Specify the expected behavior [what] not the [how].
  23. 23what are actors and Uses cases?actor: represent roles, that is, a type of user of the system
    Use cases: represent a sequence of interaction for a type of funcionality
  24. 24ActorsThis external entity communicates with the system. (user, external system, physical environment)
    They have unique names and are situated outside of the system boundary
  25. 25Use Case associationExtends, includes, Generalization
  26. 26IncludeWhen a use case A performs all the behavior described in use case B
  27. 27ExtendsWhen a use case A can be executed without the use case extension.
  28. 28GeneralizationUsing Parent and Child Use cases where the child inherits from the parent behavior and can also add or override some behavior.
  29. 29Use Cases ModelName:
    Actor:
    Entry Conditions:
    Event Flow: Use indentation(system and actor) and enumerate.
    Exit Conditions:
    Exceptions:
    Special Requierments
  30. 30—

Informationen

Beschreibung
Karteikarten am Test 3, erstellt von Javier Colon am 08/11/2015.
Erstellt von
Javier Colon
Aufrufe
0
Bewertung

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck